Project Management: Finding the Critical Path, duration and Project Duration | Critical Path Method

แชร์
ฝัง
  • เผยแพร่เมื่อ 19 ก.ย. 2021
  • CPM - Critical Path Method||Project Management Technique||Operations Research|| Solved Problem Project Management: Finding the Critical Path, duration and Project Duration | Critical Path Method
    construction project management,
    project management,
    project scheduling,
    scheduling techniques,
    PERT,
    CPM,
    Critical path method solved problems,
    project crashing,
    crashing example problem,
    project cash flow,
    direct cost,
    indirect cost,
    time cost trade off,
    project management,
    project cost crashing,
    project resource management,
    resource optimization,
    cost optimization in project,
    cpm live example,

ความคิดเห็น • 109

  • @akshaykayapak8209
    @akshaykayapak8209 ปีที่แล้ว +5

    nicely easily explained sir..thank you so much

  • @SharableMail
    @SharableMail หลายเดือนก่อน +2

    very clear easy to understand thank you

  • @radhikapareek2701
    @radhikapareek2701 2 ปีที่แล้ว +23

    Thank you so much sir ☺️ for such a easy explanation 😊.

  • @MAHENDRALANJHI-pe8zo
    @MAHENDRALANJHI-pe8zo 11 หลายเดือนก่อน +2

    Thank you sir it is beneficial.

  • @addisukorra7322
    @addisukorra7322 ปีที่แล้ว +18

    Activity No. Activity description
    Duration
    (days) Depends on
    1 Site clearance 2
    2 Excavation in foundations 6 1
    3 Foundations including plinth beam 10 2
    4 Column casting up to roof level 10 3
    5 Slab and beam of roof 21 4
    6 Earth filling and flooring 10 5FS 1 10d
    7 Brickwork 10 5FS 1 7d
    8 Doors/windows 3 7FF
    9 Plastering 10 7SS 1 7d
    10 Painting 7 9SS 1 7d
    11 Plumbing 7 7FF 1 3d
    12 Electrical works 7 11SS
    13 Handover 1 10, 11, 12

  • @user-ge6bi3tv9h
    @user-ge6bi3tv9h หลายเดือนก่อน +1

    ❤❤❤❤❤wow thanks 👍 sir, you teach well ❤❤

  • @johnkallonyokie
    @johnkallonyokie 3 หลายเดือนก่อน

    Very clear and understandable thanks

  • @amaliaazufa5232
    @amaliaazufa5232 ปีที่แล้ว +1

    thanks for the explanations

  • @g.vofficial7624
    @g.vofficial7624 2 ปีที่แล้ว +3

    Thankyou so much sir good explanation 🙏

  • @parameshnaidu5946
    @parameshnaidu5946 7 หลายเดือนก่อน +2

    Easy manner to understand everyone tq so much bro 😊

  • @adabalanagavenkatavinay1485
    @adabalanagavenkatavinay1485 ปีที่แล้ว

    Super explanation sir thanku so much

  • @029_menaha4
    @029_menaha4 10 หลายเดือนก่อน

    Thank you for this video sir

  • @learnwithb2138
    @learnwithb2138 ปีที่แล้ว +1

    Thank you sir 🙏

  • @shiva_rocky
    @shiva_rocky ปีที่แล้ว +2

    Sir good explanation thank u 😊

  • @rohanpansare555
    @rohanpansare555 ปีที่แล้ว +1

    So nice ❤

  • @Sisterdiya
    @Sisterdiya 23 วันที่ผ่านมา

    Thank You Respected Sir for teaching me so well during my examination days. You have been a blessing for all these days. Thank You Dear and Respected Sir. Thank You. God bless you and your family always. ❤️🙏✝️

  • @dularakavindu1743
    @dularakavindu1743 2 หลายเดือนก่อน

    Thank you so much ❤

  • @madhukarnaidunaidu4852
    @madhukarnaidunaidu4852 ปีที่แล้ว +1

    Thank you for the video, useful

  • @nikhithab4631
    @nikhithab4631 ปีที่แล้ว

    Easy way and good information sir

  • @safetyadvisorspecialist7272
    @safetyadvisorspecialist7272 5 หลายเดือนก่อน

    thank you sir.

  • @ucantbeat2256
    @ucantbeat2256 2 ปีที่แล้ว +1

    Verry nice

  • @serbanstere
    @serbanstere 2 ปีที่แล้ว +13

    One question. Are there any restrictions regarding the intersections between arcs ? Are them allowed in this method ?

    • @universeisherestudytime8701
      @universeisherestudytime8701 5 หลายเดือนก่อน +1

      No intersections shouldn't be practiced ... Yes when u make it for the first time u can intersect but then you can make a neatly drawn network

  • @RanjanKumar-vs5ex
    @RanjanKumar-vs5ex ปีที่แล้ว +4

    Tomorrow is my project management exam and I'm watching this video for first time 😃

  • @exploremindtech882
    @exploremindtech882 2 ปีที่แล้ว +1

    Nice bhai

  • @magedrefat1658
    @magedrefat1658 ปีที่แล้ว

    Very clear

  • @saurabhpandey3535
    @saurabhpandey3535 ปีที่แล้ว

    Nice video 👌. Well explained.

  • @alindayu
    @alindayu ปีที่แล้ว +1

    Very similar to operation management: production routing planning.

  • @abunoman1838
    @abunoman1838 6 หลายเดือนก่อน

    thanks

  • @shrinishrinivas9605
    @shrinishrinivas9605 ปีที่แล้ว

    Tq sir

  • @bbrakesha4659
    @bbrakesha4659 ปีที่แล้ว

    Thinks sir

  • @vinayakbadiger2063
    @vinayakbadiger2063 ปีที่แล้ว +1

    Well explained

  • @md-pind.wala3323
    @md-pind.wala3323 2 ปีที่แล้ว

    Good

  • @cybershrajal
    @cybershrajal หลายเดือนก่อน +1

    We are computer science student watching this

  • @danielmbozi3204
    @danielmbozi3204 6 หลายเดือนก่อน

    It is so critical

  • @vanditapatil5442
    @vanditapatil5442 ปีที่แล้ว

    How to put numbers in the circles. I wanted explanation for how to number the events correctly

  • @shafiqahmed3391
    @shafiqahmed3391 ปีที่แล้ว +1

    Hi. Do you do assignments? Related to construction management?

  • @danielkim6672
    @danielkim6672 10 หลายเดือนก่อน

    Thank u curry mucnh

  • @maingadave4841
    @maingadave4841 ปีที่แล้ว

    A nice one but am struggling to learn the english

  • @saravanan02
    @saravanan02 6 หลายเดือนก่อน

    Sir CE3302 Important mattum podunga sir pls

  • @vengalabhaskar
    @vengalabhaskar 2 ปีที่แล้ว

    is it possible to explain with site activities in a construction site ?

  • @addisukorra7322
    @addisukorra7322 ปีที่แล้ว +3

    Two project activities ‘A’ and ‘B’ (B being dependent on A) have a finish-finish relationship with 8 days ‘lag’. The estimated duration for the activities are 10 days and 15 days, respectively. If activity ‘A’ is scheduled to start on the 12th day from the beginning of project, on which day can you schedule to start activity ‘B’?

  • @umarrashid82
    @umarrashid82 2 ปีที่แล้ว +9

    What happened to the slack calculations or float calculations? Arent they necessary to check the criticality and hence find the critical path ?

    • @CivilEngineeringExam
      @CivilEngineeringExam  2 ปีที่แล้ว +2

      i'll continue in next video

    • @mandalapumanikanta3370
      @mandalapumanikanta3370 ปีที่แล้ว

      ​@@CivilEngineeringExam brother can you please tell me tution this subject per one hour daily or every three per a week please brother I very trouble to understand this subject

    • @mandalapumanikanta3370
      @mandalapumanikanta3370 ปีที่แล้ว

      Please 🙏🏻 brother

  • @shaikhfaiz3450
    @shaikhfaiz3450 ปีที่แล้ว

    Critical path will be same for everyone or its depends upon different people draw different kind of network draw ? Plz ans me sir or any one plz ?

  • @danielmbozi3204
    @danielmbozi3204 6 หลายเดือนก่อน

    But the line you used classify it so short become hard for me to validate the critical path

  • @CrimeMasterGogo900
    @CrimeMasterGogo900 ปีที่แล้ว

    Sir Path BEIJ Is possible or not and if not than why sir plz reply

  • @samuelzvirevo4481
    @samuelzvirevo4481 หลายเดือนก่อน

    am confused on activity H,,,,,to put E andJ

  • @Sunil_bavoor13
    @Sunil_bavoor13 ปีที่แล้ว +4

    thank you sir for explaining this tomarow I have exam PROJECT MANAGEMENT SKIIL (PMS)

  • @santhosh9121
    @santhosh9121 3 หลายเดือนก่อน

    😉😉😉

  • @66_priyeshgurjar97
    @66_priyeshgurjar97 7 หลายเดือนก่อน

    Sir How long will it take to Complete the Project and Critical Path Duration Is same???

  • @neharathod3158
    @neharathod3158 ปีที่แล้ว

    plz explain proprly. i cant understand

  • @sudhanshurohela
    @sudhanshurohela 2 ปีที่แล้ว +3

    Shortest duration ko select kyu nahi kiya

  • @user-tz1is1cg2h
    @user-tz1is1cg2h ปีที่แล้ว +40

    Sir why can't we take B - F - I - H . It will be the the critical path as 4 + 5 + 12 + 22 = 43 , Hence critical path will be 43.

    • @faithkarimi147
      @faithkarimi147 ปีที่แล้ว +2

      Yeah the same question am asking

    • @_lessthanzero_
      @_lessthanzero_ ปีที่แล้ว +3

      Check the video again

    • @rajanbhattarai4229
      @rajanbhattarai4229 11 หลายเดือนก่อน +21

      The time duration of i is 2 not 12

    • @TechNepal8945
      @TechNepal8945 10 หลายเดือนก่อน

      i think this question /answer both are wrong bro there is no activity connected in loop .

    • @techgarg4250
      @techgarg4250 9 หลายเดือนก่อน

      Bhai waha 2 hai not 12 please it again

  • @Foodvaalebhaiya
    @Foodvaalebhaiya ปีที่แล้ว

    6:30

  • @omkarkshirsagar3337
    @omkarkshirsagar3337 ปีที่แล้ว

    Hechhh (H) 😂👍

  • @admanassas1853
    @admanassas1853 2 หลายเดือนก่อน

    This is a PERT chart.....

  • @bibo5649
    @bibo5649 11 หลายเดือนก่อน

    Sir activity D you are confusing us

  • @robertfulau4194
    @robertfulau4194 2 ปีที่แล้ว +1

    .

  • @Prashant121_
    @Prashant121_ ปีที่แล้ว

    *20 April 2023 I didn't understand. My exam is in next week*

  • @AbhishekTiwari-kv4gq
    @AbhishekTiwari-kv4gq ปีที่แล้ว

    Sir what is slack time?

    • @CivilEngineeringExam
      @CivilEngineeringExam  ปีที่แล้ว

      difference between the time allocated to the task and the time it actually takes. flexible time for completion of the project

    • @AbhishekTiwari-kv4gq
      @AbhishekTiwari-kv4gq ปีที่แล้ว

      @@CivilEngineeringExam Thanks sir

  • @Silverwasp72
    @Silverwasp72 หลายเดือนก่อน +1

    B - E - I - J ?

    • @SanceShaji
      @SanceShaji หลายเดือนก่อน

      Not possible since the arrow is NOT from E -> I instead it is from I->E

  • @aryamanutkarsh
    @aryamanutkarsh ปีที่แล้ว +1

    Tch tch soo confused

  • @tonnymakokha
    @tonnymakokha ปีที่แล้ว +1

    I think the last path is supposed to be B-F-J-H and not B-F-I-H, this is because H is not precedent by I but H is preceded by J, please correct that sir.

    • @tonnymakokha
      @tonnymakokha ปีที่แล้ว +1

      hence the critical path should be 43 and not 34

    • @140_kenguvabhavesh
      @140_kenguvabhavesh 10 หลายเดือนก่อน +1

      yes,thank you@@tonnymakokha

    • @annonymousperson8508
      @annonymousperson8508 9 หลายเดือนก่อน

      Bro BFJ is complete path then why to add H? I guess it's perfect

    • @kipngenobrian3473
      @kipngenobrian3473 6 หลายเดือนก่อน

      You are right

  • @Suki4r
    @Suki4r 3 หลายเดือนก่อน

    This is the most confusing thing for me

  • @Snorlax_Play
    @Snorlax_Play 3 หลายเดือนก่อน

    Hindi mai bolo sir

  • @sonamtenzin1255
    @sonamtenzin1255 หลายเดือนก่อน

    your answer is wrong for your information

  • @xyz.1234hdgjtvbhh
    @xyz.1234hdgjtvbhh ปีที่แล้ว

    Its H not hech

  • @ivetymutabazi3514
    @ivetymutabazi3514 2 หลายเดือนก่อน

    It's A not Yee 😬😫

    • @itsarkadey
      @itsarkadey หลายเดือนก่อน

      Shut up

  • @shahneelkhan1442
    @shahneelkhan1442 8 หลายเดือนก่อน

    This is wrong

    • @Rakibul_52
      @Rakibul_52 3 หลายเดือนก่อน

      Are you From Bangladesh (Diu)

  • @anishbista645
    @anishbista645 2 ปีที่แล้ว +5

    time waste mumerical.