    Global change:
    The Global change feature enables you to make changes to all activities, resource assignments, or project expenses, or a selected group of these items, at one time. You can use Global change to edit existing values or assign new values. For example, you can create a statement to assign resource assignments to a group of activities.
    When you run Global change, data exclusively locked by another user does not change. To obtain exclusive access, before opening the project, choose Exclusive in the Access Mode section of the Open Project dialog box.
    Important Notes:
    • You must have access to the activities, resource assignments, and expenses to which you want to make global changes. If your security profile does not enable you to access all of these items, you will not be able to commit the changes you make.
    • If you manually plan future period resource/role allocation, changing data globally may change or delete manual future period values.
    How?
    a- For activity resource assignments, globally changing the Planned Finish, Remaining Finish, and Actual Start may cause manual future period values to change. Manual future period values are deleted when you globally change the assigned Curve, specify an Actual Finish date, or set the Budgeted or Planned and Remaining Units or Units/Time (Labor, Non-Labor, or Material) to zero.
    b- For activities, globally changing the Actual Start, Planned Finish, Planned or Original Duration, Remaining Finish, or Remaining Duration may cause manual future period values to change. Manual future period values are deleted when you globally change the Duration Type to Fixed Units or Fixed Units/Time, specify an Actual Finish date, or set the Budgeted or Planned Units/Time to zero.
    Planning - P6 Channel videos Link:
    / planningp6
    101- What is Project Portfolio Management in Primavera p6 | How to use portfolio option in p6 | primavera
    • What is Project Portfo...
    102- How to establish and assign OBS in p6 |add create and modify responsible mangers to WBS in p6| p6
    • How to establish and a...
    103- How to use and customize user defined fields feature in primaverap6|custom ufds in p6|planningp6|p6
    • How to use and customi...
    104- How to add and use stored image feature in p6 | upload logos in p6 | insert logos and images in p6
    • How to add and use sto...
    105- How does Resource Shift Calendar in Primavera P6 work | Scheduling With Shifts in Primavera P6 |p6
    • How does Resource Shif...
    106- How to Use Activity Steps in Primavera P6 | Update activity steps in p6 | Setting Up Activity Steps
    • How to Use Activity St...
    107- How To Use add Cost Accounts in primavera |What is Cost Account in P6 used for |Assign cost account
    • How To Use add Cost Ac...
    108- What are Funding Sources in primavera p6 | How to create funding accounts p6 | planningp6 | p621.12|
    • What are Funding Sourc...
    109- How to get and install Primavera P6 21.12 New Version 2022 | latest version of P6 21.12 | PlanningP6
    • How to get and install...
    110- Primavera P6 Tricks By Using Schedule Analyzer | convert Xer p6 schedule to excel by analyzer | p6
    • Video
    111- Primavera P6 Resource Curves feature | How to Generate Different Types of Resource Curves Primavera
    • Primavera P6 Resource ...
    112- How To Change Customize the Values and Setting Activity Usage Profile in Primavera P6 | Planning P6
    • How To Change Customiz...
    113- How to Apply Actual in Primavera P6 | Quick way to update the schedule as planned in primavera p6 |
    • How to Apply Actual in...
    114- How to prepare recovery Schedule in Primavera P6 | Recovery Schedule in p6 | Planning-P6 | Primavera
    • How to prepare recover...
    115- How to update progress feature works in primavera p6 | how to update progress as planned quickly p6
    • How to update progress...
    116- How to do Recalculate Assignment Cost in Primavera P6 For Resources | how to recalculate cost in p6
    • How to do Recalculate ...
    117- How to do Summarizing Projects in Primavera P6 | How does P6 summarize data in the Summary/Grouping
    • How to do Summarizing ...
    118- How to prepare revised schedule in p6 | Make revised schedule for any changes in p6 | Primavera p6 |
    • How to prepare revised...
    119- Financial Periods and Using Stored Period Performance in Primavera P6 | primavera p6 | Planning P6 |
    • Financial Periods and ...
    120- How to use Primavera P6 Global Change Tool and feature |Global Change option in p6|Tips, Tricks P6|
    • How to use Primavera P...
    #global_change_in_p6, #changes_to_all activities_resource_assignments_project_expenses_global_change_p6, #primavera_p6

ความคิดเห็น • 4

  • @bluetick9965
    @bluetick9965 19 วันที่ผ่านมา

    ❤❤❤

    • @PLANNINGP6
      @PLANNINGP6  16 วันที่ผ่านมา

      Thanks for the feedback and Compliment.
      We are glad to hear that our content has been helpful to our friends and viewers. We appreciate the feedback, please share our content on LinkedIn and other social media platforms with others.
      Remember to mention @planningp6 and #planningp6

  • @sahdaaulia864
    @sahdaaulia864 3 หลายเดือนก่อน +1

    how to modify global change with different subject area at parameter value

    • @PLANNINGP6
      @PLANNINGP6  3 หลายเดือนก่อน

      You can add any parameter.
      you can apply multiple global changes in one go.
      please contact us via WhatsApp for further queries