Import Progress from Excel to Primavera P6

แชร์
ฝัง
  • เผยแพร่เมื่อ 29 มิ.ย. 2021
  • To request a live help session with Pat, visit our website at www.pjmss.com/

ความคิดเห็น • 15

  • @sarah-janefirth1951
    @sarah-janefirth1951 ปีที่แล้ว +1

    Hi Pat, these videos are really useful as I'm moving from using MS Project to P6 for a new job role so I really appreciate the work you put into these videos!

  • @MissTopDJ007
    @MissTopDJ007 2 ปีที่แล้ว +2

    Thank you so much for creating these series on P6! I'm currently preparing myself to switch from Cost Control to Schedule Control.

    • @PJMScheduling
      @PJMScheduling  2 ปีที่แล้ว

      Thanks for the kind words! I also started off in cost controls and switched to scheduling early in my career. The cost control background will serve you well!

    • @Naved1231
      @Naved1231 หลายเดือนก่อน

      Were you able to make the switch? If yes, do you think its worth it? I want to move to cost control but not sure if it will be a wise decision.

  • @Mileyrubymiles
    @Mileyrubymiles 7 หลายเดือนก่อน

    This video rescued me, thank you so much

  • @muhammadsaifullah8519
    @muhammadsaifullah8519 2 ปีที่แล้ว

    Very informative tutorial.

  • @jessicaelizabethperezmelia50
    @jessicaelizabethperezmelia50 ปีที่แล้ว

    Hi pat, just a question if you have resources asigned how do you update the progress?

  • @ryane1383
    @ryane1383 2 ปีที่แล้ว

    Do you have a troubleshooting guild for importing excel schedules? When I go through the import process nothing gets updated

    • @PJMScheduling
      @PJMScheduling  2 ปีที่แล้ว

      I have quite a few tutorials on my channel for importing from excel to P6. Let me know specifically what you are trying to import from excel, and I may have a video for it and can point you in the right direction. If you're not able to find what you're looking for online, feel free to reach out to me on our website at pjmss.com if you want to set up a live tutoring session with me and we can walk through it.

  • @bhushankhadtale996
    @bhushankhadtale996 ปีที่แล้ว

    Hello Mr Pat, thank you for this useful video, as i am trying to import the excel sheet in P6, i am getting an error
    "An application event has been intercepted. Please note the event code for reference. Event code TPCAT-1067-C".
    Kindly suggest me how to fix this.
    Best Regards

    • @PJMScheduling
      @PJMScheduling  ปีที่แล้ว +1

      So hard to know without looking at the excel file! But, a few things I would check for are:
      -Column headers are named correctly.
      -Required tabs are there and named correctly.
      -The actual data fields have the correct formatting.
      -There are no spaces in the rows.
      If you're still stuck - I do offer tutoring at pjmss.com for a fee. Feel free to reach out through the site and we can take a look together.

  • @MrJithingopal143
    @MrJithingopal143 7 หลายเดือนก่อน

    How we knows our data date while scheduling

    • @PJMScheduling
      @PJMScheduling  6 หลายเดือนก่อน

      Click the "Tools" tab at the top of the screen, and click "Schedule". It will display the data date.

    • @MrJithingopal143
      @MrJithingopal143 6 หลายเดือนก่อน

      @@PJMScheduling so we doesn’t need to change the date which coming as default.some times I noticed that while doing it entire schedule dates are changing

    • @PJMScheduling
      @PJMScheduling  6 หลายเดือนก่อน

      @@MrJithingopal143 Try going to "Schedule Options" under schedule, and uncheck "Schedule automatically when a change affects dates". That should fix your issue. You can then manually reschedule the program after you make a change to recalculate the date.