Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JUL 2024

แชร์
ฝัง
  • เผยแพร่เมื่อ 22 ส.ค. 2024
  • Blue line updates from Hebbal to Kasturinagar. Recorded Date : 14-JUL-2024
    Phase 2B - Hebbal to K R puram
    ***********************************************
    JUL 2024 Updates
    Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line
    PKG2 - NCC LTD - 11.678 KM
    PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
    Piling Works Happening and Pier casting Picking up pace.
    Stations in the stretch :
    Package 1 :
    Kasturinagar Station - Pier casting Upto Concourse level in Progress.
    Horamavu Station - All piers cast up to concourse level.
    HRBR Layout Station - Concourse Arm Connector affixing has begun.
    Kalyan Nagar Station - Concourse Arm Connector affixing has begun.
    HBR Layout Station - Pier casting in progress.
    Nagavara Station ( Interchange with Pink Line ) - Piling In Progress.
    Veerannapalya Station - RHS : Pier casting. LHS : Piling.
    Kempapura Station - Median Pier casting has begun.
    Hebbal Station - Pier casting yet to begin.
    ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಕೆ.ಆರ್‌.ಪುರ ನಿಂದ ಕೆಂಪೇಗೌಡ ಅಂತರ್ ರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ | ಏರ್ಪೋರ್ಟ್ ಮೆಟ್ರೊ ಎರಡನೇ ಹಂತ-2B

ความคิดเห็น • 11

  • @mysterious_billionaire
    @mysterious_billionaire หลายเดือนก่อน +8

    This will take another 3 to 4 years i think

  • @shreyasms6786
    @shreyasms6786 หลายเดือนก่อน +4

    NCC need to speedup on this stretch.

  • @ashishsuvarna6685
    @ashishsuvarna6685 หลายเดือนก่อน +3

    why hebbala and kempapura section is very slow by ncc...update on nagawara station progress

    • @SunilHP
      @SunilHP  หลายเดือนก่อน +3

      Hebbal - Kempapura is because of designing / redesigning and then traffic permission. Initially it was portal beams and then now it is split as Up and down line for BLUE line on the ORR - Service road median. ORR main carriageway median is reserved for future Orange line - ORR West line . Nagavara too piling happening. complex station . was delayed for the pink line station box pushing. now hopefully gathers pace.

    • @ashishsuvarna6685
      @ashishsuvarna6685 หลายเดือนก่อน

      @@SunilHP okk

  • @shreyass5664
    @shreyass5664 หลายเดือนก่อน +2

    Hi sir is the orange line metro connecting the blue line metro at kempapura station?

  • @shreyass5664
    @shreyass5664 หลายเดือนก่อน +1

    Any update on the dismantling of the power line at 10.53 min?

  • @murugananthammuruganantham3332
    @murugananthammuruganantham3332 12 วันที่ผ่านมา

    This 11km package work progress is very slow compared to other packages. I think it will be completed by 2029.

  • @shreyass5664
    @shreyass5664 หลายเดือนก่อน

    If any one knows when double decker flyover will be open to public kindly share 😊

    • @SunilHP
      @SunilHP  หลายเดือนก่อน

      @@shreyass5664 your prayers answered and will be opened tomorrow. Njoy

    • @shreyass5664
      @shreyass5664 หลายเดือนก่อน

      @@SunilHP 😊👌👌