Project Management: Finding the Critical Path, duration and Project Duration | Critical Path Method
ฝัง
- เผยแพร่เมื่อ 19 ก.ย. 2021
- CPM - Critical Path Method||Project Management Technique||Operations Research|| Solved Problem Project Management: Finding the Critical Path, duration and Project Duration | Critical Path Method
construction project management,
project management,
project scheduling,
scheduling techniques,
PERT,
CPM,
Critical path method solved problems,
project crashing,
crashing example problem,
project cash flow,
direct cost,
indirect cost,
time cost trade off,
project management,
project cost crashing,
project resource management,
resource optimization,
cost optimization in project,
cpm live example,
nicely easily explained sir..thank you so much
very clear easy to understand thank you
Thank you so much sir ☺️ for such a easy explanation 😊.
Most welcome 😊
Thank you sir it is beneficial.
Activity No. Activity description
Duration
(days) Depends on
1 Site clearance 2
2 Excavation in foundations 6 1
3 Foundations including plinth beam 10 2
4 Column casting up to roof level 10 3
5 Slab and beam of roof 21 4
6 Earth filling and flooring 10 5FS 1 10d
7 Brickwork 10 5FS 1 7d
8 Doors/windows 3 7FF
9 Plastering 10 7SS 1 7d
10 Painting 7 9SS 1 7d
11 Plumbing 7 7FF 1 3d
12 Electrical works 7 11SS
13 Handover 1 10, 11, 12
??😅
❤❤❤❤❤wow thanks 👍 sir, you teach well ❤❤
Very clear and understandable thanks
thanks for the explanations
Thankyou so much sir good explanation 🙏
Easy manner to understand everyone tq so much bro 😊
Super explanation sir thanku so much
Thank you for this video sir
Thank you sir 🙏
Sir good explanation thank u 😊
So nice ❤
Thank You Respected Sir for teaching me so well during my examination days. You have been a blessing for all these days. Thank You Dear and Respected Sir. Thank You. God bless you and your family always. ❤️🙏✝️
Thank you so much ❤
Thank you for the video, useful
Easy way and good information sir
thank you sir.
Verry nice
One question. Are there any restrictions regarding the intersections between arcs ? Are them allowed in this method ?
No intersections shouldn't be practiced ... Yes when u make it for the first time u can intersect but then you can make a neatly drawn network
Tomorrow is my project management exam and I'm watching this video for first time 😃
😅
Nice bhai
Very clear
Nice video 👌. Well explained.
Thanks a lot 😊
Very similar to operation management: production routing planning.
thanks
Tq sir
Thinks sir
Well explained
Good
We are computer science student watching this
It is so critical
How to put numbers in the circles. I wanted explanation for how to number the events correctly
Hi. Do you do assignments? Related to construction management?
Yes
Thank u curry mucnh
A nice one but am struggling to learn the english
Sir CE3302 Important mattum podunga sir pls
is it possible to explain with site activities in a construction site ?
sure
Two project activities ‘A’ and ‘B’ (B being dependent on A) have a finish-finish relationship with 8 days ‘lag’. The estimated duration for the activities are 10 days and 15 days, respectively. If activity ‘A’ is scheduled to start on the 12th day from the beginning of project, on which day can you schedule to start activity ‘B’?
20th
15th ?
16th?
What happened to the slack calculations or float calculations? Arent they necessary to check the criticality and hence find the critical path ?
i'll continue in next video
@@CivilEngineeringExam brother can you please tell me tution this subject per one hour daily or every three per a week please brother I very trouble to understand this subject
Please 🙏🏻 brother
Critical path will be same for everyone or its depends upon different people draw different kind of network draw ? Plz ans me sir or any one plz ?
same for all
But the line you used classify it so short become hard for me to validate the critical path
Sir Path BEIJ Is possible or not and if not than why sir plz reply
see the arrows its opposite
am confused on activity H,,,,,to put E andJ
thank you sir for explaining this tomarow I have exam PROJECT MANAGEMENT SKIIL (PMS)
Same
Send some important questions
😉😉😉
Sir How long will it take to Complete the Project and Critical Path Duration Is same???
yes
plz explain proprly. i cant understand
Shortest duration ko select kyu nahi kiya
Mene bhi shortest hi parha hai waise.
Sir why can't we take B - F - I - H . It will be the the critical path as 4 + 5 + 12 + 22 = 43 , Hence critical path will be 43.
Yeah the same question am asking
Check the video again
The time duration of i is 2 not 12
i think this question /answer both are wrong bro there is no activity connected in loop .
Bhai waha 2 hai not 12 please it again
6:30
Hechhh (H) 😂👍
This is a PERT chart.....
Sir activity D you are confusing us
.
*20 April 2023 I didn't understand. My exam is in next week*
Sir what is slack time?
difference between the time allocated to the task and the time it actually takes. flexible time for completion of the project
@@CivilEngineeringExam Thanks sir
B - E - I - J ?
Not possible since the arrow is NOT from E -> I instead it is from I->E
Tch tch soo confused
I think the last path is supposed to be B-F-J-H and not B-F-I-H, this is because H is not precedent by I but H is preceded by J, please correct that sir.
hence the critical path should be 43 and not 34
yes,thank you@@tonnymakokha
Bro BFJ is complete path then why to add H? I guess it's perfect
You are right
This is the most confusing thing for me
Fr
Hindi mai bolo sir
your answer is wrong for your information
Its H not hech
It's A not Yee 😬😫
Shut up
This is wrong
Are you From Bangladesh (Diu)
time waste mumerical.
acha