Cost Performance Index and Schedule Performance Index - CPI and SPI Example
ฝัง
- เผยแพร่เมื่อ 2 ต.ค. 2024
- I discuss how to calculate the Cost Performance Index and Schedule Performance Index. I also describe the process of using the actual cost, budget at completion, Earned Value (EV), Planned Value (PV), and Cost Variance (CV) to determine the CPI and SPI.
EV/PV in case those V's are identical, will be just similar to E/P. I am wondering why should multiplication with V exist
Thank you for this!!
Thanks for your video! I was wondering if a cumulative CPI is calculated differently.
beautifully explainer
Thank you so much
Thank you ❤️
Do you know an equation to find Upper and Lower Limit of the SPI values
Well explained! thank you!
in 5 minutes very well teach.
What is schedule cost? Formula for it
schedule variance??
clear !
Awesome vid.
Thanks man! great video
good video, easy to understand
👌