PERT | Calculate the project variance | Program Evaluation and Review Techniques
ฝัง
- เผยแพร่เมื่อ 27 ส.ค. 2024
- In this video, you will learn how to calculate the project variance and standard deviation .
PERT is used for R&D and Defence , where estimation becomes a challenge.
The following steps are followed :
1. Calculate the Time Estimate
2.Draw the project network
3. Identify the critical path
4. calculate the variance and Standard deviation of the critical activities
5. Calculate the probability of completing the completing the project for the estimated time.
#PERT #projectscheduling #Probability #standarddeviation #zscore #normaldistribution
Keep Watching, Keep Learning
Hi everyone.
To find the variance , Please use the formula (tp-to)/6)^2.
The chapters are added here :
0:00 - Intro
1:47 - Time estimate
8:11 - Network diagram
13:16 -critical path
20:04 -Standard deviation
20:40 - Variance of the critical path
22:25 - Probability of completing the project.
Keep watching, Keep learning
Ma'am I have one doubt variance calculate me last wala 0.4444 kese aaya
SD = Sqrt(Variance)@@ShubhamSharma-st3hd
(a)How can I calculate the expected time for the completion of the project?
(b)how can I calculate the individual slack of the parts?
Madam, why we are not calculating standard deviation of the critical path by adding the SD value of each critical activity?
This explanation is very clear and easy to understand. Thank u so much mam
Wow, u have explained it really well, I appreciate ur effort
Very simplified presentation. Awesome. Want to see more similar videos particularly for project management end. Cheers
The explanation is very clear and easy to understand. Thank you for sharing this online.
Really very well explained ma'am, thanks a lot. A learner like me is understandable easily. Because I am not a student of math's 12th Bio and graduated within the BA stream and working for the last 13 years in IT (as a UI/UX Designer) even then I am getting 98% of your teaching. I am pursuing MBA from Jaipur Manipal online.
Hi, your explanation is clear thanks for your support.
This is very helpful. Thank you so much for your generosity 😊
you are so wonder full.. you have fully talented on good explanation thanks a lot
Thank you! I really appreciate your presentation
Worthy content and easily understandable
Madam am from Tanzania, actually i understood your lessons, thank you
Glad you enjoyed the video ! Aptunalex
wish ,,,if you took our operations research paper. it would have been so much easier, :') you explain in such a simple way. you make it easy for us
Good class mam
best teaching in you tube
Thank you for this.youre a life saver
Thank you very much mam for this video.
Very well explained
thank you so much maam for explaining this topic
Good explanation thanks mam
amazing the way you explain
Thank you so much. Stay blessed!
Thank you so much, ma'am
This video saved me. Thank you so much!
Well explained indeed 👏
Madam, why we are not calculating standard deviation of the critical path by adding the SD value of each critical activity?
This is really good explanation thanks ma'am 🙏🏽
Excellent presentation ma'm. One doubt...should we alwsys divide with 6 for grtting SD ? And...a diverging activity is burst...right ?
its the part of the formula
Nice explanation tnx!
Thank you, ma'am. You're awesome!
Ma'am you're Good. Thank you so much
Thank you ...very much..
THANK YOU A LOT.
very useful this lecture
Last value is wrong for variance..??mam if possible can uh please clear it
VERY HELPFUL
understanding clearly mam tq
Ma'am you're too good!!!
Thank you very much
Thank you,
Can you enlighten me how can I determine a,b,m duration at the start of the project? Thank you
it nice clarification please put each formulas in the note form
Thank you ❤
Simplified 😊
Mam how to calculate variance..??
thank you 💕
at 23:28 0.7874 will round off to 0.79 thwn we have to take 0.7 and 0.09 ? am i correct??
Thank you
Dear Mrs. Arvin,
I hope this message finds you well. My name is palak, and I am an aspiring digital business student with a strong interest in supporting content creators in growing their online presence.
I have been following your exceptional work and am truly inspired by the impact and quality of the content you produce. I believe that with some targeted strategies, your reach and viewer engagement can be significantly enhanced.
I would be delighted to offer my services, free of charge, to assist you in areas such as improving video quality, optimizing audience engagement, and implementing growth tactics specific to your content. My aim is to help you continue delivering high-value content while expanding your audience base.
If you are open to discussing this further, I would be thrilled to collaborate and contribute to your success.
Thank you for your time and consideration.
Best regards,
Palak aggarwal.
Thanks mam ❤️
Thank You maam
Thank you Ma'am
Thank you ❤️❤️
How did you arrive at the variance?
She had to square the standard deviation to reach to the values on the variance..
Thank you mam
Hello mam! I have a problem related to crashing. How can i share my pdf to you. Thanks
Hi mam..if u don't mind can u please update on jz drawing network diagram from basics
Mam how to calculate mean time
How to find delay time
Mam how to find variance and delay value?
Yeah, the video skips there. I figured out the variance is the standard deviation squared. The delay probability is 100% - 78.23%.
Hello madam how to contact you ??
Why to contact dude ?
How to find variance
Formula to find tp tm and to
It will be given in the problem
Hello mam please send me pdf
36÷6=6
how do you find variance ?? @karpagam QT corner
[(tp-to) /6]^2
variance is simply the square of Standard Deviation
Do u have a network diagram, seperate videos to understand ....pls take few simple problems before solving bigger problems
hey, can i get your email?