Earned Value Management | EVM | PMP Questions and Answers 1 | PMP Exam Prep

แชร์
ฝัง
  • เผยแพร่เมื่อ 2 ต.ค. 2024
  • Earned Value Management or EVM is a systematic approach to analyze project status with respect to planned scope, planned schedule and planned cost. This is also referred to as Earned Value Analysis or EVA.
    This lesson addresses the following
    Earned Value Management Questions
    Earned Value Management Formulas
    Earned Value Management Problems
    Additional Lessons
    1. Fixed Price Incentive Fee Contracts: • What is a Fixed Price ...
    2. Firm Fixed Price Contracts: • What is a Firm Fixed P...
    3. Cost Plus Incentive Fee Contracts: • Cost Plus Incentive Fe...
    4. Time Value of Money: • What is Time Value of ...
    5. NPV and IRR: • What is Net Present Va...
    6. Benefit-Cost Ratio & ROI: • Benefit-Cost Ratio & R...
    7. Straight Line Depreciation: • What is Straight Line ...
    8. Double Declining Balance Depreciation: • What is Double Declini...
    9. Sum Of Years Digits Depreciation: • Sum Of Years Digits De...
    All the best with your PMP exam!!
    [Schedule Variance]
    Schedule Variance and Cost Variance
    Schedule Variance in Project Management
    Schedule Variance Formula
    Schedule Variance Calculation Example
    Schedule Variance Example
    Schedule Variance Graph
    Schedule Variance Formula with Example
    [Cost Variance]
    Cost Variance Analysis
    Cost Variance Project Management
    Cost Variance Formula
    Cost Variance and Schedule Variance
    [Schedule Performance Index]
    Schedule Performance Index (SPI)
    Schedule Performance Index Calculator
    Schedule Performance Index PMP
    Schedule Performance Index Formula
    Cost Performance Index and Schedule Performance Index
    [Cost Performance Index]
    Cost Performance Index in Project Management
    Cost Performance Index Example
    Cost Performance Index Calculation
    [Budget At Completion]
    Budget At Completion Project Management
    Budget At Completion Example
    Budget At Completion Formula
    Budget At Completion PMP
    #SunnySensei #EarnedValueAnalysis #EVA #TCPI #SPI #CPI #ETC #EAC #SV #CV #PMP #EV #AC #PV

ความคิดเห็น • 33

  • @scotthall2341
    @scotthall2341 4 ปีที่แล้ว +4

    Those were good questions and a good explanation. This filled in a few gaps. Thank you!

    • @sunny.sensei
      @sunny.sensei  4 ปีที่แล้ว

      You are most welcome. I am happy to know that you found the contents useful. I will be soon posting a lesson on Earned Schedule - a concept introduced in PMBOK Guide 6th Edition. I hope that you will like that too.
      #SunnySensei

    • @scotthall2341
      @scotthall2341 4 ปีที่แล้ว +1

      I also recommended this to a couple of friends today. I look forward to your other explanations.

    • @sunny.sensei
      @sunny.sensei  4 ปีที่แล้ว

      Thank you. I am working on a new lesson on Critical Path Method. I will post that around this weekend. I will be happy if you find that useful too!

  • @khalidmuhammad2798
    @khalidmuhammad2798 4 ปีที่แล้ว +3

    I am not sure the explanation given for question 3 is correct. If the project was not completed on time the SPI can't be 1. SPI 1 means project is on track, SPI=budgeted cost of work performed/ Budgeted cost of work scheduled. At the end of two years work was not complete so the EV can't be 1,000,000 as 4 month worth of work still needs to be performed, based on the fact that your SPI has to be less than 1. Same way SV can't be zero, it will be a negative number

    • @sunny.sensei
      @sunny.sensei  4 ปีที่แล้ว +3

      Hello Khalid, I think you are referring to question #4, not question #3.
      Let me explain. The question says that the project is “already complete”. This means the objectives of the project are met. In EVM terminology, this means EV=BAC. In addition, the planned value of a complete project also equals BAC, or, PV = BAC.
      Now, we have the SPI = EV/PV = BAC/BAC = 1 and SV = EV - PV = BAC - BAC = 0
      This is indeed a strange result. The project ended with a delay, and ideally, we should have SPI < 1 and SV < 0. This is actually a problem with the Earned Value based approach. To overcome this limitation, we use Earned Schedule, an extension to the EVM technique. Please have a look at the following lesson for details.
      th-cam.com/video/s-3fHiZwY1Q/w-d-xo.html
      Good luck with your PMP exam!

    • @cynrooney8411
      @cynrooney8411 3 ปีที่แล้ว

      @@sunny.sensei thank you for the further explanation, as I was wondering the same thing. It says "planned" so that leads me to the initial price of the project, not an adjusted one. I will assume PMI operates under this mentality as well.
      However, the concept of CPI and SPI, on a finished project, seems to be contradictory. How is it, when a project is complete the "planned value" now equals the BAC or EV, and the SPI now equals 1 because the project is now complete (which no longer allows it to be ahead or behind schedule), yet the CPI is not 1? That is extremely confusing. Why are they treated differently?
      Your videos explain everything quite well. Good use of colour to differentiate between terms and calculations.
      I managed 3/5. Not good enough for PMP exam.

  • @Dunbeezytv
    @Dunbeezytv หลายเดือนก่อน

    0-5, but I learned a lot.

  • @spencerfogel3001
    @spencerfogel3001 3 หลายเดือนก่อน

    isnt PV = (planned% completeXBAC) ?

  • @IamPeterP
    @IamPeterP 3 ปีที่แล้ว +1

    I like all your videos. They are clear and helps me to understand more about EVM. Are you sure that the answer of question 3 is B? Because when CPI=0.65, EV=1, then AC=1,53. That means 53% over budget.

  • @larakirwan9297
    @larakirwan9297 10 หลายเดือนก่อน +2

    3 out of 5, but I learned how to calculate CV from CPI and AC. Thank you for revisiting my much-needed algebra I lesson!

    • @sunny.sensei
      @sunny.sensei  10 หลายเดือนก่อน

      I am glad that this lesson was useful to you. Thanks for your comment.

  • @mroyon
    @mroyon 3 ปีที่แล้ว +2

    wish to get more vdos from you, it really helped to improve the problem solving approaches. great work.

    • @sunny.sensei
      @sunny.sensei  3 ปีที่แล้ว

      Thank you again for your kind words. I am sorry for the huge gap between my lessons. I have been quite busy lately. I promise to post another lesson around end of December.

  • @Muhammadshafique-wg8zv
    @Muhammadshafique-wg8zv 8 หลายเดือนก่อน +1

    Excellent. you made my day. this way of explanation with solve examples is amazing and easy to understand. you deserve subscription

    • @sunny.sensei
      @sunny.sensei  8 หลายเดือนก่อน

      Thank you for you kind words. I am glad that you found the lesson helpful 😊

  • @usmansaeed4850
    @usmansaeed4850 2 ปีที่แล้ว +1

    I answered 4 correctly

  • @tesfayeyalew5563
    @tesfayeyalew5563 ปีที่แล้ว

    As to me, the answer to Q3 is "B", not "C". As there is time overrun, the schedule variance is negative, and this makes "C" true, not false. "B" is false as SPI is negative.

  • @amfallkhtaab6036
    @amfallkhtaab6036 4 ปีที่แล้ว +1

    Good channel

    • @sunny.sensei
      @sunny.sensei  4 ปีที่แล้ว

      Thank you, I am glad that you liked my lessons. All the best with the PMP exam!

  • @ihussain6
    @ihussain6 4 ปีที่แล้ว +1

    Good Question and very good explanation, more video on such problems solving will be better for all aspirant. Thank you sir...

    • @sunny.sensei
      @sunny.sensei  4 ปีที่แล้ว

      Thank you for your feedback. I am happy to know that you liked the lesson. I will try to prepare more videos with sample problems. All the best with your PMP exam!!

  • @dudelab8923
    @dudelab8923 4 ปีที่แล้ว +1

    superb! thanks for sharing sir! cheers...

    • @sunny.sensei
      @sunny.sensei  4 ปีที่แล้ว

      I am glad that you liked the lesson. All the best with your PMP exam!

  • @nizarworld2020
    @nizarworld2020 6 หลายเดือนก่อน +1

    Excellent work done

  • @chamansinghchauhan4715
    @chamansinghchauhan4715 3 ปีที่แล้ว +1

    Solid presentation and explanation.

  • @ketemabir1686
    @ketemabir1686 ปีที่แล้ว

    ok

    • @coolio442
      @coolio442 9 หลายเดือนก่อน

      ???? who asked

  • @tdhinaker9327
    @tdhinaker9327 2 ปีที่แล้ว +1

    Relevant and useful examples and a very methodical and simple way to present/teach. Thank you!

    • @sunny.sensei
      @sunny.sensei  ปีที่แล้ว

      Thank you for your encouraging words 🙏