Construction Claims and Responses: effective writing and presentation | Public Webinar 25th Feb 2021

แชร์
ฝัง
  • เผยแพร่เมื่อ 6 ม.ค. 2025

ความคิดเห็น • 19

  • @ChangeVneed
    @ChangeVneed ปีที่แล้ว +1

    That's a great presentation, very informative and Andy has kept it simple to understand by a 12 year old.

  • @varshanme
    @varshanme 3 ปีที่แล้ว +4

    Very informative and useful webinar. The webinar presented with simple and clear English pronunciation, which can easily understand by even not native English people. Thank you very much sir.

  • @forestriver7180
    @forestriver7180 3 ปีที่แล้ว +2

    Thank you so much for this. I’m looking forward to be a member of ICCP 😊

  • @vannakchhay3366
    @vannakchhay3366 2 ปีที่แล้ว +1

    Please let me ask you whether we are able to settle the claim by statements recorded as the invoices or bills of purchase destroyed by fire ?

    • @instconstclaimspractitioners
      @instconstclaimspractitioners  2 ปีที่แล้ว

      Thank you for watching. Unfortunately, we do not have the resources to answer all questions asked in public forums. However, we regularly host live question-and-answer sessions free to the public. Please contact hello@instituteccp.com for more information.

  • @danielessiet4063
    @danielessiet4063 2 ปีที่แล้ว

    What is the road map like, to becoming a construction claims specialist?

  • @canbolkan
    @canbolkan ปีที่แล้ว

    thank you

  • @selamawitamanuel73
    @selamawitamanuel73 11 หลายเดือนก่อน

    Thank u so much!

  • @murin7185
    @murin7185 ปีที่แล้ว

    thanks

  • @YasseinAhmed-to4qm
    @YasseinAhmed-to4qm ปีที่แล้ว

    Good evening Mr. Andy,
    Great presentation
    i would like to ask you for a claim dispute and i need your feedback please,
    the contract is a lumpsum contract - General conditions under Fidic Red Book 1999 , we should supply the steel in a certain duration but the Employer had change the design of the raft which taken around 2 months delay,
    the Cause is the Raft redesign
    the Effect is that the steel prices had been increased due to the delay
    the entitlement (actually the contract is a lumpsum contract but the delay beyond our control and the employer had a benefit for such redesign but we loss a lot of money)
    i believe that the unforeseeable physical condition clause cannot considered in that case as its not a physical case, but i need your help to give me another supported clause which can be rely on it.
    thanks

    • @instconstclaimspractitioners
      @instconstclaimspractitioners  ปีที่แล้ว

      Unfortunately, we don't have the resources to respond to each question, but we regularly offer live question-and-answer sessions in the form of Construction Clinics. Please subscribe to our newsletter to be kept informed of our events schedule. www.instituteccp.com/subscribe/

    • @pragmaticpc
      @pragmaticpc ปีที่แล้ว

      Yes you are eligible for both Time and cost under FIDIC Red book 1999

  • @fentishaboswell2398
    @fentishaboswell2398 2 ปีที่แล้ว

    Hi there, would it be possible to attach this power point presentation?

    • @instconstclaimspractitioners
      @instconstclaimspractitioners  2 ปีที่แล้ว

      Webinar slides are available on our website. Scroll down to find this video link and accompanying presentation download: www.instituteccp.com/webinar/

  • @milago8140
    @milago8140 2 ปีที่แล้ว

    I have a book by Andy Hewitt and would like to join ICCP!

  • @mohamadgohar72
    @mohamadgohar72 ปีที่แล้ว

    Iccp?