Are these the steps I need for delaying the start times? When I do a load test, I need the AC units to completely stop spinning before the Transfer switch swaps to generator power. The office equipment is on battery, so I have time. I want it to delay 4 minutes before the load is transfered.
Are these the steps I need for delaying the start times? When I do a load test, I need the AC units to completely stop spinning before the Transfer switch swaps to generator power. The office equipment is on battery, so I have time. I want it to delay 4 minutes before the load is transfered.
yes, just change the normal to emergency time delay to 4:00