Lesson 6 part 5 Link Activities and define activities relationships to achieve the project dates

แชร์
ฝัง
  • เผยแพร่เมื่อ 8 ก.พ. 2014
  • Lesson 6 part 5 Link Activities and define activities relationships to achieve the project dates
    files link: planningengine...
    Before you try to add links to primavera, you should understand what is the types of links:
    Finish-to-Start (FS):This means that Activity B cannot start until Activity A has completed. This is the most common relationship between multiple activities In most schedules.
    Example: Column Activity should be finished to start the slab activity above.
    Did you like this Video? Join us in Planning Engineer Website where we have specialized training courses for planning and scheduling. courses link: bit.ly/2yVJ3z2
    Start-to-Finish (SF):Start-to-finish means that Activity A must start before Activity B can finish. This is a very rare relationship.
    Example: If you want to determine backward the date of the latest shop drawings completion for an activity, Then we can link the start date of foundation with the finish date of the shop drawings of foundation.
    Start-to-Start (SS):This means Activity A must start before Activity B can start.This relationship is based on the activity start times. The end times of each activity are not related.
    Example: we could link the start of the plaster to the start of masonry works with lag 15 days.
    Lag: means that activity A will not start immediately with activity B. Activity B will wait for X days after activity A start to start (X days = lag). Lag could be positive amount or negative amount.
    Finish-to-Finish (FF): This means Activity A must finish before Activity B can finish.
    Example: Project handing over can not be finish until testing is finished.
    ---------------
    Keep in Touch:
    Join our email Newsletter, we send useful free content regularly: planningengine...
    WhatsApp: +201277767728
    Email: Info@PlanningEngineer.Net
    Linked in: / planning-engineer-est
    FaceBook Page: / planningengineerdotnet
    FaceBook Group: / 1138400132963230
    Twitter: / planningeest
    Instagram: / planningengineerest
    ---------------

ความคิดเห็น • 9

  • @KMann71
    @KMann71 6 ปีที่แล้ว

    Thank you very much - nice and simple to follow

  • @javedjamshed4933
    @javedjamshed4933 6 ปีที่แล้ว

    i am new learner here excellent presentation

  • @vijaydev75
    @vijaydev75 10 ปีที่แล้ว

    Its a very nice work. Thanks

  • @dancehatke
    @dancehatke 6 ปีที่แล้ว

    excellent..explained very well. Thank you sir.

  • @ferozkhan5425
    @ferozkhan5425 9 ปีที่แล้ว

    Thank you very much..it is very useful for me...

  • @mohd180584
    @mohd180584 7 ปีที่แล้ว

    Thank you so much sir, helped me so much to understand

  • @joehardcock7242
    @joehardcock7242 6 ปีที่แล้ว

    excellent presentation

  • @ameenuddinmohammed4235
    @ameenuddinmohammed4235 6 ปีที่แล้ว

    Please can you guide, how to give relationship for successors actives at once.

  • @MrJaykecracker
    @MrJaykecracker 9 ปีที่แล้ว

    Assalamualaikom sir!!! Where i can download the CSI internaltional division and subdivision system.