CPM in Project Management & Operations Research | How to do a Critical Path Method
ฝัง
- เผยแพร่เมื่อ 4 ส.ค. 2024
- In this video, you will learn how to do a critical path method in the most easiest way.
CPM is an important scheduling technique. This method is used when the duration is known or certain.
The steps involved in CPM:
1. Network Diagram
2. Identify the critical path
3. Calculation of Early start time, Early finish time, late start time and late finish time.
4. Calculate the float, free float and independent float.
#CPM #Criticalpathmethod #freefloat #independent float #float
00:00 -Intro
00:43 -Network Construction
02:30 - Critical Path
04:59 -Early Start Time
06:04 - Late Finish Time
8:34 - Early Finish Time
09:08 - Late Start Time
09:57 - Total Float
11:02 Free Float
13:49 Independent Float
Keep Watching, Keep Learning
I always have mental block with this topic. But thank you very much for making it so clear, palatable, and easy to understand. You are an amazing educator!
Kenzo I'm glad this video helped you .Stay tuned for more such videos
@@karpagamqtcorner8764 float and slack both r sam ma'am?
@@kranthikumar4665 yes
pl
Thank you 💕
Simple and great teaching. I never understood clearly this topic either during my college days or during my service till today. You made so clear . Thank You Madam.
YOU ARE SO ORIGANIZED AND GENIUS TEACHER. IT'S WOW!
very nice video. tomorrow is my exam
Same bro
Us bro
Today is my exam, I am in bus going to college and watching this video
Can u share the question paper?@@04_ritampaul87
Watched so many vedeos regarding free float,total float, indipendent float. But can't get it untill I see ur vedeo.Finally I understand this topic. Thank you for your excellent explonation.
had an exam today, watched this video yesterday with 0 prior knowledge and still managed to nail these problems correctly. Great Video, Came back here to say Thank You!
This is fantastic. Learning it online and you've made it easy for me to understand 👍
I am having an exam related to topic and was confused with the formulas. Thanks to u mam now I am clear with everything. The topic was taught very clearly and easy to understand. You are doing a great job and please continue helping people with your way of teaching.
Glad to hear that Santhosh.
I didn't understand it in my class. I also found it very boring. But this is now very clear and enjoyable to me.
Thank you for this amazing video!
Wonderful explanation, each and every step is clearly explained! Thanks Ma'am.
The best explanation for self study students. Very easy to understand
you are an amazing tutor ,, thanks for making it so simple to understand
Thank you, Madam..for your wonderfull explanations..Helps me lot for my MBA in Engineering Management exam. I was little confused...you explains better..Love from Malaysia.
Thank you so much
It's very easy to learn!
It's help me alot ❤️
This is fantastic. Learning it online and you've made it easy for me to understand
Glad to hear that George Ogalo
Hi Miss, I from Malaysia. I really appreciate that finally I can find someone with good knowledge and widely share. Thank you 😊
Your teaching, is so amazing. Am so clarified and refreshed by your teachings. Thanks alot
I always have mental block with this topic.but thanks for making it clear and easy to understand. Your educating method short, precise, easy and very simple to understand....You're unstoppable
I love the way She made everything easy, I understood everything She said.
My mission is to break complex concepts into a simple concept. I'm glad that you have enjoyed the video Unathi Febane .
thanks dear porf
god blees you
two days i was watching the different videos related to this lecture.
fortunately your lecture solved my problems in 10 minutes .
Thank you Ma'am for this easy-to-understand video tutorial.
This is on point. Thank you 🙏
Just the perfect explanation.Thank you
Madam 1 day before exam me video chusa....aboo ma teacher 1week cheppina Ardham kaanidhi meeru vanna rasinattu chepparu .....tq you very much Madam❤️❤️......
I forgot I saw this and realized it again...Thank you ㅠㅠ
Madam 1 day before exam me video chusa....aboo ma teacher 1week cheppina Ardham kaanidhi meeru vanna rasinattu chepparu .....tq you very much Madam......
Thank you so much! Extremely helpful!
It didn’t took even 5 minutes to understand. Thank you ma’am
Thank you so much Ma'am -- Very Nicely clearing the concept.---"Hope This is the best way you teach".
Thanks for liking. Stay tuned for more such videos
I havr understood the concept very clearly thank u so much ma'am 😊
Most welcome 😊 Vaishnavi R
The best explanation for self study students. Very easy to understand. Thank you Ma'am.
Glad to hear that Kaushini
Very informative video !!! Thank you
Thank you so much mam, i have understand the concept of this math Very clearly. Thanks again mam
It's my pleasure Julekha Juthi
Greeting from Kenya. This is very simple to understand. Thanks very much for the clarification 🙏
mam, you have explained it soo clearly and politely, thanks
It is really well-explained ma'am, thank you so much ma'am for this video.
The method of study is very simple and more effective than others.
Thank-you very much,concept become crystal clear.
Very clear teaching. Thank you
Thank you, it's clearly understood
Getting you very well from Tanzania” Mathematics Unite all the people despite our differences”
Indeed it is true Obilla Ezra
Very nice work! Thank you so much ma'am!
Thank you too! Keep Watching
The way of teaching is brilliant 💓thanks alot
I will follow your learning video always, but a great thank's for this topic. Thank you so mach.
You are most welcome Amanuel Getaneh :-)
Good afternoon, I am a Ghanaian from West Africa, and I really enjoy your presentation.
You are a good Teacher. Very good explanation. thanks
You are welcome!
Very helpful thanks for saving my semester
You're so welcome! Madaraka Deche
Thank you maam for explaining this topic beautifully in 16 mins. i was facing problem while understanding this topic and reading the boring ppts
OMG!! Thank you so much ma'am! finally i understood this topic!
Most welcome 😊
The clarity of mam's teaching is remarkable
Thank you very much ma'am. I'm subscribing. I have an exam tomorrow and this really helps❤
Urs teaching way is easy understand by this topic mam... In my clg my mam doing this topic I felt fear how to do but I saw this vedio easily I understand ..tq so much mam
with 20 minutes i got it clear, thanks mam.
U said in independent float if the value is negative & u made it 0, the same is applicable for Total float and free float.Thanks in advance
❤❤❤ Thanks very much for the precise procedure ...easy to understand and lovely
Thank you mam .... i do not understand cpm example but,your support and explaination are understand example
Tomorrow is my exam i have no one to help me so you are my only hope
Thank you so much mam 🎉❤️ very clear and easy explanation 💫just perfect 💯😌
Simple and clear networking am done thank you so much mum
Simply understood
Thank you for this video.
Thanku ma'am for that much simpler explanation 👏👏
TQ mam I have understood very clearly it is very useful for my exam mam
That was very well done,.. easy and simple, you get my subscription
Watching this a couple of days before CMA Finals.... And this is the best video I've come across for network analysis.... Thanks a lot ma'am 🙏
Same here😅.. All the Best!!
@@alishakashyap4431 You too!!
This problem process after 5 mins heading is rounding.. Super telling mam thank you so much
Thank you so much Madam, it is so easy to understand. Thank you. Have an exam in 4 hours lol.
Glad it was helpful!
for backward pass at step 2 , 26-15 = 11 is minimum , compared to 28-15= 13
So what did you take 11 or 13??
Because it make sense..jaisa forward process gya tha waisa hi backward jana chahiye and mam ne wo 2-4 wali line calculate nai kri jisse 11 Aa rha h minimum.. Ya to esa ho skta ki aage jake wo 11 - 13 krke - 2 ho rha hoga islie nai lia..?? Somebody clear me plz😭
On the critical path i.e 1-2-5, there will be no float. Because it is already taking the maximum time, we cannot shift the start or finish without adversly affecting the end time i.e 28 . Hence logically the EST and LFT will be the same.
Thank you ma'am your video is really helpful for me 😊 the day after tomorrow is my exam 😃 so thank you 😊
This was a great help!!!!Thank yoouuuu!!!:):):)
Glad it helped! Waithera
Thanks
well understood
Well explained
thank you, the video is very informative and helpful
Glad to hear that!
Thanks a lot for this.
Very clear video. Thanks
This is a nice asynchronous learning
Great session all concepts got cleared
I was struggling to understand free float, Total float and independent float .. Thanks.
Also I would like to which app or software used as Whiteboard to explain with all colourful markers
very useful, thank u!
Thank you so much ma'am
Very useful for cma final level costing
Thanks so much I was able to understand this
Explaination excellent 👍👍
Very good and easy to learn
Very clarified way 🙏🏻
I like your way of teaching.
Thank you,u where a great help., 🙏🙏
You are amazing ma'am. Thank you so much. Lots of love.❤
Great explanation
thank you so much madam for this critical path method is teach very easily and i understand this method and i prepare for exam
thank you so much mam
All the best
Great video
nice explanation
really appreciated
Well lectured👏
Thank you so much mam.Your video is most important to understand this CPM Method easily and after seen this video now i will solve all type of sum in this method.Once again thanks a lot mam.😊🥰
Thank you for this amazing video!😍😍😍🌹🌹🌹
Amazing explanation...!!!!!!!!!!
Helpful Video
fantastic explaination
Thank you, very very helpful
Thank you very much for nice explained
Very explicit
Thank you very much ma'am
Tq❤️very much for making clear easy to understand
I'm glad that the video helped you Boini Sanganna :-)
Most helpful .it's clearly explanation
thank you very much to identify simple to more understand