Lesson 7 part 1 Add shop drawings submittals and approvals to the time schedule

แชร์
ฝัง
  • เผยแพร่เมื่อ 23 พ.ย. 2024

ความคิดเห็น • 18

  • @mohammedelewy5878
    @mohammedelewy5878 5 ปีที่แล้ว

    Thanks So Much E. Hani For this recognized lesson ,,,,,,,

  • @solomonsackey7775
    @solomonsackey7775 4 ปีที่แล้ว

    Perfect. Thumps up

  • @mohammedaltaf4877
    @mohammedaltaf4877 10 ปีที่แล้ว

    Fantastic job.

  • @denisgritsiyenko
    @denisgritsiyenko 3 ปีที่แล้ว

    How do we take into account long lead items? We approved the shop drawings, but what if it 6 months out?

  • @muhammadusmananwar8992
    @muhammadusmananwar8992 ปีที่แล้ว

    any other way to load budgeted cost? can we load as a expenses?

  • @engineerkhan6458
    @engineerkhan6458 4 ปีที่แล้ว

    Nice

  • @pkmcpec1020
    @pkmcpec1020 7 ปีที่แล้ว

    good job

  • @caseydoseroscabrera3576
    @caseydoseroscabrera3576 8 ปีที่แล้ว

    hi I want lesson 1 to finish of this video thank you

  • @mohammedaltaf4877
    @mohammedaltaf4877 10 ปีที่แล้ว

    How i can get lesson 10,11,12

  • @alaaabuenayah1505
    @alaaabuenayah1505 3 ปีที่แล้ว

    يعطيكي العافيه بس ياريت باللغة العربية

  • @codhighlights2910
    @codhighlights2910 10 ปีที่แล้ว

    From previous lesson 6.6, after loading the cost all original duration became zero. Can you explain why this happened and how to fix it? thanks

    • @hasanshirazi9535
      @hasanshirazi9535 7 ปีที่แล้ว

      Did you get the answer to this question? I am facing the same problem.

    • @abdulrahimtaha_
      @abdulrahimtaha_ 6 ปีที่แล้ว

      1. Define the Cost resource as Material with unit of measurement $, and setting Standard Rate = 1.00/$. Keep "Default units/time" = 0/d.
      2. Uncheck "Auto Compute Actuals" and "Compute Costs from units".
      3. Assign Cost resource to all required activities.
      4. Through Global Change tool, change the value of "Budget Material Units" under Cost Resource to 1.
      5. Import Cost from excel file or directly input values into the "Budget Cost" parameter.
      Now when you will run the Scheduler or "Recalculate Assignment Costs", it will not effect your schedule or the Budgeted Total Cost.

    • @mingsun6683
      @mingsun6683 6 ปีที่แล้ว

      How about trying to recopy the duration to excel file then importing the excel into Primavera again?

    • @hasanshirazi9535
      @hasanshirazi9535 6 ปีที่แล้ว +1

      @@abdulrahimtaha_ Strange that your comment is exact copy of my comment on:
      engineerbook.net/questions/view/50/primavera-p6-duration-and-budgeted-total-cost-turns-zero
      Did you get it from there?

    • @abdulrahimtaha_
      @abdulrahimtaha_ 6 ปีที่แล้ว

      @@hasanshirazi9535 yes 🙂