How to find Standard Deviation for a Project!!! (Network Diagram - Critical path - PERT method)
ฝัง
- เผยแพร่เมื่อ 9 มิ.ย. 2023
- PROJECT MANAGEMENT SKILLS- 20PM01T (PMS)
C-20 SYLLABUS DIPLOMA STUDENTS KARNATAKA
This video demonstrate the solution to find standard deviation for a project when three time estimate is given. Also network diagram is drawn to find critical path.
More more content visit:
@DEEMECH - TH-cam channel
Webpage: deemechkvgp.wordpress.com/
Join My telegram channel for frequent update and learning materials:
t.me/deemechtelegram
PMS Questions and Answers for semester end exam: deemechkvgp.wordpress.com/notes-manuals/question-answer-for-project-management-skills-20pm01t/
Thanks bro 💚✨ your good teaching
Thank you so much❤
Sir your all videos related to diploma subject are useful to me and your teaching techniques was so good sir every thankyou so much sir
Your teaching way of very good sir thank you so mach
Thank u sir namma college alli sir heliddu artha agilla adre niv heliddu artha ayitu sir ✨💝🥰
Thank you sir
thank you so much sir....now am very clear this problem
😊Tq sir
Tq❤
ಥ್ಯಾಂಕ್ ಯು ಅಣ್ಣ❤❤
Tq sir ❤❤
bro in our cw sir has done everthing almost same but duration he has written under each number like box 1/13 is it corrrect???
That cannot be right, here 1 and 2 are events and 1 to 2 are activity. Duration is given to the activity not to the event.
Sir aiml question paper haki sir
International financial management subject du question papers salve madi plz 🙏
❤❤❤❤❤❤❤💥✨️💯💯💯🎟️
sir pms exam postpone agutta atva illa heli
PMS exam is on 12.07.2023. Till date there is no update about any postponement.
@@DEEMECH artha aglilla sir plz heli
@@DEEMECH sir today circular haktara postponement.or exam will run as usual of pms
@@srujanpatil8489 exam will run as usual on 12th of July 2023.
@@DEEMECH and for passing which which units we have to read only for getting 40marks
Reply