ProjectLibre : Managing projects using Work Breakdown Structures in ProjectLibre

แชร์
ฝัง
  • เผยแพร่เมื่อ 29 ม.ค. 2025

ความคิดเห็น •

  • @everythingisfake7555
    @everythingisfake7555 11 หลายเดือนก่อน +1

    how do you change the wbs numbering to behave in a more industry standard manner? the number system should be 1 1.1, 1.2, 1.3… etc. Is it possible to change that? Also the root is 0 not 1, I dont think you are using it properly here

  • @TheLeneghad
    @TheLeneghad 4 ปีที่แล้ว +1

    Hi Marc, thank you for these videos they are really useful. As someone just getting started with PM and PM software this is a fantastic resource. If I could make a suggestion for your youtube channel, it's to put these videos into a playlist so that they can be watched in the intended order.

    • @ProjectLibreCloud
      @ProjectLibreCloud  4 ปีที่แล้ว +1

      Great suggestion Darren, we will do that and thank you for the comments! We will continue adding the videos.

  • @0ren504
    @0ren504 11 วันที่ผ่านมา

    How do you enlarge the GUI???

  • @flemmingdall9100
    @flemmingdall9100 2 ปีที่แล้ว +1

    Hi Marc, in Danish language you need these Letters - æ ø å. Great job though, love it.

  • @saschathiede
    @saschathiede 4 ปีที่แล้ว +1

    Hi, thanks for the tutorial! Is there a way to change the layout of the WBS to sideways? I have quite a lot of parallel tasks, and the WBS is now exceptionally wide.

    • @ProjectLibreCloud
      @ProjectLibreCloud  4 ปีที่แล้ว +1

      ProjectLibre does not have a setting

    • @saschathiede
      @saschathiede 4 ปีที่แล้ว

      @@ProjectLibreCloud Alright. Thanks anyways for the fast answer. Keep up the great work!

  • @thomaswala997
    @thomaswala997 4 ปีที่แล้ว +1

    Great, thank you!

  • @ipohboy
    @ipohboy 3 ปีที่แล้ว +1

    Excellent thank you.

  • @erincampbell2761
    @erincampbell2761 4 ปีที่แล้ว

    Hi Marc, What is the difference between the two styles of boxes in the WBS? The third row of items are in a square box, but the top ones have a diagonal slant.. I'm confused..

    • @tahoeob
      @tahoeob 4 ปีที่แล้ว +1

      Hi Erin, what a great question.... Here are the differences.
      * Parallelogram with the slanted sides represent Summary Tasks
      * Box with two angled lines on each side represent a Milestone task (0 duration)
      * Rectangle represents tasks (note the Red indicates a Critical task and Blue a non-critical task)
      Once again, great question and I should have included in the video so apprecaite your noticing!

  • @Hayounam
    @Hayounam 2 ปีที่แล้ว

    Thank you for your video. Is there anyway that I can put completion percentage in WBS?

    • @ProjectLibreCloud
      @ProjectLibreCloud  2 ปีที่แล้ว

      Hi Hayoung, wow you surprised me because when we tested ....you are correct. We don't have a developer to put on this but in the past I believe as you did a "Zoom Out" it would add more fields and that included percent complete. I just tried and it just makes the box larger not adding the fields.... Thank you for the note!

  • @gunitinug
    @gunitinug 3 ปีที่แล้ว

    where did the budget come from?

    • @tahoeob
      @tahoeob 3 ปีที่แล้ว +1

      When you enter resources rate and then assign the resource to a task it creates a cost. When you baseline it creates the budget. Example: Marc is $100/hour on a 1 day task (8hr). The task cost is $800 and if I baseline the cost is $800. If the task takes 16 hours then the cost is $1,600 but the baseline budget is still $800.