What is Extension of Time claim ? | Important duty of a Quantity Surveyor | EOT in construction

แชร์
ฝัง
  • เผยแพร่เมื่อ 14 ก.ค. 2024
  • Learn more about Extension of Time from this video.
    #eot #construction #claims
    0:00 Introduction
    3:17 Components
    3:32 Delay Analysis
    14:10 Time related costs
    19:28 Communications & correspondences
    20:59 Thank you
    For video of Head office related cost, click below link:
    • How to Calculate Head ...
    To enroll for my Quantity Surveying Courses, Click:
    Quantity Surveyor's Guide for Pre-Contracts Management
    www.udemy.com/course/quantity...
    Contracts Management in Construction Projects
    www.udemy.com/course/contract...
    HVAC Ductwork Quantity Take off for Quantity Surveyors
    www.udemy.com/course/hvac-duc...
    Quantity Surveying Templates for Effective Cost Management
    www.udemy.com/course/quantity...
    Quantity Surveying With Rate Analysis And Take Off-Beginners
    www.udemy.com/course/quantity...
    Project Management: Cost & Schedule Monitoring using EVM
    www.udemy.com/course/earned-v...
    For my credentials, please check out my Linkedin Profile:
    / akhil-krishna-5126b946
    Follow me on Facebook:
    / theqsstudio
    Follow me on Instagram:
    / theqsstudio

ความคิดเห็น • 21

  • @teshanrathnayake6122
    @teshanrathnayake6122 7 วันที่ผ่านมา

    Very helped ❤

  • @Civilians_Bala-and-Vigi
    @Civilians_Bala-and-Vigi ปีที่แล้ว +1

    Thank you so much, it's very use ful. I love the way you explained

  • @vijaybhilwade3194
    @vijaybhilwade3194 ปีที่แล้ว +1

    As per Clause 10.5 of the concession agreement EOT ( Extension of Time ) will be given only in the following scenario (a) delay in providing the Right of Way of Construction Zone, environmental clearances or approval of railway authorities, specified in Clause 3.1 (iv);
    (b) Change of Scope (unless an adjustment to the Scheduled Completion Date has been agreed under Article 13);
    (c) occurrence of a Force Majeure Event;
    (d) any delay, impediment or prevention caused by or attributable to the Authority, the Authority's personnel or the Authority's other contractors on the Site;

  • @syedtamjeed4250
    @syedtamjeed4250 2 ปีที่แล้ว +2

    Learning a lot from ur channel 📈

  • @ahmadfareedthoufeek1133
    @ahmadfareedthoufeek1133 2 ปีที่แล้ว +3

    Hi, I will request u to teach takeoff using 3D models. I think that's is the priority for QS. Mostly Civil QSs knows all these stuffs. But,need takeoff using NRM2 and POMI. I hope u understand... Thanks for your free service. Good luck

  • @AB-ff1cq
    @AB-ff1cq ปีที่แล้ว +1

    Nice one Akhil

  • @irzathmohamed3151
    @irzathmohamed3151 ปีที่แล้ว +1

    😊😊❤

  • @PradeepKumar-sw8hl
    @PradeepKumar-sw8hl ปีที่แล้ว +1

    Thanks

  • @Adnan.4474
    @Adnan.4474 ปีที่แล้ว +1

    Very well explained, i am watching all your videos, very helping and informative, just asking about the approved claims, like Variation orders once approved we claim them in IPC's same to be done for these EOT and other claims??

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  ปีที่แล้ว

      All claims can be included in the monthly IPA's. EOT is usually a part of final account.

  • @tabish128
    @tabish128 ปีที่แล้ว

    Sir, Can you tell us when is the right time to submit the EOT claim? is it just after the delay or just before the end of the project completion date? and what if eot is granted but than again another delay occurs will we apply again for the EOT?

  • @jalpasuthar2128
    @jalpasuthar2128 2 ปีที่แล้ว +1

    Hi Akhil, thank you so much sharing these videos, just out of interest would like yo know are you a chartered surveyor?

  • @tabish128
    @tabish128 ปีที่แล้ว

    is this claim taken from FIDIC?

  • @charlesbird3021
    @charlesbird3021 ปีที่แล้ว

    Hi! what is the value of the daily rate calculation in respect to extension of time claims?