How to claim the Materials On Site ? | Cash flow management technique

แชร์
ฝัง
  • เผยแพร่เมื่อ 18 ส.ค. 2024

ความคิดเห็น • 51

  • @cymamohammed1311
    @cymamohammed1311 3 หลายเดือนก่อน +1

    Students and job seekers get advantages from your videos. Thanks.
    Clear explanation....Simply Fantastic
    👍
    Great job...

  • @descartesdivindushime2201
    @descartesdivindushime2201 4 หลายเดือนก่อน +1

    Very helpful

  • @mohdhamza297
    @mohdhamza297 ปีที่แล้ว +2

    The main supporting document for MOS claim is.approved material inspection request.

  • @nifrassm
    @nifrassm ปีที่แล้ว +1

    Brother ❤️👍👍👍👍

  • @cjmariano5853
    @cjmariano5853 2 ปีที่แล้ว +1

    maybe we could include the materials site inspection approval as attachment, as some engineers requires the same..its informative video..thanks

  • @ab2_3000
    @ab2_3000 3 ปีที่แล้ว +1

    Thanks for the educative videos
    So the contractor claims for material on site and again claims for the work excuted using the same material probably later on,I believe at a certain time(guessing at completion) the client will have to be refunded the amount he paid for material onsite since the same material would have been used in the works and consequently xlaimed by contractor

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  3 ปีที่แล้ว +1

      The deduction for material claim needs to be done at the time it is installed in ideal situation. Ultimately since MOS is to be completely deducted the client may decide when this can be done.

  • @khalilahmed485
    @khalilahmed485 ปีที่แล้ว +1

    we can pay ‘’Material on site’’ 80% of the particular item of the BOQ in a lumpsum contract. if we go through material prices, it maybe lower or higher than the BOQ. So it’s better to follow the 80% of BOQ prices. please correct me if I’m wrong.

    • @khalilahmed485
      @khalilahmed485 ปีที่แล้ว +1

      Contractor have to submit day work schedule along with his contract and consult can derive the rates and quantity from that. Delivered material from contractor May be more than actual quantity as well rates. So the 80% Determined by the engineer

  • @hasanthiyasarathne8092
    @hasanthiyasarathne8092 25 วันที่ผ่านมา +1

    How to prove the purchased rate?

  • @shinazkv6709
    @shinazkv6709 3 ปีที่แล้ว +1

    Please make a video of payment claims against the approved terms in a contract.

  • @oghoghoizedonmwen9275
    @oghoghoizedonmwen9275 2 ปีที่แล้ว +1

    Thanks for educative vidoe on how to calculate materials on site , pls send me a copy .

  • @MesheKitchen
    @MesheKitchen 2 ปีที่แล้ว +1

    Do we claim 80% for each MOS? And when and how is the deduction for MOS made?

  • @dama4316
    @dama4316 3 ปีที่แล้ว +1

    How about in the case of making delivery of 100% of the materials required for the entire project to the site in the first month of the project duration with the intention to claim MOS? Would you succeed in claiming all of it?

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  3 ปีที่แล้ว

      Yes you can. But would depend on the approval of your Programme from the Engineer wherein the procurement schedule of the materials are mentioned.

  • @dama4316
    @dama4316 3 ปีที่แล้ว +1

    What if you dont have the Delivery Notes? Is there any contractual or legal implication if the delivery notes are not available to support the MOS claim?

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  3 ปีที่แล้ว

      As per FIDIC Clause 14.5 Plant and Materials intended for the works, documents required for the clain has been specified. But if engineer can be convinced that the delivery notes are missing and the material is actually intended for the project then you may. But i would advise to keep all these documents properly documented and safe.

  • @nifasmazook2317
    @nifasmazook2317 2 หลายเดือนก่อน +1

    Could you please send me the template

  • @john21219811
    @john21219811 3 ปีที่แล้ว +1

    Can we use the rate as per boq instead of the purchase rate in case the contractor does not want to disclose the purchase amounts?

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  3 ปีที่แล้ว +1

      If BOQ has a separate Material rate for each item, then depending on the Client/Consultant requirement you can. Usually major items are only claimed under MOS.

    • @john21219811
      @john21219811 3 ปีที่แล้ว

      @@QuantitySurveyingStudio I believe that is why they fix a percentage in the appendix to form of tender for MOS , so we can claim that percentage of the boq value , we have done this in many projects

    • @nixsteo9398
      @nixsteo9398 2 ปีที่แล้ว

      Usually Appendix is 100% if not stated. Please check Pam form.

  • @jumeenmohamed6589
    @jumeenmohamed6589 2 ปีที่แล้ว

    Here if a material is claimed under MOS 1 and not used until MOS 2...Will it claim again in the MOS 2?

  • @abysebastian1587
    @abysebastian1587 3 ปีที่แล้ว

    In this video you are showing after the material is installed 100% claim is made.
    But in your experience whether the Client/consultant will approve 100%claim?
    In my experience they will hold 5 to 10% amount till Final testing and commissioning is over.
    Especially in the case of Cables.
    Please reply

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  3 ปีที่แล้ว

      Hi Aby. I have mentioned in the video that percentage of claim will depend as per contract condition and used 80% in the example too.

  • @ismalebbemohamedjaleel838
    @ismalebbemohamedjaleel838 3 ปีที่แล้ว

    Hi, Thanks please can you explain how to recover of MOS

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  3 ปีที่แล้ว +1

      MOS is just for cash flow purpose. It gets deducted/added in each monthly payment application based on stock & consumption. Finally reduces to 0.

    • @ismalebbemohamedjaleel838
      @ismalebbemohamedjaleel838 3 ปีที่แล้ว

      Many Thanks for the reply

  • @ppakbarali
    @ppakbarali 3 ปีที่แล้ว

    Why we need to disclose the material rate to Client/Consultant?

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  3 ปีที่แล้ว

      Claiming MOS is totally upto the contractor. If they don't intend to diclose their rates then they may not claim it. At the end of the day all rates are already fixed and contractually binded.

  • @tariqaziz6643
    @tariqaziz6643 2 ปีที่แล้ว +1

    please send me this brilliant sheet ,

    • @QuantitySurveyingStudio
      @QuantitySurveyingStudio  2 ปีที่แล้ว

      Sure. Share your email id here or in any of my social media accounts.

  • @musharrafsiddiqui9804
    @musharrafsiddiqui9804 ปีที่แล้ว +1

    Provide me the above sheet

  • @euginemulundu5347
    @euginemulundu5347 ปีที่แล้ว +1

    me

  • @emmanuelchilemba6583
    @emmanuelchilemba6583 2 ปีที่แล้ว

    Please send me this brilliant sheet 👏