Resource Allocation & Leveling - Project Management - Tutorial & Example

แชร์
ฝัง
  • เผยแพร่เมื่อ 9 เม.ย. 2019
  • Resource allocation and leveling are important parts of any engineering project. Learn them from this tutorial and example!
    -----------------------------------------------------------------------------------------------------------
    Now try to solve it on your OWN! Don't just "understand"... PRACTICE!!
    -----------------------------------------------------------------------------------------------------------
    AF MATH AND ENGINEERING - Students Helping Students!
    Join our Community! =)
    -------------------------------------
    Follow us on Twitter at / afmatheng
    Follow us on Facebook at AFMath1/?fre...
    #math #civilengineering #engineering #education #edchat #lrnchat #blendchat #mlearning #elearning #ipadchat #pblchat #passiondriven #blendedlearning #ccchat #ccss #commoncore #competencyed #curriculum #deeperlearning #digln #earlyed #edapp #eddata #edleaders #edpolicy #edtech #education #elearning #highschool #leadership #middleschool #literacy #engchat #mathchat #scichat #stem #highered #calculus

ความคิดเห็น • 29

  • @adityapatel8701
    @adityapatel8701 2 ปีที่แล้ว +10

    As activity E depends on completion of activity C. It is not possible to keep both on same day. To lower the labor demand we will have to extend the duration of the project by one day.

  • @talk2minie
    @talk2minie 3 ปีที่แล้ว +5

    This was very helpful! I was able to complete my course homework thanks to your explanation.Thank you very much!

  • @Chichi-ez1xo
    @Chichi-ez1xo 2 ปีที่แล้ว +3

    My goodness!!! Where have you been the last 2 years of my life?!!!!!! Thank you Thank you very much! this was very helpful, well detailed and specifically explained!

  • @vp-xk3rt
    @vp-xk3rt 4 ปีที่แล้ว +4

    Thank you sir

  • @Orthodox19.
    @Orthodox19. 2 ปีที่แล้ว

    Your explanation is very accurate and to the point i.e it was very easy to understand SO Keep it up !!!@

  • @anhtruong2636
    @anhtruong2636 2 ปีที่แล้ว +1

    Very good and funny videos bring a great sense of entertainment!

  • @navnithrajsn1705
    @navnithrajsn1705 3 ปีที่แล้ว

    Very nicely explained thanks

  • @benyang6546
    @benyang6546 2 ปีที่แล้ว

    so touching for an excellent video

  • @quizzlerprofessor
    @quizzlerprofessor 3 ปีที่แล้ว +1

    Helpful content thanks

  • @andrewmurschel2608

    This also makes the assumption that task C can pause once started. Bear in mind that some tasks cannot pause like that without negative facets.

  • @mongezinkandi6544
    @mongezinkandi6544 21 วันที่ผ่านมา

    Can you please clarify this for me, the task C part that you reallocated to day 13, how did you do it, hence the task E depends on tasks C and D?

  • @btpex536
    @btpex536 ปีที่แล้ว +2

    Sir actually there is a mistake as C latest finish time is 12 but u took it too 13 which is not correct.

  • @elizemach
    @elizemach 3 ปีที่แล้ว +6

    LF of activity C is day 12 - and you alocated it to day 13???

  • @SadamHussain-yx4sl
    @SadamHussain-yx4sl ปีที่แล้ว

    Thank you for solution. Sir, I little bit confusion here because, we have Total Flot of activity C is 4, but we shift labour (8) five time why?

  • @balamuruganr6840
    @balamuruganr6840 3 ปีที่แล้ว

    If i want to use all 15 labors every day, what should i do? Thanks in advance.

  • @samuelbabarinsa8044
    @samuelbabarinsa8044 4 ปีที่แล้ว +7

    but C is a predecessor of E so if the last activity of C comes to the day when E is meant to start, that means E cant start, because C has not finished .....what do you think?

  • @ahmeddesoky3599

    Thank you for the effort. I've noticed that the date you used in your example are not that precise. At the end you'll end up extending the project by 1 day.

  • @AFMathandEngineering
    @AFMathandEngineering  5 ปีที่แล้ว +5

    At the end of the video we place Task 'C' and Task 'E' at the same day. As this is a Start to Finish relationship we can assume that the work will first start with assignment C and only once 'C' is done 'E' will start. We can do that as long as the question/project permits us to perform two tasks at the same day. when you think about it, it makes sense that first we pave and only later we demobilize. However, if we would have a curing time that requires a day or the question would specify that only one task is allowed per day we would have to further allocate the task. If this would be the case we would probably delay the project by one day.

  • @samratparajuli6032
    @samratparajuli6032 2 ปีที่แล้ว

    muhaah !!!

  • @saharincuker7718
    @saharincuker7718 4 ปีที่แล้ว +1

    Excellent Video! Sorry for chiming in, I am interested in your thoughts. Have you considered - Teannah Psychic Sucker (Sure I saw it on Google)? It is a good one off product for finding the best project management and business templates minus the headache. Ive heard some interesting things about it and my coo-worker after many years got amazing results with it.