ไม่สามารถเล่นวิดีโอนี้
ขออภัยในความไม่สะดวก

How To Do Rolling Wave Planning in Primavera P6

แชร์
ฝัง
  • เผยแพร่เมื่อ 18 ส.ค. 2024
  • One of the biggest challenges with building project schedules is that often you don’t know the details of a piece of work but you need it on your schedule regardless.
    If you work in IT or software development, everyone knows about Rolling Wave Planning. It’s the foundation of iterative methodologies like SCRUM or Lean.
    But maybe you didn’t know we can also apply it to construction projects. Watch this video to learn how you can apply this technique to your project.
    -
    Project Controls Courses that will ignite your skills and career: www.planacadem...
    Find more answers and great Project Controls and Planning information on our blog: www.planacadem...
    Linked In: / planacademy
    ~
    TAGS:
    construction, rolling wave planning, primavera p6, project controls, project management, project controls tools, project controls software, project scheduling, primavera p6 application, construction project

ความคิดเห็น • 51

  • @ashkhan7887
    @ashkhan7887 4 ปีที่แล้ว

    Really like your way of teaching. Very impressive. Simple with clear english

  • @abhishekk4312
    @abhishekk4312 3 ปีที่แล้ว

    Great Explanation, Thank you for the video.

  • @sayedaworor2755
    @sayedaworor2755 2 ปีที่แล้ว

    You explained it so well, Thank you.

  • @tcattie189
    @tcattie189 2 หลายเดือนก่อน

    Great video. On another topic- can you help me understand the error message that occurs when I am progressing my schedule and it says “the remaining finish cannot be greater the

  • @syedshah9411
    @syedshah9411 5 ปีที่แล้ว +2

    Love your videos, nice job keep it up

  • @renezabaldica3757
    @renezabaldica3757 5 ปีที่แล้ว

    Thank you. Great help for me to manage my baseline data and updates on tracks.

  • @kishorekadam1
    @kishorekadam1 5 ปีที่แล้ว

    Great Video and explanation Micheal, super liked it.

  • @TherapyNature
    @TherapyNature 6 ปีที่แล้ว +1

    That’s a good move, I’ve done something like this few years back. But it was rejected to submit that as updated schedule, that’s kind of drive should only be elaborated in excel not on current schedule. Thanks load for the message.

    • @PlanAcademy
      @PlanAcademy  6 ปีที่แล้ว +2

      Glad you enjoyed it.

  • @irviantantohaditomo3526
    @irviantantohaditomo3526 3 ปีที่แล้ว

    Thank you very much, it's great one. How to make a baseline for those are new activities?

  • @angymontes1984
    @angymontes1984 3 ปีที่แล้ว

    I do like your videos.

  • @kes4349
    @kes4349 11 หลายเดือนก่อน

    Would be also good to cover how to deal with resources allocated to the activity. Should the resources be removed from the summary activity and reassigned to shorter activities?

  • @mojtabaabdolifard2086
    @mojtabaabdolifard2086 2 ปีที่แล้ว +1

    Hi, What if the original activity is resource loaded, Should we assign the resources to the new tasks and zero out the resources in the original task?

  • @LEARNPROJECTMANAGEMENT
    @LEARNPROJECTMANAGEMENT 5 ปีที่แล้ว +1

    Appreciated

  • @JerryBrett
    @JerryBrett ปีที่แล้ว

    Great tutorial. Thank you. I have followed the steps but have come up against an issue. The baseline seems to have been lost againt the original activity when changed to a level of effort activity type. Yet, I see there is still a baseline bar for you! Could you explain a work around for me please?

    • @PlanAcademy
      @PlanAcademy  ปีที่แล้ว

      Hey Jerry - It's probably that you are not showing Level of Effort bars in the Gantt Chart. Go into View->Bars, and turn on Remaining Level of Effort bars. In case that doesn't work, make sure you are showing your baseline bars here and you can also try using the "Shift Up / Down" buttons in this Bars screen in case bars are overlapping.

    • @JerryBrett
      @JerryBrett ปีที่แล้ว

      @@PlanAcademy Thanks for the reply. No, LOE bars were turned on, and the other suggestions did not work. Craziest thing..

  • @arianecarmichael4788
    @arianecarmichael4788 6 ปีที่แล้ว +1

    Great TUT, Thank you! When working with level of effort (focus on expenses in a fix price project) which Duration Type and %complete type would you recommend?

    • @PlanAcademy
      @PlanAcademy  6 ปีที่แล้ว +1

      I always recommend using "Fixed Duration & Units/Time" and Physical % Complete.

  • @chhekulama5004
    @chhekulama5004 ปีที่แล้ว

    Can still Rolling Wave applied even though the schedule already baselined. How? Or after adding activties do we need to rebaseline again? By the way, thanks a lot of your videos...Hope more videos to come especially new techniques in scheduling

    • @PlanAcademy
      @PlanAcademy  ปีที่แล้ว

      You can do rolling wave planning with a baseline - I think it's covered in the video. But it might not be accepted by everyone involved. No need to rebaseline if you are following the technique I show here.

  • @dilshodzaiytullaev5233
    @dilshodzaiytullaev5233 6 ปีที่แล้ว

    Thank you

  • @azharmuhammad2190
    @azharmuhammad2190 4 ปีที่แล้ว

    great video

  • @jacksass1978
    @jacksass1978 ปีที่แล้ว

    Hi Mike - thanks for the video - I found it helpful. I notice that when you created the the Hammock (LOE) that you assigned both activities A & F as "successors" to the hammock. I would have made A a SS predecessor and F a FF successor. You state that the hammock/LOE does not show critical because of the way you set up the relationships... is this what you meant?? if you had used my method (SS Pred & FF Succ) would the hammock/LOE show critical?

  • @ibrahimkhail9602
    @ibrahimkhail9602 5 ปีที่แล้ว

    thank you

  • @TheDheerajpandey
    @TheDheerajpandey 6 ปีที่แล้ว +2

    I work a lot on rolling wave planning schedules and always had to manually make changes to maintain the links with baseline. I now know i was doing it all wrong.

    • @PlanAcademy
      @PlanAcademy  6 ปีที่แล้ว +2

      Thanks! great feedback for me!

  • @rameezraja4915
    @rameezraja4915 5 ปีที่แล้ว

    Great

  • @flexworld3069
    @flexworld3069 4 ปีที่แล้ว

    Not sure you can still use the LOE now to compare against your baseline. P6 ignores level of effort tasks when doing baseline analysis. You might need to rebaseline to include the sub activities you created under the new LOE task.

    • @PlanAcademy
      @PlanAcademy  4 ปีที่แล้ว +1

      I'm not finding this is the case. If you don't see a baseline bar under the activity when it is changed to an Level of Effort type, you have to adjust the Bars settings for the Project Baseline Bars line to include LOE activities.

  • @michaelangeloatienza492
    @michaelangeloatienza492 5 ปีที่แล้ว

    hi sir , i think you must remove the successor of the LOF activity that it is dot not summarizes.

  • @elanp
    @elanp 5 ปีที่แล้ว

    If the total duration of activities A through F is 250 days (which is also the duration of "Fabricate Wheel Shop Equipment"), why did activity F have a different Finish date than Fabricate Wheel Shop Equipment, causing the Fabric Wheel Shop Equipment duration to decrease to 247 at the final update? Thanks for the great video, very helpful.

    • @PlanAcademy
      @PlanAcademy  5 ปีที่แล้ว +2

      Good question. Calendars. If you scrutinize, you'll see that my A-F activities use "8x5 workweek calendar", while the Fabricate uses "Corporate 8x5 calendar". So there are likely some differences between these 2 calendars in terms of non-working days that caused the totals to mismatch.

    • @elanp
      @elanp 5 ปีที่แล้ว +1

      Plan Academy Inc. Ah, got it. Thanks for the quick response.

  • @flaviusstanciu1128
    @flaviusstanciu1128 5 ปีที่แล้ว

    How come when you add up the duration of the new 6 activties you get to 247 days instead of 250 days? A=50days; B=30days; C=35days; D=35days; E=50days & F=50days. Summing this is 250, just like the baseline. Different calendar?

  • @basra567
    @basra567 5 ปีที่แล้ว

    Hi. one query please. I m also working on a tutorial. For your video Primavera P6 tutorial : Subcontractor update using reflections. Are the slides made in powerpoint 2010? one feature i m not able to implement

  • @johnb5482
    @johnb5482 4 ปีที่แล้ว

    If the high-level activity has resources loaded on it how are those handled as the details are defined and added? Thanks...

    • @PlanAcademy
      @PlanAcademy  4 ปีที่แล้ว

      You can either leave them on the high-level activity, or move them down to the sub-activities, adjusting as you go. It's preferred to have them on the subactivities for accuracy.

  • @mohammedajmal3326
    @mohammedajmal3326 6 ปีที่แล้ว

    Nice
    Learn something new

  • @mohamedyousuf348
    @mohamedyousuf348 5 ปีที่แล้ว

    Best you use activity steps so we can get detailed activity breakdown

    • @plannerguy
      @plannerguy 5 ปีที่แล้ว

      Maybe, but of course, there's limitations with using activities steps - no dates, no durations, etc.

    • @junemichaelbarnes1031
      @junemichaelbarnes1031 5 ปีที่แล้ว

      It can be but the problem is all activities is set to activity steps as well

  • @lawrenceekwebelam2241
    @lawrenceekwebelam2241 4 ปีที่แล้ว

    Pls how can i remove the dot in wbs code. Ex if i have a wbs code of 21440.-2.2 and I want to remove the dot and left with the dash. how do i go about it in p6

    • @PlanAcademy
      @PlanAcademy  4 ปีที่แล้ว

      P6 WBS always have dots to indicate a next level. No removing them since WBS is a hierarchy.

  • @uharjp2012
    @uharjp2012 5 ปีที่แล้ว

    Thank you

  • @os801
    @os801 5 ปีที่แล้ว

    Great

  • @quevengalang4874
    @quevengalang4874 6 ปีที่แล้ว

    Thank you

  • @ferroudjiabderrahmane3628
    @ferroudjiabderrahmane3628 6 ปีที่แล้ว

    Thank you

  • @9037375313
    @9037375313 5 ปีที่แล้ว

    Thank you