Updating Progress in P6: Benefits of Retained Logic, Progress override & Actual Dates

แชร์
ฝัง
  • เผยแพร่เมื่อ 26 ธ.ค. 2024

ความคิดเห็น • 23

  • @PlanAcademy
    @PlanAcademy  2 ปีที่แล้ว

    Need to learn P6? Check out the best Advanced P6 Training Available online:
    www.planacademy.com/

  • @troyeubank1228
    @troyeubank1228 4 ปีที่แล้ว +5

    I think of the Actual Date option as middle ground between Progress Override and Retained Logic. It uses available actual dates rather than remaining date to perform the calculation. This will behave like retained logic for in-progress out-of-sequence tasks, but like progress override for completed out-of-sequence tasks. Stated another way, logic behind the DD is treated as if scheduling in Progress-Override and logic beyond the DD as if using Retained Logic.
    I typically use this option only when I need to record progress beyond the datadate and still want to show tasks progressed beyond the datadate with the driving indicator for the associated pred or successor. It makes active logic traces a little easier without completed tasks showing as driving unless there is duration after the DD. However, I agree that it's best to use Retained Logic for any "official" schedule reporting.

  • @ninerout399
    @ninerout399 2 ปีที่แล้ว +1

    Actual Dates runs as Retained Logic until there is an Actual Date applied after the Data Date then that one activity is treated as Progress Override. Using Actual Dates allows the illogical use of Actual Dates after the Data Date while not flagging an error in the Schedule Log.

  • @PriyankaVijayMohan
    @PriyankaVijayMohan 3 ปีที่แล้ว +1

    Actual dates : as the name suggests considers actualized logic to show impact . This is helpful when you actualize and update logic prior to rolling DD. Ex : We update our schedules weekly and make sure we address every current week planned activities (current filters on),give new forecast and only then roll Data date. "Actual dates" help in such scenarios.

    • @br_velo
      @br_velo 2 ปีที่แล้ว

      Thanks for this. Using a similar update process and wish I’d known this earlier.

  • @project2080com
    @project2080com 3 ปีที่แล้ว +1

    Hi Michael, about the Actual Dates option it impacts the Late / Early dates. So some floats may change because of it

  • @momunyokol
    @momunyokol 2 ปีที่แล้ว

    When I Update the actual costs the costs in the previous period changes. Why?. How do I make p6 to maintain the previously entered values when I entre the current values

  • @EngrFesan
    @EngrFesan ปีที่แล้ว

    Sir, do you have a video about the total budget cost minus the expense actual cost to give me the remaining cost. something like that.

  • @herminiocruz6636
    @herminiocruz6636 3 ปีที่แล้ว

    Regardless whether retained logic or progress over ride, the actual should be before the data date. Activity H is done, so to my understanding activity H should be before the data date?

  • @berik84t
    @berik84t ปีที่แล้ว

    Hi Michael, thanks for useful videos. I have questions there. Is it correct way if we use all 3 options (depends which we need) during the progress updates? I mean, firts month using retain logics, second month with override logics,... sixth month again with retain logics and etc.
    When/where we can choose them on right way? If we change it every month (for example) we may get different critical paths and also finish date can be unstable (can get back).

    • @PlanAcademy
      @PlanAcademy  ปีที่แล้ว

      You could do that. It's a setting in the "schedule options" screen. These options are set and saved with each project. So you would have to manually change them on each update project.

  • @Lifehacksflakes
    @Lifehacksflakes 4 ปีที่แล้ว +2

    😂😂😂Actual dates , I don’t know . I like your comment on that . Thanks a lot

  • @muhamedessawy3662
    @muhamedessawy3662 2 ปีที่แล้ว

    When it’s recommended to use actual date ??

  • @fsuchek
    @fsuchek 2 ปีที่แล้ว

    Great video and explanation!
    One question: What is the difference between update schedule using the button F9 "Schedule" and the button "Update Progress"?
    Thank you!

    • @brandyharding7692
      @brandyharding7692 2 ปีที่แล้ว

      Exactly the same. It is simply a shortcut for us DOS shortcut users from back in the day.

  • @TKV007
    @TKV007 4 ปีที่แล้ว +1

    Progress override is not a preferred scheduling option since it ignores the network logic

  • @ckryegrass11
    @ckryegrass11 4 ปีที่แล้ว +1

    anybody on here ever take the course from these guys???

  • @murtazaghulam8862
    @murtazaghulam8862 3 ปีที่แล้ว

    Hi sir May I course syllabus

  • @mahansor8295
    @mahansor8295 4 ปีที่แล้ว

    Many thanks

  • @RR.1963
    @RR.1963 3 หลายเดือนก่อน

    Nothing understood, you are not goos teach r