Activity % Complete Based on Activity Steps - Primavera P6 SETTINGS Explained
ฝัง
- เผยแพร่เมื่อ 14 ก.ค. 2024
- Today we're looking at a project level setting that relates to steps.
"Activity % complete based on activity steps". What does that setting do? I'm going to explain it.
Learn the Fundamentals of Primavera P6:
www.planacademy.com/primavera...
Take your skills to the next level and check out our Advanced Course:
www.planacademy.com/course-ad...
In this new beginner series, Michael breaks down various Primavera P6 Settings, explaining what they are, how they work and giving his recommendation on which preferences you should use.
Need to learn P6? Check out the best Advanced P6 Training Available online:
www.planacademy.com/
You are a real teacher, whenever I watch your training session I admire your skills and your generous in sharing the experiences.I really appreciate it
Much appreciated, Kourosh! Glad I could help!
Thank u
No problem, Yaser!
Thanks Michael 👍
No problem!
I have an activity with labor units & labor costs that is divided into 4 steps with 25% weight. When I put the progress based on the first step (for example) 25%, my labor units and cost don't change and still are the same.
Is there any setting that I should have adjusted?
Good explain. Mohammed (Oracle primavera certified specialist )
Some people call activity steps "rules of credit".