I got error after running the 2nd global change function to change Planned & finish dates to start 5D & Finish5D . Some activities got changed but for some other activities it is showing as "Error: Cannot modify "
I tried this in ver23.12, it seems nothing changed. I create 1 activity date 2024-8-19 to 2024-8-30. Do as video told but date is right but if you set project display as hours. You will see project will less 1 hour at finish. Why?
Hi bro.. Got a query ? Will not global Change affect all projects in the system ?? So when i make the final change as 5D start to Planned start, What will happen to other projects in the same data base ?
I have a doubt sir if we allocate Resource to the activity before doing change.it may have variation in units and cost After changing the calendar.is it
Thanks a lot for the feedback. Will surely cover this topic one day, as I am currently going step by step. I welcome you to subscribe this channel to enjoy more interesting videos.
we can just do that with one global change by mutipling the original duration by the ratio between the original duration before and after changing the calender.
I got error after running the 2nd global change function to change Planned & finish dates to start 5D & Finish5D . Some activities got changed but for some other activities it is showing as "Error: Cannot modify "
Do I use the same process to go from 7 day durations on a 7 day calendar to 5 day durations on a 5 day calendar?
I tried this in ver23.12, it seems nothing changed. I create 1 activity date 2024-8-19 to 2024-8-30. Do as video told but date is right but if you set project display as hours. You will see project will less 1 hour at finish. Why?
for finish date not work for planed finish date it worked
You are a Life Saver
Most Welcome
Hi bro.. Got a query ? Will not global Change affect all projects in the system ?? So when i make the final change as 5D start to Planned start, What will happen to other projects in the same data base ?
global change will be applied to only the opened project.
How can I change 5*8 calendar to 7*12?
I have a doubt sir if we allocate Resource to the activity before doing change.it may have variation in units and cost After changing the calendar.is it
Yes.
@@dptutorials how can we rectify the resource change during this method
@@fas-yt765 maybe you can export it first the resource to an excel file, after the calendar change, you import it back the unit and cost..
Thank you ustad
Most welcome
Very good and quick explanation for changing the calendar , I appreciate if you can explain us the loading of non labors cost in P6 in quick way
Thanks a lot for the feedback. Will surely cover this topic one day, as I am currently going step by step.
I welcome you to subscribe this channel to enjoy more interesting videos.
thanks a lot , please i appreciate if you provide me the method of loading the non labor resources
thank you very much...my program worked well this way. But after scheduling date got changed little
please Can u explain how to use 2 difference calender in the same Project ? and how we can keep finish date un changed
Please add a column "Calendar" and by activity wise you can select the desired calendar.
@@dptutorials I mean that will change finish date but I want how to keep it
we can just do that with one global change by mutipling the original duration by the ratio between the original duration before and after changing the calender.