Total Float represents the amount of time a task can be delayed without affecting the completion date of the project, while Free Float represents the amount of time a task can be delayed without affecting the start date of its subsequent tasks.
I am happy to say that I understood the value of Power Query from Mr. Hany and I could say Eng. Khalid Shah have covered lot many things from his 2 years of experience. Best wishes for him.
Thank you. It's a valuable interview.
Keep it up boss , I enjoy really watching your videos.
Wishing the best for eng.salah.
Thank you, I will
Thank u sir hani and engr Khalid for sharing knowledge
Amazing 💙💙
Hope more interviews like this 👋
sir thank you so much for gives us such information
its really really helpfull for us
basically you explain the basic and practical with knowledge related to planning
Nice interview Mr.Hani from Hani P.E. from Bahrain
First question is answer :
1- contract
2- BOQ
3- shop drawings
4-specifications
Good expérience.thx
Thank you from morocco 👍
I wish to take part in one session. Good question.
You are welcome. You can join from this link: planningengineer.net/planning-engineer-interview-challenge-pass-or-fail/
Good one .
Thanks
Basically you must understand the scope first.
Very good interview session...
Thanks
Sir please explain the difference bw free float and total float
Total Float represents the amount of time a task can be delayed without affecting the completion date of the project, while Free Float represents the amount of time a task can be delayed without affecting the start date of its subsequent tasks.
👍👍👍