Setting down 3.5 million pounds at the Freedom Mine dragline construction site

แชร์
ฝัง
  • เผยแพร่เมื่อ 27 ต.ค. 2010
  • This is a day Dean Jones and Craig Real have been talking about for months. The revolving frame -- the top white part -- is being lowered down onto the tub of the dragline being built at the Freedom Mine.
    (Dean Jones): "Once we come down on that, it'll never leave that again, at least for 20 years. So, this is a big day."
    Dean Jones works for The Coteau Properties' Freedom Mine. Craig Real works for CCC Group, the contractor on this job.
    (Craig Real): "Everybody's excited. For some, it's the first time... Matter of fact, I've been with the dragline stuff for a long time, but this is actually my first time lowering one. I've had several projects of mine, but I've never been able to be there at the right time. So, this was fortunate for me to be here, to see one lower."
    This is a closer look at the tub. The tub is what the revolving frame sits and rotates on once the dragline is working.
    (Dean Jones): "This morning we made sure the dirt was out from under the rollers and the rails because once we come down, there's not a lot of access to that and you can't get them really clean. Everything has to be spotless before we grease it and go to work."
    The revolving frame must be lowered a total of 40 inches. The job will take at least eight hours. The work is done eight inches at a time.
    (Dean Jones): "It's just a safety factor. Plus, the hydraulic rams themselves, most hydraulic rams don't have a long stroke to them. So, these jacks have a 12 inch stroke, we're gonna use only 8 inches of it."
    First, the revolving frame is lifted less than an inch up. The supports that have been holding the frame in place are removed.
    Then, a pre-measured eight-inch section is cut.
    Some of the sections need a little extra incentive to tumble out.
    Once the first sections are out, the frame is slowly lowered. This first time is the most critical. The frame must be exactly in line with the pin on the tub.
    (Dean Jones): "Yeah, left to right, front to back, we're looking at about an eighth of an inch, we've got clearance on the bushing, so that's all we can do is land that 3 ½ million pounds within an eighth of an inch."
    Once the frame is sitting eight inches lower than before, the process starts up again. It's lifted slightly, sections are cut, and the frame is lowered another eight inches.
    This video shows three minutes of work in three seconds.
    There are fewer than 20 people on site. Most days, there are about 60.
    (Craig Real): "We want to focus on just this part of it. If you have a lot of other people around, that's more people you have to worry about and everything else. Here, we have teams that have been assigned, we're reviewed the whole project and everything. So everybody has a station they work in."
    (Dean Jones): "Tomorrow, everybody comes back in and we go back to work."
    The milestone started at about 10:30 a.m. -- and was finished by 6:00 p.m.
    (Dean Jones): "This is some of the most boring things we can do, and we want it that way. (laughs)"