How to Change Calendar From 5 Day to 7 Day but keep Project Finish Date Unchanged In Primavera P6

แชร์
ฝัง
  • เผยแพร่เมื่อ 30 ม.ค. 2025

ความคิดเห็น • 23

  • @saud83mech
    @saud83mech 11 หลายเดือนก่อน +1

    I got error after running the 2nd global change function to change Planned & finish dates to start 5D & Finish5D . Some activities got changed but for some other activities it is showing as "Error: Cannot modify "

  • @par5nto
    @par5nto 3 ปีที่แล้ว

    Do I use the same process to go from 7 day durations on a 7 day calendar to 5 day durations on a 5 day calendar?

  • @byrn1s0nl0rek
    @byrn1s0nl0rek 5 หลายเดือนก่อน

    I tried this in ver23.12, it seems nothing changed. I create 1 activity date 2024-8-19 to 2024-8-30. Do as video told but date is right but if you set project display as hours. You will see project will less 1 hour at finish. Why?

    • @byrn1s0nl0rek
      @byrn1s0nl0rek 5 หลายเดือนก่อน

      for finish date not work for planed finish date it worked

  • @jerabraham
    @jerabraham 3 ปีที่แล้ว

    You are a Life Saver

  • @anithrocks
    @anithrocks 3 ปีที่แล้ว +1

    Hi bro.. Got a query ? Will not global Change affect all projects in the system ?? So when i make the final change as 5D start to Planned start, What will happen to other projects in the same data base ?

    • @dptutorials
      @dptutorials  3 ปีที่แล้ว

      global change will be applied to only the opened project.

  • @shirinh1488
    @shirinh1488 ปีที่แล้ว

    How can I change 5*8 calendar to 7*12?

  • @fas-yt765
    @fas-yt765 3 ปีที่แล้ว

    I have a doubt sir if we allocate Resource to the activity before doing change.it may have variation in units and cost After changing the calendar.is it

    • @dptutorials
      @dptutorials  3 ปีที่แล้ว +1

      Yes.

    • @fas-yt765
      @fas-yt765 3 ปีที่แล้ว

      @@dptutorials how can we rectify the resource change during this method

    • @PenyebarIslamChannel
      @PenyebarIslamChannel 3 ปีที่แล้ว

      @@fas-yt765 maybe you can export it first the resource to an excel file, after the calendar change, you import it back the unit and cost..

  • @nazirahmad4712
    @nazirahmad4712 2 ปีที่แล้ว +1

    Thank you ustad

  • @miaksozs
    @miaksozs 6 ปีที่แล้ว

    Very good and quick explanation for changing the calendar , I appreciate if you can explain us the loading of non labors cost in P6 in quick way

    • @dptutorials
      @dptutorials  6 ปีที่แล้ว

      Thanks a lot for the feedback. Will surely cover this topic one day, as I am currently going step by step.
      I welcome you to subscribe this channel to enjoy more interesting videos.

    • @miaksozs
      @miaksozs 6 ปีที่แล้ว

      thanks a lot , please i appreciate if you provide me the method of loading the non labor resources

    • @shiyas155
      @shiyas155 5 ปีที่แล้ว

      thank you very much...my program worked well this way. But after scheduling date got changed little

  • @ahmedabdelfatah92
    @ahmedabdelfatah92 4 ปีที่แล้ว

    please Can u explain how to use 2 difference calender in the same Project ? and how we can keep finish date un changed

    • @dptutorials
      @dptutorials  4 ปีที่แล้ว

      Please add a column "Calendar" and by activity wise you can select the desired calendar.

    • @ahmedabdelfatah92
      @ahmedabdelfatah92 4 ปีที่แล้ว

      @@dptutorials I mean that will change finish date but I want how to keep it

  • @bananmd751
    @bananmd751 9 หลายเดือนก่อน

    we can just do that with one global change by mutipling the original duration by the ratio between the original duration before and after changing the calender.