I have a question considering the duration of each activity in the network. Do we use the mean time of the activity or the most-likely time??As my teacher in the college said that we use the most-likely time and I'm a bit confused.
I have a question for you can you please send me all the Z values which is given by your teacher 😂 because my teacher gives me only the half of the Probability values
please with timing labelled A, M and B does A represent optimistic, M the most likely and B the pessimistic. If yes, then why is activity A most likely timing greater than the pessimistic timing that is B.
I hate PERT because my teacher gave me 6/10 in it 😂. Do you like it?
Atleast you were given 6/10 mine gave me 2/10
I do
😲
😂
Thank you Engineer boy, I got a 100% on homework assignment!!!
❤️
Most useful lecture for project management. 👍👍👍👍 Thank you dear
Most welcome
You are better than my teacher. Thank you very much.❤
Thank you for watching me
Thanks a lot been so confused all along but you have made it easy🙏🙏🙏💯💯
Very useful and well explained lecture. Thanks for sharing sir.
welcome dear
Great Sir g..Keep it Up
#chemistryunseen
Great job! Perfect walk through, clear explanation, and made it very simple to understand. Thank you.
Thank you for visiting ❤️
U clear the cpm flowchart concept over a particular tupe question
Your cpm concept fails over questions with more than one ending activities
weldone Salman Bhai... perfectly Explained
Enjoy bro ❤️🥰
Appreciates your lecture engineer boy and clearly step by step guide for study 🤝🤝🤝🤝🤝
Thank you for visiting
best best best ,,, Thank you
Most welcome 🥰
Excellent 👏
Thank you for compliment
Thanks sooooo much .... very helpful lecture
Welcome
This is really useful and helpful thanks a lot!
Glad it was helpful!
thank you very much bro i understood each and every thing you said about this lucture i wish you and your be loved family happy and health life
❤️❤️❤️
Most useful
Glad you think so!
well explained.thank you
Welcome infinite
how did we get the checking project time 36days??
0:55 it is already given in question
Very helping lecture 👍👍
Thank you infinite ❤️
thank you sir
you are most welcome
Hi!!!
I want to ask a question. In network diagram at 3:24, you used mean time as duration of that activity.
I am right...?
yes, you are
@@Sulimankhanacademy ok. Thanks a lot!!!🙂
@@whatsnew2807 welcome
I have a question considering the duration of each activity in the network. Do we use the mean time of the activity or the most-likely time??As my teacher in the college said that we use the most-likely time and I'm a bit confused.
in PERT method, we use mean. in CPM we use Most likely
Hi. How did you get the checking project time?
Yah I also have that doubt..
very useful
Glad you think so!
Thanks!😁
Welcome dear
How did you get the checking project time?
Thank you
You're welcome
why you looked the 0.1 coloumn ? thanks
Wondering too
9:50 Are u sure that it's 2.61? I mean it's 2.6195, which should round up to 2.62
Am a bit behind on the last part why 0.1 on the t tables when crossing changing probability?
How did u take checking project time as 32 days?
Thanks for the video, but small mistake in task A time, where mean time is more than pessimistic time, which is incorrect.
Let me check. However focus on method/procedure.
Sir, how did you solved for the early and late for starting and finishing the project?
Watch part 1 of this video.
how do you calculate optimistic most likely and pesimistic times?
There are different techniques for this. Experts do this
hi there, great video! Does Pert Analysis work if there is 1 person to do everything?
No. Because pert is three time estimation.
how can the worst case take less time than the most expected? (first row)
Okay a bit late but what if my teacher's excersises bring out decimal days? Because I can't calculate 10,33333 days.
what would the probability be if the question is asking for more than 35 days?
If the mean time turn out to be a decimal should I use that or round it?
Use that because we are doing iterations here where rounding is not better
Pert example two is uploaded yesterday
@@Sulimankhanacademy Okay thanks alot
How you calculated checking project time?
its given '
I have a question for you can you please send me all the Z values which is given by your teacher 😂 because my teacher gives me only the half of the Probability values
whatsapp me
Programme évolution an review technique
A or B values ai kha sy hen
Manana sir g
Shukria
Once i asked you a question related to PERT and CPM but you didn't reply. I asked you on Facebook massager
Hi. Usually i reply to everyone and each comment. I have not seen your comment. You can ask again. Thanks
How 36 comes
Good explanation. But do you mind loosing the accent?
How can the pessimistic time be less than the Optimistic time in column A
what's with the fake accent!! So irritating.
Its not fake. Its pathan’s accent
thank you sir
Most welcome
please with timing labelled A, M and B does A represent optimistic, M the most likely and B the pessimistic. If yes, then why is activity A most likely timing greater than the pessimistic timing that is B.