    The video addresses some of the Frequently asked questions related to Estimate at Completion (EAC) from Earn value concept.
    For instance, you are executing a project which is still undergoing, and you have a defined duration and an identified baseline budget (budget at completion). There comes the point when you analyze your performance, you think can it be possible to complete the project in the previous budget and if not what should be the revised budget (this revised budget is the estimate at completion)? How much money is required to complete this project?
    The term used for the required money is ‘estimate to complete.’
    EAC= AC (Actual Cost) +ETC (Estimate to complete)
    How can you calculate how much more money one needs to complete this project?
    What are the three ways to calculate this EAC? And why do we need three ways and not one formula?
    What are Atypical variants?
    Find answers to these and more interesting questions related to EAC. This is an important topic from PMP® exam point of view.
    Do drop your feedback and recommendations for the webinar topics in the comment box.
    Subscribe to our TH-cam channel and receive email alerts of latest video upload
    The Project Management Professional (PMP), PMBOK, The Agile Certified Practitioner (PMI-ACP), and The Professional in Business Analysis (PMI-PBA) is a registered mark of the Project Management Institute, Inc.
    PMBOK is a registered mark of the Project Management Institute, Inc.
    Materials in this video are based on the text, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Sixth Edition, Project Management Institute Inc., 2017.
    The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.

ความคิดเห็น • 107

  • @Blissful8640
    @Blissful8640 ปีที่แล้ว

    This is by far the best explanation of EAC calculations on TH-cam

  • @cacapoopooface
    @cacapoopooface 4 ปีที่แล้ว +1

    This is the clearest anyone has been able to explain EAC to me. Instead of just rote memorization of these formulas, I now have an understanding of what is happening in both the typical and atypical variance cases and when to use either formula. Thank you!

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      Hi Roger, thanks for your kind words!! Keep an eye on the upcoming videos; we publish them from time to time!!

    • @Blissful8640
      @Blissful8640 ปีที่แล้ว

      I share your sentiments Roger

  • @basictalent1
    @basictalent1 10 ปีที่แล้ว +17

    Thanks alot, this explanation of EAC is so far the best on youtube

    • @izenbridge
      @izenbridge  10 ปีที่แล้ว

      Great!!!! basictalent1 you may like to join our Discussion Forum forum.izenbridge.com

    • @marcoty6312
      @marcoty6312 3 ปีที่แล้ว

      I guess I'm quite randomly asking but do anybody know of a good website to stream newly released tv shows online?

  • @jhonnymohammed7351
    @jhonnymohammed7351 7 ปีที่แล้ว +2

    I have been searched so many videos for EAC concept....but this one is the best one for me....NICE EXPLANATION sir👌👌👌

    • @izenbridge
      @izenbridge  7 ปีที่แล้ว

      Thank you for your kind words :) we are happy to know you found Saket's programs helpful.

  • @angiekourouclis
    @angiekourouclis 3 หลายเดือนก่อน

    You possess an extraordinary gift for teaching; your explanations are both straightforward and effortlessly absorbed.

    • @izenbridge
      @izenbridge  3 หลายเดือนก่อน

      Glad it was helpful! The current PMP Exam is not getting into this much details for this topic.

    • @angiekourouclis
      @angiekourouclis 3 หลายเดือนก่อน

      @@izenbridge Thank you, appreciate the input.

  • @72LINEA
    @72LINEA 5 ปีที่แล้ว

    Very nicely explained. Drilled the concept . Thanks. It’s certainly a great contribution from you to the project management community.

  • @izikrules
    @izikrules 8 ปีที่แล้ว +2

    I finally got the concept of EAC!!!! THANK YOU! Keep up the good job!

    • @izenbridge
      @izenbridge  8 ปีที่แล้ว

      Thank you :) good to know you our resources helpfull

  • @akshtsrivastav3021
    @akshtsrivastav3021 6 ปีที่แล้ว +2

    You are very good at explaining points. Thanks you for the videos.

  • @Krishnag2409
    @Krishnag2409 6 ปีที่แล้ว +1

    The best explanation for EAC...

  • @hiyer8790
    @hiyer8790 6 ปีที่แล้ว +1

    thank you sir! the explanation is fabulous - makes it very simple to follow

  • @SaurabhGupta-fl1vp
    @SaurabhGupta-fl1vp 4 หลายเดือนก่อน

    Best Explanation, now it is crystal clear.....
    Sir, i followed your videos and successfully passed SAFE6. Now PMP concept is also explained amazingly well.
    Thanks for the guidance.

    • @izenbridge
      @izenbridge  4 หลายเดือนก่อน

      Thank you for checking our videos , The Earned Value Management Related topics are not that much important in current PMP Exam, You only get two questions and these two also does not require any calculation. I recommend checking our latest Exam trend based PMP Exam Questions explanations series here : th-cam.com/play/PLWcvFkRbuunlxAQ92tIt1kXWOcgoyhTRR.html

  • @vaishnaviv9850
    @vaishnaviv9850 4 ปีที่แล้ว +3

    Hi Saketh, I thought I need to memorize these formulas , now after watching this video I understood the logic and you have made it easy to think and apply this formula in Exam. Tomorrow is my exam :)
    Thank you , you are the best

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว +2

      Thank you for exploring our videos and for comment here. In general , we make PMP content understandable rather than memorizing it.

    • @vaishnaviv9850
      @vaishnaviv9850 4 ปีที่แล้ว +1

      @@izenbridge I also passed my PMP last month 😀

  • @darkaouioussama5044
    @darkaouioussama5044 9 ปีที่แล้ว +1

    Excellent,
    Thank you so much

  • @gulahmad3215
    @gulahmad3215 8 ปีที่แล้ว +1

    sir fabulous & conceptual, very nice

  • @sanjujgeo
    @sanjujgeo 4 ปีที่แล้ว

    Perfectly explained..after so many trials, finally got the concept in brain with this video. Good job Saket!

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      Keep watching!! To know more about Saket training program, please visit - www.izenbridge.com/landing/youtube/Saket-Bansal/

  • @projectmanagementwes1716
    @projectmanagementwes1716 4 ปีที่แล้ว

    Your work is so great I think others could benefit from learning about it.

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      Thanks for your kind words, keep exploring iZenBridge TH-cam Channel.

  • @FAMCast
    @FAMCast 8 ปีที่แล้ว +1

    From now and on you are my PMP guru sir... Soon will join pmp forum on ur site...

    • @izenbridge
      @izenbridge  8 ปีที่แล้ว

      +Faheem Akhter thanks for exploring our program :) stay connected

  • @sudeepm8096
    @sudeepm8096 7 ปีที่แล้ว +1

    Flawless Explanation, Cheers!!!

  • @kvc2334
    @kvc2334 7 ปีที่แล้ว +1

    Hello! very clear explanation and easy to understand. Thank you

    • @izenbridge
      @izenbridge  7 ปีที่แล้ว

      Thank you for exploring our videos :) good to know you found it helpfull

  • @naghmehvahidian
    @naghmehvahidian 9 ปีที่แล้ว +1

    excellent, thanks

  • @ZiaSherif
    @ZiaSherif 7 ปีที่แล้ว +1

    Very clear explanation. It is indeed really helpful. Thanks

    • @izenbridge
      @izenbridge  7 ปีที่แล้ว

      Thanks for exploring our content :) good to know you found it helpful.

  • @pancycreations
    @pancycreations 8 ปีที่แล้ว +1

    Well explained.
    I have seen the best explanation on this topic in internet

    • @izenbridge
      @izenbridge  8 ปีที่แล้ว

      +Rama Krishna thanks for the kind words :) stay connected

  • @anmarshakir3311
    @anmarshakir3311 5 ปีที่แล้ว

    You did great job and give the subject most of probability to solve exams.. Thanks a lot

    • @izenbridge
      @izenbridge  5 ปีที่แล้ว

      Thank you, we started this channel by solving the Earned Value management problem only. Now we have complete PMBOK 6 program which also has better quality videos, you may like to check our program page for more details: www.izenbridge.com/pmp/online-course/

  • @stax666
    @stax666 4 ปีที่แล้ว

    Mr. Saket, thank you so much!

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      Rajon, happy to know that you liked the video!!! Keep watching them. All the best.

  • @sourav2328
    @sourav2328 6 ปีที่แล้ว +1

    brilliant!

  • @rafavaliente741
    @rafavaliente741 6 ปีที่แล้ว +1

    Master Zen , please continue showing your mastery

    • @izenbridge
      @izenbridge  6 ปีที่แล้ว

      Thanks for exploring our content :) good to know you found it helpful.
      You can explore our complete content - www.izenbridge.com/pmp/online-course/
      You may also drop in your training related queries at sales@izenbridge.com

  • @FernandoLoo
    @FernandoLoo 8 ปีที่แล้ว

    This was really well explained. Thank you!

    • @izenbridge
      @izenbridge  8 ปีที่แล้ว

      +Fernando Loo thank you for appreciating :)

    • @izenbridge
      @izenbridge  8 ปีที่แล้ว

      +Fernando Loo thank you for appreciating :)

  • @israallawati6507
    @israallawati6507 5 ปีที่แล้ว

    Love this. God bless you

    • @izenbridge
      @izenbridge  5 ปีที่แล้ว

      Thank you!! Isra for exploring and liking our content.
      You can also explore our PMP FAQ on Critical Path Method
      th-cam.com/video/QLq9-oFvHbQ/w-d-xo.html&lc=UgxWZInSK_4fDhD4rbt4AaABAg

  • @artie77cg88
    @artie77cg88 9 ปีที่แล้ว +1

    Hi Mr.Pansha.
    Applying also SPI to calculate EAC... Which will be the final formula within TYPICAL case?
    Thanks!

  • @Zamella1
    @Zamella1 5 ปีที่แล้ว

    Many thanks!

    • @izenbridge
      @izenbridge  5 ปีที่แล้ว

      Thank you !! Zamella, for exploring and liking our content.
      In Continuation to it, you can explore our video as per PMBOK Guide sixth edition on "Critical Path Method"
      th-cam.com/video/eZgv1BW1lCU/w-d-xo.html

  • @milanshah4
    @milanshah4 8 ปีที่แล้ว

    bahu saras...!

  • @KumaragoudaPatil20
    @KumaragoudaPatil20 7 ปีที่แล้ว +1

    Very clearly explained 👌

    • @izenbridge
      @izenbridge  7 ปีที่แล้ว

      Thanks for exploring our content :) good to know you found it helpful. You can explore our complete content - www.izenbridge.com/pmp/online-course/
      You may also drop in your queries - sales@izenbridge.com

  • @rgsivacts
    @rgsivacts 7 ปีที่แล้ว +1

    wonderful explanation... :-) I don't need to memorize these formulas any more..

  • @GermanMedinaNeria
    @GermanMedinaNeria 5 ปีที่แล้ว

    Good , Nice explanation, very clear

    • @izenbridge
      @izenbridge  5 ปีที่แล้ว

      Thank you!! Medina for exploring and liking our content.
      In continuation, you can also watch the following video on "Difference between Total Float & Free Float"
      th-cam.com/video/n6YIXmUEoYA/w-d-xo.html

  • @Turkistanian
    @Turkistanian 4 ปีที่แล้ว

    Hello. Thanks allot professor. Tutorial was awesome and it was really helpful giving detailed information about Estimate At Compilation.

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      Thanks Khair Salijogy, for your kind words. Happy to know that you found value in the video.

  • @prakashlavania3543
    @prakashlavania3543 4 ปีที่แล้ว

    this explanation is really awesome...

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      Thanks, Prakash for kind words!! Keep exploring iZenBridge TH-cam Channel.

  • @yasirkhan954
    @yasirkhan954 2 ปีที่แล้ว

    Thanks alot professor. ❤️

    • @izenbridge
      @izenbridge  2 ปีที่แล้ว

      Thank you for watching.

  • @nehatiwary5674
    @nehatiwary5674 หลายเดือนก่อน

    Thank you so much creating amezing content ❤🙏it's worth watching 🙌😇

    • @izenbridge
      @izenbridge  หลายเดือนก่อน

      Thank you so much 😀

  • @IoSzMoAnEeL
    @IoSzMoAnEeL 7 ปีที่แล้ว

    Thank you! very useful! although the third option I didn't get the name correctly in the wb, lol

  • @serioushamster
    @serioushamster 5 ปีที่แล้ว

    Thank you.

    • @izenbridge
      @izenbridge  5 ปีที่แล้ว

      Thanks for exploring and liking our content.
      You can explore our complete content of PMP (Project Management Professional) Based on PMBOK6 here: www.izenbridge.com/pmp/online-course

  • @sandy13121987
    @sandy13121987 7 ปีที่แล้ว +1

    Nicely explained..

    • @izenbridge
      @izenbridge  7 ปีที่แล้ว

      Thanks for exploring our content :) good to know you found it helpful.

  • @ahmedomar6388
    @ahmedomar6388 7 ปีที่แล้ว +1

    You are very beautiful man thank you for these lectures .

  • @piyushsinha1659
    @piyushsinha1659 7 ปีที่แล้ว +2

    Awesome

  • @mahmoudaboubakr6526
    @mahmoudaboubakr6526 4 ปีที่แล้ว

    Fantastic

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      Thanks, Mahmoud for your kind words, keep exploring iZenBridge TH-cam Channel.

  • @kaviwithshanu-pursuitofper9393
    @kaviwithshanu-pursuitofper9393 5 ปีที่แล้ว

    superbly explained sir. Thanks. Moreover you like Jackma

    • @izenbridge
      @izenbridge  5 ปีที่แล้ว

      Thanks!! Raman for exploring our content and liking it. You can also explore our informative video on EVM inline with PMBOK Guide Sixth edition.
      th-cam.com/video/MO6EOMd-CkA/w-d-xo.html

  • @nocsoc2000
    @nocsoc2000 8 ปีที่แล้ว +1

    very useful video

  • @delakofitsigbeh8807
    @delakofitsigbeh8807 4 ปีที่แล้ว

    Good teacher

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      Thanks for your kind words!! Happy to know that you liked videos.

  • @gulmohammadkhan9893
    @gulmohammadkhan9893 5 ปีที่แล้ว

    Very very good

    • @izenbridge
      @izenbridge  5 ปีที่แล้ว

      Thank you!! Gul for exploring and liking our content.
      In continuation to it, you can also explore the PMP video as per PMBOK Guide Sixth edition.
      Earned Value Management Analysis in simple language
      th-cam.com/video/MO6EOMd-CkA/w-d-xo.html

  • @luckboysunday
    @luckboysunday 9 ปีที่แล้ว

    I'm trying to find training on project control and scheduling. Can u recommend please? I want to get better as this is currently my full time position. Thax

    • @izenbridge
      @izenbridge  9 ปีที่แล้ว

      luckboysunday as of now we only do PMP based program, we do not have specialized scheduling program yet.

  • @neel55555
    @neel55555 7 ปีที่แล้ว

    HOW TO CLAIM PDU FOR THIS LECTURE?

  • @JD-rx2kh
    @JD-rx2kh 2 ปีที่แล้ว

    This is extremely confusing lol. And it’s part of my job.

  • @Awais9428a
    @Awais9428a 9 ปีที่แล้ว +1

    Very helpful indeed :)

    • @izenbridge
      @izenbridge  9 ปีที่แล้ว

      Awais Mehmood Thanks... You can also join our Forum www.forum.izenbridge.com/

  • @luckboysunday
    @luckboysunday 9 ปีที่แล้ว

    When you use the word "EV" is this meaning weekly or total?

    • @izenbridge
      @izenbridge  9 ปีที่แล้ว

      luckboysunday It mean at that instance, as part of our cost management plan we need to define at what frequency we are going to do EVM analysis. So EV gets calculated from the start of the project till that point. Please join our forum.izenbridge.com for discussions on PMP related topics

  • @oscarchoops902
    @oscarchoops902 9 ปีที่แล้ว

    Very helpful. Thank you.
    P.S. Fire the camera person.

    • @izenbridge
      @izenbridge  9 ปีที่แล้ว

      Oscar Choops if there is any issue with camera or video, please specify, we will surely look after that

    • @oscarchoops902
      @oscarchoops902 9 ปีที่แล้ว

      Frame the scene. There's no need to zoom in and out or pan to see a formula or answer. It's very distracting.
      Thank you again for the informative video. It's appreciated.

  • @MrKr0307
    @MrKr0307 5 ปีที่แล้ว

    Cost Variance(CV) = EV-AC not AC-EV

  • @erichchan3
    @erichchan3 5 ปีที่แล้ว

    My left ear was able to hear it just fine. My right ear fell asleep.

    • @izenbridge
      @izenbridge  5 ปีที่แล้ว

      Thankyou!! Eric for exploring our content and sharing your valuable feedback.

  • @haseebahmed617
    @haseebahmed617 4 ปีที่แล้ว

    Dear Sir Saket,
    i have a query,
    The BAC of a small project is $100,000. So far $40,000 has been spent to deliver work worth $30,000. What will be the cost estimate to finish the project, assuming future work will be done at the budgeted rate?
    a) $70,000
    b) $60,000
    c) $110,000
    d) $100,000
    i have selected option A, because cost estimate to finish (when future work will be done at budgeted rate) formula is ETC=BAC-EV, BAC is 100,000 and EV is 30,000 so ETC becomes 100,000-30,000=70,000$
    but correct answer was option C with following Explanation:
    At the budgeted rate, EAC = AC + (BAC - EV) = 40000 + (100000 - 30000) = $110000. (In this case EAC is the cost to date plus the value of work remaining, assuming budget remains the same). Refer PMBOK Guide 7.4.2.2 Data Analysis (1st bullet, page 265).
    i have taken cost estimate to finish is estimate to complete ETC
    please guide....
    regards,
    Haseeb Ahmed.

    • @izenbridge
      @izenbridge  4 ปีที่แล้ว

      I think in question it is about ETC , but in answer it is EAC. I think this is an error in question.

    • @haseebahmed617
      @haseebahmed617 4 ปีที่แล้ว

      @@izenbridge 👍

  • @NiniPa668
    @NiniPa668 6 ปีที่แล้ว

    Please get a proper camera man

  • @davidmatlaw7833
    @davidmatlaw7833 6 ปีที่แล้ว

    forced, sing-song voice