Managing Baselines in Primavera P6
ฝัง
- เผยแพร่เมื่อ 14 ก.ค. 2024
- Primavera P6 Professional allows you to assign up to three user baselines and one project baseline per project. Here we take a look at these. Learn More at tensix.com
- วิทยาศาสตร์และเทคโนโลยี
7 YEARS AGO YOU UPLOADED THIS, AND IT HELPED ME ALOT
Hii bro if u available can u help me abit ?
Very clear and concise explanation! Thanks a lot!
Muchas Muchas Gracias, llevaba tres días intentando que a linea base no se moviera cuando modificaba el proyecto.
very clear explaining thanks for tensix
Thanks so much, enjoyed it!
Very Clear and understandable.
Thanks
Hi Nourhanne - No, resource leveling does not require a schedule baseline. The Max Units/Time is the number of each skill trade you have available to work on your project. If your Max Units/Time demarcation line in the resource usage profile is higher than you would expect, perhaps, you have the time scale set to display Month/Week or weeks instead of Week/Day 1 or days.
was massively useful
It's a wonderful proud on you dear sir
THANKS FOR YOUR INFORMATION
Good tutorial. Very good.
Thanks Robert...we really appreciate your positive feedback.
You made my day ♥️
Very very informative
Help full thanks buddy
Very good explain
thank you very much.
Excelent!
Thanks a lot Sir~
Great use
do i have to assign baseline in order to do leveling ?
i have a problem that when i do leveling , still overallocation exists and the horizontal max unit/ time is referring to a higher value !! like it is pushed up ..
Fantastic
Very nice
Thanks Bro
When I look at my activities only tab my WBS Tabs do not show in larger font or highlighted or at all in. How do I get that to happen?
Great, But we should show the multiple critical paths not only the Float path. Activities are concurrent on the critical and risky, Yes?
thanks
I'm glad you found this useful Fawaz
Thanks for the tutorial , i would like to know when to use the baseline?
This is a static copy of the project, usually made after the final baseline has been agreed by all stakeholders. This must be under version control and not modified without a reasonable process.
When? after all parties (Owners, Consultants, and Contractors) agree that the project must be carried out according to the agreed duration
What for? for comparetion, whether the project is carried out according to plan & schedule, whether the project is on schedule or behind schedule
contact me in ujang.bopengineer@gmail.com
When I add weather days (nonwork) to the project calendar, my baseline doesn’t reflect these changes, so I end up with negative float. Would I need to restore the baseline as its own project and add the same weather days to that project calendar?
How do I show a productivity factor per activity? Is there a
custom column I can create to make this calculation? For example...If I
have an activity that is estimated at 100 hours.....and my actual hours
to date are 75...and im 50% complete with the job, which means I earned
50 hrs....which also means I am running a .67 productivity factor for
that particular activity. How do I make the .67 show up on the activity
line item in one of the columns?
i am new user of Primavera can i know what is your first lecture Please favor.
Regard
Abdul Ghafoor
Thumb up
+Femi Akinlade Thanks Femi :-)
Why do we mention baseline type while maintaining baseline? And what are the definitions are each Baseline type (any source content)?
Please my project is not accessible when . All the information such as WBS, activities etc under the project are grey colour or are not active
My question for you is that , i have problem in start and finish date chnaging as if i perform scheduling, It is going beyound the deadline finish date , so can you provide me solution for that ?
thank you
Regards,
Irshad khan.
Planning engineer
Hi Abdul - You may want to take our online video training class for Primavera P6. Learn more here tensix.com/training/primavera-p6-training/video-training-primavera-p6-professional-r8-3/