Why Not To Use “Must Finish By” in Primavera P6

แชร์
ฝัง
  • เผยแพร่เมื่อ 11 ก.ย. 2024

ความคิดเห็น • 19

  • @PlanAcademy
    @PlanAcademy  2 ปีที่แล้ว +1

    Need to learn P6? Check out the best Advanced P6 Training Available online:
    www.planacademy.com/

  • @azadehkhateri8817
    @azadehkhateri8817 2 ปีที่แล้ว +1

    Mike, thanks for the presentation. One comment though: just because the activity is on the critical path doesn’t mean total float is zero. We can define total float for the critical path in P6 settings to any number of days.

  • @JohnsonJLB
    @JohnsonJLB 3 ปีที่แล้ว +6

    I disagree. You just identified some cons to the Must Finish By. You didn't identify cons to the Finish on or Before method. A better comparative analysis would be preferred. I don't believe there should be a hard-set rule on saying don't use the Must Finish By as there are many different schedule types. Say for instance we had a large schedule 30k activities with multiple paths that were close in duration to the longest critical path. Then one of them extends out past the current critical path that you set a Finish on or Before constraint on. You won't see negative float where you should on the new critical path. Whereas with the Must Finish By you would. Maybe a few processes should be put into play before entering in a Must Finish By. 1. Enter in a Must Finish By only after the schedule is set before the 1st update. 2. While entering in the Must Finish by change users preferences to show time so that the correct date and time is selected. Negative float isn't necessarily bad. It's good because it's an indicator to let us know to pay attention to the schedule and get it back on track. No one want's a schedule that's behind, but we also do want good indicators to let us know when that happens. On a complex schedule the Finish on or Before may not cut it.

  • @mdimrannazeer5432
    @mdimrannazeer5432 4 ปีที่แล้ว +2

    Thank you so much Michael . This is a very important information for planners. Much appreciated

  • @mohi7381
    @mohi7381 2 ปีที่แล้ว

    Thank you so much Michael . This is a very important information for planners. Much appreciated for your awsome problem solving attitude.

  • @eshorlawal7484
    @eshorlawal7484 4 ปีที่แล้ว +1

    Thanks for sharing this Michael. Learned something from this video.

  • @mahansor8295
    @mahansor8295 4 ปีที่แล้ว +1

    Many thanks Michael, very informative, perfect ☑️

  • @seddikben1645
    @seddikben1645 4 ปีที่แล้ว +1

    Thank you so much Michael , i was wondering on it

  • @mahansor8295
    @mahansor8295 3 ปีที่แล้ว

    Many thanks Michael , great

  • @tarikr5853
    @tarikr5853 ปีที่แล้ว

    We're still awaiting for the BMW performance driving lessons :)

  • @anassaidi90
    @anassaidi90 4 ปีที่แล้ว +1

    Thanks you helped me

  • @exploreskillswithdawoodmasih
    @exploreskillswithdawoodmasih 3 ปีที่แล้ว

    Thanks for making such an amazing content.

  • @SS-Shadow
    @SS-Shadow 4 ปีที่แล้ว +1

    Good information 😊👍

  • @igbinevboemmanueli.9897
    @igbinevboemmanueli.9897 4 ปีที่แล้ว +1

    Thank you

  • @rubenaugustine8666
    @rubenaugustine8666 2 ปีที่แล้ว

    Thanks, Mike. I have never used it since my original P6 trainer advised me to avoid Must Finish by. I could not quite understand when you made an example increasing the duration of one critical path activity and then you re-scheduled and the total float changed from zero to -3. You said that it is not what it suppose to happens when you increase a duration (Minute 3:33) butI am confuse now. If you have an activity in the critical path with an specific duration and zero float, if you increase the duration, should not the total float become negative + the amount of days you increase the original duration of the acivity?

    • @azadehkhateri8817
      @azadehkhateri8817 2 ปีที่แล้ว

      That -3d was the same in either method, the difference I guess was in cutting the duration. I still don’t get it: a 15d critical activity with zero float and you reduce the duration by 8d, so it should show 8d positive float.

  • @dastak4724
    @dastak4724 ปีที่แล้ว

    How can I remove this project must finish date?

    • @PlanAcademy
      @PlanAcademy  ปีที่แล้ว +1

      From the Projects screen, you'll find it on the Dates tab. Just erase any date in the field.