Very helpful. How is Productivity rate calculated? Is is per one labour or per labour crew in that particular activity..For example, In Painting Activity that has quatity of 1000 square meter and the productivity is 100 meter square/day. is this 10 meter square/day for one labour(painter)? Again, must we need to add the labour helper is our resource-loading?
Thanks for the feedback and Compliment. However, please always comment on the related tutorial: th-cam.com/video/1WgKABEe-6c/w-d-xo.html For the resources calculation and productivity visit aforementioned tutorial link.
Please share your schedule with us via WhatsApp so that we can investigate and identify the problem. wa.me/923088663797?text=Hello%2C%0A%0AWelcome%20to%20PlanningP6.
Thanks very much Sir, for this other Video which is really instructive. Really hepfull,
Thanks for the feedback and Compliment.
We are glad to hear that our content has been helpful to our friends and viewers. We appreciate the feedback, please share our content on LinkedIn and other social media platforms with others.
Remember to mention @planningp6 and #planningp6 and planningp6.com
Excellent presentation
Thanks for the feedback and Compliment.
We are glad to hear that our content has been helpful to our friends and viewers. We appreciate the feedback, please share our content on LinkedIn and other social media platforms with others.
Remember to mention @planningp6 and #planningp6 and planningp6.com
Nice sir!! However when we split the activity what about resources and cost assigned to it??????
Thanks for the feedback and Compliment.
It is explained in the tutorial, that get the remaining resources and assign them to the new activity.
Very helpful.
How is Productivity rate calculated?
Is is per one labour or per labour crew in that particular activity..For example, In Painting Activity that has quatity of 1000 square meter and the productivity is 100 meter square/day. is this 10 meter square/day for one labour(painter)?
Again, must we need to add the labour helper is our resource-loading?
Thanks for the feedback and Compliment.
However, please always comment on the related tutorial: th-cam.com/video/1WgKABEe-6c/w-d-xo.html
For the resources calculation and productivity visit aforementioned tutorial link.
I tried your method but still my resulting PV is not equal to earned value.
Please share your schedule with us via WhatsApp so that we can investigate and identify the problem.
wa.me/923088663797?text=Hello%2C%0A%0AWelcome%20to%20PlanningP6.
I didn’t understand anything sir…
You'll understand, whenever you will prepare the recovery/revised schedule.