Resource Leveling & Smoothing - PMP - Learn in 3 minutes

แชร์
ฝัง
  • เผยแพร่เมื่อ 11 ธ.ค. 2024

ความคิดเห็น • 28

  • @_SriyaKanneganti
    @_SriyaKanneganti 11 หลายเดือนก่อน +1

    explained in 2 minutes what most 20+ videos are not able to. really grateful

  • @farhanamjad6046
    @farhanamjad6046 3 ปีที่แล้ว +2

    Very well explained in short time Resource leveling is used when limits on the availability of resources are paramount. Resource smoothing is used when the time constraint takes priority. The objective is to complete the work by the required date while avoiding peaks and troughs of resource demand. Resource smoothing is another project management tool for optimizing your resources that adjusts the activities of your schedule, so resources don't exceed the limits already pre-defined during the planning.

  • @Urmy998
    @Urmy998 2 ปีที่แล้ว +2

    Amazingly explained, and I would like to kindly ask if you can reexplain the same slides in a bit longer time and more details. That would be awesome.
    Thank you.

  • @aqashali8962
    @aqashali8962 3 ปีที่แล้ว

    Very well explained in such a short time, Resource Leveling and Resource Smoothing are the techniques that are used for Resource Optimization in a project. The main objective of resource leveling is to allocate the resources Efficiently to complete the project with in the given time limit. By using resource leveling, We can minimise wastage of resources, prevent over or under allocation of resources and Manage the supply and demand of the resources. But it increases risk because rearranging the activities may cause rework or it may rearrange the project as well.
    Whereas Resource Smoothing is use to optimize the resources without affecting the project Duration. It is more focused on maximum utilization of the resources.

  • @tayyabfaheem3784
    @tayyabfaheem3784 3 ปีที่แล้ว +1

    Resource Leveling is used when scheduling the production of available resources are limited and need to be used optimally and Resource Smoothing is used when time constraints are the biggest factor blocking production. The idea is to finish a project on time while avoiding peaks and dips in resource demand.
    Resource leveling is usually scheduled first and resource smothering is often performed after resource leveling in resource leveling the finish dates of the project can be changed whereas in smoothing the finish date remains the same

  • @MominSubhani
    @MominSubhani 3 ปีที่แล้ว

    Thank you very much Sir. Numan for making and sharing such valuable video to under stand basics of resource optimization. This would be highly recommended for beginners in project management. I appreciate for this video.

  • @amtulamna0
    @amtulamna0 3 ปีที่แล้ว

    Resource leveling techniques are closely related with critical path calculations. For that reason, total float, activity sequences and logic of the network diagram effect the required resource quantities per time. Resource Leveling, called Resource Leveling, is a technique that avoids over-allocation. Resources are taken from non-critical activities and allocated to critical activities.
    Resource smoothing is defined as a technique that adjusts the activities of a schedule model so that all requirements for the resources do not go beyond the resource limits already pre-defined during the planning.
    Resource smoothing is used when the time constraint takes priority. The objective is to complete the work by the required date while avoiding peaks and troughs of resource demand. Resource levelling is used when limits on the availability of resources are paramount. It simply answers the question ‘With the resources available, when will the work be finished?.

  • @engineerabdulsamadkhan1866
    @engineerabdulsamadkhan1866 3 ปีที่แล้ว +1

    Sir,Fabulous self explanatory topic video.. resource smoothing method is very much helpful and is working for managing multiple ongoing activities and maximizing the Efficiency of any organization...I m pretty much astonished and we'll informed about gantt chart too after watching this informative video.thanks sir..regards Abdul samad khan SAP ID 23209

  • @xuattrieutrieu3879
    @xuattrieutrieu3879 2 ปีที่แล้ว

    Very good and funny videos bring a great sense of entertainment!

  • @hussainmuhammadasadullah2645
    @hussainmuhammadasadullah2645 3 ปีที่แล้ว

    The schedule of the project modified to best use the resources allocated to the project activities. It needed when there is resource constraint. And required resource smoothing.
    The two resource optimization techniques are:
    a) Resource leveling
    b) Resource smoothing
    Resource leveling is a resource-limited scheduling technique, while resource smoothing is a time-limited scheduling technique.
    By managing the total float of the non-critical activities, we can optimize the resources.
    Resource constraint is when the project activities required more resources per day and have fewer resources available to allocate.
    Resource Leveling: it used when fewer resources are available to utilize per day. May affect the critical path.
    Resource Smoothing: the activities modified within their float times without changing the critical path or project end date.

  • @hassansaleemmughal8605
    @hassansaleemmughal8605 3 ปีที่แล้ว

    Ref above video activities are usually first sequenced and assigned resources based on the dependencies between different activities either mandatory or discretionary dependencies.
    Resource Leveling: Resource Leveling is a resource optimization technique in which the Project Manager adjusts the start dates and finish dates of different activities in order to balance the demand for resources vs available supply.
    - Resource Leveling is always carried out first
    Resource Smoothing: Resource Smoothing is a resource optimization technique in which the Project Manager adjusts the timing of different activities so that the requirement for resources does not exceed a certain pre-defined limit.
    - The pre-defined limit may be statutory or a company policy, e.g. no more than 38 hours’ work in a week

  • @engineerabdulsamadkhan1866
    @engineerabdulsamadkhan1866 3 ปีที่แล้ว

    Very much informative video

  • @jyotinegi7413
    @jyotinegi7413 2 ปีที่แล้ว

    Leveling Project-in what manner it should be executed ? at original time or cost ? or minimum amount of time or minimum amount of cost?

  • @ZakirKhan-io3lc
    @ZakirKhan-io3lc 3 ปีที่แล้ว

    Great explanation Sir,
    In this video we have Resource Optimization techniques which have 2 parts and difference between these two are , In Resource leveling it may impact the critical path while in Resource smoothing it does not impact the critical path .
    Resource usage profile shows how different resources are assigned to different activities .
    This method is very helpful for managing multiple activities at a same time for the betterment and efficiency of organization ...
    Muhammad Zakir 22866

  • @ganeshbhaushelar4244
    @ganeshbhaushelar4244 2 ปีที่แล้ว

    「もっと多くの人が必要なので、このビデオをもっと

  • @Abbas-es1rk
    @Abbas-es1rk 3 ปีที่แล้ว +1

    I like it 👌

  • @muhammadijazkhan4504
    @muhammadijazkhan4504 3 ปีที่แล้ว

    Very well and explainatory video of Sir Engr Nouman , really in a very video he explained the concept of Resource leveling and Resource smoothing
    Thanks for clear my concept
    Muhammad Ijaz Khan SAP ID 29949
    MsPM

  • @hamidb9016
    @hamidb9016 4 ปีที่แล้ว

    Great explanation

  • @muhammadzeeshan8229
    @muhammadzeeshan8229 3 ปีที่แล้ว

    It was really an informative video. I have got clear my concept by watching all the stuff shared in that video. The method of teaching is also faboulus, simple and understandable.
    Refferred by Anam Akbar.
    Sap ID: 27935
    Student of riphah international university of project management program.

  • @Nasirbashirchauhdary
    @Nasirbashirchauhdary 4 ปีที่แล้ว

    Great explanation sir

  • @pmpbatais1196
    @pmpbatais1196 ปีที่แล้ว

    nice work, but sound needs to be improved

  • @anumakbar6437
    @anumakbar6437 3 ปีที่แล้ว

    resource leveling and resource smoothing explained very good in less timee i appreciatee your effforrrt sir 🤝
    anam akbar 27935

  • @amnatabbsum5606
    @amnatabbsum5606 3 ปีที่แล้ว

    Well informed by Gantt chart, very informative video for improving efficiency of organization by managing multiple ongoing activities at the same time.
    Amna tabassum
    23815

  • @sidoubojang7766
    @sidoubojang7766 2 ปีที่แล้ว

    「もっと多くの人が必要なので、このビデオをもっと

  • @ayeshagull3326
    @ayeshagull3326 3 ปีที่แล้ว

    It was really an informative video. I have got clear my concept by watching all the stuff shared in that video. The method of teaching is also faboulus, simple and understandable.
    Refferred by Anam Akbar.
    Sap ID: 27935
    Student of riphah international university of project management program.

  • @ayeshagull3326
    @ayeshagull3326 3 ปีที่แล้ว

    It was really an informative video. I have got clear my concept by watching all the stuff shared in that video. The method of teaching is also faboulus, simple and understandable.
    Refferred by Anam Akbar.
    Sap ID: 27935
    Student of riphah international university of project management program.

  • @katedragonite7620
    @katedragonite7620 2 ปีที่แล้ว

    「もっと多くの人が必要なので、このビデオをもっと

  • @adiikhandrofdx7991
    @adiikhandrofdx7991 3 ปีที่แล้ว

    It was really an informative video. I have got clear my concept by watching all the stuff shared in that video. The method of teaching is also faboulus, simple and understandable.
    Refferred by Anam Akbar.
    Sap ID: 27935
    Student of riphah international university of project management program.