How To Crash Primavera Schedule In Just 5 Minutes || Schedule Crashing || Schedule Compression Trick

แชร์
ฝัง
  • เผยแพร่เมื่อ 18 ส.ค. 2024
  • In this tutorial, let us learn about How To Crash Primavera Schedule In Just 5 Minutes
    As a Planner, you might have faced this situation to crash the project schedule in Primavera to bring the project finish date back.
    Actually, this is a very lengthy process which involves a lot of re-planning.
    But, if you are left with very limited time, there is a smart trick some sort of shortcut for doing this.
    Let us consider this sample project which is having the finished data as " "
    and let us crash the schedule to move the finish date early.
    Step 1:
    I define a Global Change, go to tools, click on global change.
    Give this global change a name, say it as schedule crashing.
    Select the subject area as Activities and set the condition as where Critical equals yes, then remaining duration = remaining duration - 8h.
    so what it does is, it reduces the duration of all the critical activities by 1 day.
    Click Ok.
    Step 2:
    Run Global Change. Once it is executed, Press F9 and Schedule the project plan.
    As we have reduced the duration of critical activities, project duration will also reduce accordingly. So, you can see the new Project Finish date as
    Step 3:
    Remember friends, by this global change, critical activities might have changed and a new critical path will be derived.
    Step 4: If you want to still compress the schedule, run the global change for one more time, by which you will reduce the duration of the newly formed critical activities.
    Step 5:
    Repeat this process until you reach closer to your desired project finish date.
    But friends before performing this trick, take all the necessary step of taking the backup and checking the log files if in case of any errors, as this is just a trick and not the recommended standard way of crashing the schedule.
    So, friends, this is all about ow To Crash Primavera Schedule
    If you have enjoyed this tutorial, please give me a like, share and comment.
    For Personalized detail learning, write to dptutorials15@gmail.com
    If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.
    ***********************************************
    ★ My Online Tutorials ► www.dptutorial...
    LEARNING RESOURCES I Recommend: www.dptutorial...
    Subscribe for more Awesome Tutorials: goo.gl/NyAtg2
    Support the Channel via shopping: ift.tt/2jH38PR
    Tools that I use for Vlogging:
    • Laptop: amzn.to/2E5U3MO
    • Microphone: amzn.to/2VwZyPn
    • 2nd Microphone: amzn.to/2JAK1qt
    • Screen recorder: www.techsmith....
    • Camera: amzn.to/2HglDYA
    • Wireless Mouse: amzn.to/2E23cpN
    Note: This description contains affiliate links, which means at no additional cost to you, we will receive a small commission if you make a purchase using the links. This helps support the channel and allows us to continue to make videos like this. Thank you for your support!
    ***********************************************
    You Can Connect with Me at:
    TH-cam: / dptutorials
    G+: ift.tt/2kAOpa6
    Twitter: / dptutorials15
    Facebook: ift.tt/2kfRnDi
    BlogSpot: ift.tt/2kB14dh
    Follow:
    www.dptutorials.com
    www.askplanner.blogspot.com
    Tags: -
    P6:
    primavera p6 training online, primavera p6, primavera p6 training, primavera p6 tutorial, oracle primavera, primavera p6 download, primavera 6, oracle primavera p6, primavera p6 free download, primavera project management, primavera project planner, primavera download, primavera online, primavera training, primavera software free download, youtube primavera, primavera tutorial, is primavera online easy, p6 online, primavera p6 complete video tutorial free download, critical path, oracle primavera, primavera p6, primavera, primavera software, construction project management software, project management software, project management books, microsoft project, project management courses, project management certification, online project management, project management tools, free project management software, project management training, best project management software, pmp certification, free project management tools, project management apps, microsoft project management, project management professional certification, google project management, ms project, agile project management, basecamp project management, project portfolio management, project management, project management system, scrum project management, open source project management, project management template, construction project management, project plan, project management professional, free project management, it project manager, project manager jobs, project management excel, project management consultant, pmi, project management plan, certified associate in project management, pmp, project management examples, what is project management, project managemen

ความคิดเห็น • 12

  • @roadrunnerpro_d
    @roadrunnerpro_d 4 ปีที่แล้ว +1

    Crashing landing safely executed ☺👍

  • @abhishekbaranwal5801
    @abhishekbaranwal5801 3 ปีที่แล้ว +1

    Lovely trick

  • @adityasingh-sv6cs
    @adityasingh-sv6cs 4 ปีที่แล้ว

    Thank you for sharing

  • @ahmedmedhat9975
    @ahmedmedhat9975 3 ปีที่แล้ว

    you are the best

  • @yamin207eb
    @yamin207eb 5 ปีที่แล้ว

    Keep up the good work dear. Thanks

    • @dptutorials
      @dptutorials  5 ปีที่แล้ว

      Thanks a lot Yamin. I welcome you to subscribe to the channel.

  • @mehboobmisbah
    @mehboobmisbah ปีที่แล้ว

    I just sow this video it is good
    I need other way round
    My project duration was 483 days
    Today 417 days over with 660 activity finish out of 1388
    91 activity in process
    637 activity not started
    Schedule slip
    Additional 417 days required to finished all balance activity
    In resources i am changing per day units by 150% so that finished date prepone but nothing happened.
    Please let me know by this trick how my problem solve

  • @nouranessam9841
    @nouranessam9841 4 ปีที่แล้ว

    Thanks alot

    • @dptutorials
      @dptutorials  4 ปีที่แล้ว

      Most welcome

    • @dptutorials
      @dptutorials  4 ปีที่แล้ว

      Thanks a lot for the feedback.
      I welcome you to subscribe to this channel to enjoy more interesting videos.