Situation based questions for PMP® Exam | Episode 11 | Practice questions for PMP® Exam preparation

แชร์
ฝัง
  • เผยแพร่เมื่อ 3 ส.ค. 2024
  • In this video, we have solved situational questions on Closing process with detailed explanation for every question that will help solve not only these type of questions but numerous others that test similar skillsets.
    00:00 Intro
    00:45 Question 1
    09:37 Question 2
    36:14 Question 3
    39:59 Question 4
    47:40 Question 5
    ___________
    Take mock exam simulators to test your preparation with exam-like questions: exams.edzest.org
    Not sure how and where to start your PMP® preparation, talk to us at
    Phone/WhatsApp/Telegram: +91 9673332684
    Mail: contact@edzest.org

ความคิดเห็น • 17

  • @SailuIVA
    @SailuIVA 8 หลายเดือนก่อน +2

    Amit, Excellent Logic explained in Question 2 to compare Validation of the scope and stakeholders Concensus

    • @edzest
      @edzest  8 หลายเดือนก่อน

      Thank you so much! I'm glad you liked it. 🙂

  • @muttoon
    @muttoon ปีที่แล้ว +1

    Finally a video dedicated to project closure. Thank you! Scored 4 out of 5. Rationale behind question No 2 was clear.

    • @edzest
      @edzest  ปีที่แล้ว

      You're welcome.

    • @edzest
      @edzest  ปีที่แล้ว

      Stakeholders having a difference in opinion could happen mostly because of lack in clarity of success criteria, lack of information available to all stakeholders, or bad attitude of Stakeholders. Only option A talks about multiple reasons because of which the conflict can arise.

  • @azraabbas
    @azraabbas ปีที่แล้ว +1

    I’ve been looking for videos on project closure. Thanks a ton for this one Amit!

    • @edzest
      @edzest  ปีที่แล้ว

      You're welcome.

  • @umamaheswariannadurai8462
    @umamaheswariannadurai8462 3 หลายเดือนก่อน +1

    TanQ!

    • @edzest
      @edzest  3 หลายเดือนก่อน

      You're welcome!

  • @rizwanshahab8720
    @rizwanshahab8720 7 หลายเดือนก่อน +1

    Hi Amit
    Question -2
    A- tells about adding additional cost in terms of external auditor,
    B- since the project is in closing stage that means all the efforts are made to meet the final result throughout the project duration, that means the closing criteria as mentioned in the project charter. Can we keep on updating the charter then How we will close the project?
    C- reaching consensus by bringing 2 stakeholders on one table is better, because I am not going to spend extra cost for that. Also the conflict arised in the closing stage so making consensus shall not be planning stage activity.
    D - is ruled out
    I am not convinced by the answer A.
    My answer is C, can you please tell why C is not the answer.

    • @edzest
      @edzest  6 หลายเดือนก่อน

      Hi Rizwan, C is not a good choice as it says bring "all" the stakeholders. Bringing relevant stakeholders is ok but not all.

  • @yashpalchudasama
    @yashpalchudasama 7 หลายเดือนก่อน +1

    Sir my view option B is also fit as criteria is fixed in Project charter

    • @edzest
      @edzest  7 หลายเดือนก่อน

      Hi, which question is this about?

  • @azharbashir8208
    @azharbashir8208 5 หลายเดือนก่อน +1

    In Question 4 - Why I not choose option for external auditor is because we already have too much cost overruns and while bringing external auditor will also consume more amount so I rejected this...

    • @edzest
      @edzest  5 หลายเดือนก่อน +1

      That's also a correct way of eliminating that option.

  • @adrianoFB
    @adrianoFB 4 หลายเดือนก่อน +1

    regarding question 5, I donot agree that we can add something new to the proect during the closing, It should have been rejected,

    • @edzest
      @edzest  4 หลายเดือนก่อน

      Hi, it has not been added, it was initially planned but not executed, and was somehow noticed while closing the project.
      Hence, we cannot reject.