Update and Insert Changes Into Your Project? MS Project Made Easy Tutorial #8

แชร์
ฝัง
  • เผยแพร่เมื่อ 22 ธ.ค. 2024

ความคิดเห็น • 20

  • @jeffreypavos2218
    @jeffreypavos2218 3 หลายเดือนก่อน

    Hi Tom,
    I am a construction manager and am very much happy for wealth of knowledge in your tutorials

    • @TomStephensontraining
      @TomStephensontraining  3 หลายเดือนก่อน

      Thanks so much Jeffrey! I’m happy they help or remind you of things.

  • @bobkavoossi2251
    @bobkavoossi2251 ปีที่แล้ว +1

    Very nice and comprehensive.

  • @nordwind2637
    @nordwind2637 ปีที่แล้ว

    Tom as you said i always consider open ends to review schedule. My question is if there is Start to Start relation between 2 activities even in that case do you recommend the link these open ends to next other activities?

    • @TomStephensontraining
      @TomStephensontraining  ปีที่แล้ว

      Yes because if the first activity takes a lot longer to finish than planned i want to see what else it delays

  • @ClaassenChris
    @ClaassenChris 3 ปีที่แล้ว +1

    Tom, could you please share your method for creating S Curves in MS Project directly?

    • @TomStephensontraining
      @TomStephensontraining  3 ปีที่แล้ว

      i will try in future to do a video on that. specifically what do you want the S curve to display? work hours, cash flow ....

    • @HarshitSharma-gc5jb
      @HarshitSharma-gc5jb 3 ปีที่แล้ว

      @@TomStephensontraining I too had a tough time for this s-curve.
      Is it possible to make a s-curve for "baseline cumulative % complete" vs. "actual cumulative % complete"?
      this is to show planned % progress vs actual % progress in a line chart.

  • @ig7061
    @ig7061 ปีที่แล้ว

    Dear tom Thank you shearing the your lessons. this is very easy for understanding. Thanks again !!

  • @angeloprestigiacomo7626
    @angeloprestigiacomo7626 3 ปีที่แล้ว

    Hi Tom. After you have inserted a change order, it appears without baseline. If the change order is accepted by client, should I set a new baseline and how? In general, when I update a schedule and for example insert a new task, or when I set a recovery by inserting a new task, should I set a new baseline and how? Thanks.

    • @TomStephensontraining
      @TomStephensontraining  3 ปีที่แล้ว

      Hi Angelo,
      You can do it without setting a new baseline but little complicated to explain here. Ill try to do a video coming up that better explains that. In simple terms try set base line interim plan, selecting start finish into selected tasks (make sure you select the new tasks.
      Good question

    • @angeloprestigiacomo7626
      @angeloprestigiacomo7626 3 ปีที่แล้ว

      @@TomStephensontraining Hi Tom. Thank you for your answer. I'll look at interim plans. Looking forward to your video.

  • @doudathedevil
    @doudathedevil ปีที่แล้ว

    Tom, I really like how you have a detailed task and breakdown. Does your book have a schedule sample with the breakdown? If yes, I will buy it right now. If not, can you please send me a schedule for a large commercial 3-store building? I will pay for it. Because it will help me to have a guideline. Thanks again

    • @TomStephensontraining
      @TomStephensontraining  ปีที่แล้ว +1

      Hi, I don’t have one I can share specifically for a 3 storey building. I definitely go theough Wbs in my book. Also check my playlists as ive done MS Project and lectures on wbs

    • @doudathedevil
      @doudathedevil ปีที่แล้ว

      @@TomStephensontraining Hi, Tom I already watch the WBS video it was very helpful.

  • @yusufcans
    @yusufcans 10 หลายเดือนก่อน

    Thanks