Situation based questions for PMP® Exam | Episode 11 | Practice questions for PMP® Exam preparation
ฝัง
- เผยแพร่เมื่อ 3 ส.ค. 2024
- In this video, we have solved situational questions on Closing process with detailed explanation for every question that will help solve not only these type of questions but numerous others that test similar skillsets.
00:00 Intro
00:45 Question 1
09:37 Question 2
36:14 Question 3
39:59 Question 4
47:40 Question 5
___________
Take mock exam simulators to test your preparation with exam-like questions: exams.edzest.org
Not sure how and where to start your PMP® preparation, talk to us at
Phone/WhatsApp/Telegram: +91 9673332684
Mail: contact@edzest.org
Amit, Excellent Logic explained in Question 2 to compare Validation of the scope and stakeholders Concensus
Thank you so much! I'm glad you liked it. 🙂
Finally a video dedicated to project closure. Thank you! Scored 4 out of 5. Rationale behind question No 2 was clear.
You're welcome.
Stakeholders having a difference in opinion could happen mostly because of lack in clarity of success criteria, lack of information available to all stakeholders, or bad attitude of Stakeholders. Only option A talks about multiple reasons because of which the conflict can arise.
I’ve been looking for videos on project closure. Thanks a ton for this one Amit!
You're welcome.
TanQ!
You're welcome!
Hi Amit
Question -2
A- tells about adding additional cost in terms of external auditor,
B- since the project is in closing stage that means all the efforts are made to meet the final result throughout the project duration, that means the closing criteria as mentioned in the project charter. Can we keep on updating the charter then How we will close the project?
C- reaching consensus by bringing 2 stakeholders on one table is better, because I am not going to spend extra cost for that. Also the conflict arised in the closing stage so making consensus shall not be planning stage activity.
D - is ruled out
I am not convinced by the answer A.
My answer is C, can you please tell why C is not the answer.
Hi Rizwan, C is not a good choice as it says bring "all" the stakeholders. Bringing relevant stakeholders is ok but not all.
Sir my view option B is also fit as criteria is fixed in Project charter
Hi, which question is this about?
In Question 4 - Why I not choose option for external auditor is because we already have too much cost overruns and while bringing external auditor will also consume more amount so I rejected this...
That's also a correct way of eliminating that option.
regarding question 5, I donot agree that we can add something new to the proect during the closing, It should have been rejected,
Hi, it has not been added, it was initially planned but not executed, and was somehow noticed while closing the project.
Hence, we cannot reject.