  • The design of the 2010 Ryder Cup Course at the Celtic Manor Resort involved various challenging factors for the design team, not least the issues associated with catering for over 40,000 spectators per day! Safety, corporate hospitality, vehicular and spectator movements, logistics and viewing all had to be considered in creating a fantastic venue for all those attending and participating in what is considered to be one the world's largest sporting events.

    To satisfy spectator viewing, the final three holes were designed to sit within dramatic amphitheatres on the side of a steep hillside overlooking the golf course. The creation of these holes involved cuts of up to 10m deep through rock, and on the 18th hole alone 350,000m³ of material was moved to form the golf hole, as well as the large platforms where hospitality units capable of entertaining 3,000 people at a time are located. This vast amount of material was then used to build up and raise flatter, poorly drained areas at the bottom of the valley to accommodate the main tented village and the newly designed holes 1-5 alongside the River Usk. A new lake was also created to enhance the strategy of the par 3, third hole, with the extra material generated from this excavation also utilized in the shaping of the course.
    Throughout the design process amendments were made to incorporate the location of water mains, gas mains and overhead power cables. Also during construction, areas of important archaeological interest were discovered which meant inovative design solutions had to be found to prevent delays in the construction schedule, without impacting on the overall quality of the golf course.
    3d Modelling Software was used extensively throughout the design phase of the Ryder Cup Course to accurately calculate cut and fill figures and generate sections of the various design adjustments the site conditions presented. Data was exchanged efficiently with the Contractor and Surveyor on site so that the construction accurately followed the design. 3D visualisations proved invaluable as the course could be viewed from any angle or height, reassuring the design team the new changes would provide maximum spectator enjoyment and allowing the client to understand the nature of the proposed work. In addition, once rendered, the 3D models were able to be used in marketing and promotional work for Celtic Manor Resort before the course took shape.

ความคิดเห็น • 1

  • @Yahooooogle
    @Yahooooogle 15 ปีที่แล้ว

    Wow! What a great course it will be for holding events, especially the 2010 RC...
    I think that 350,000 cut/fill on a single hole is about a world record... & blasting through 10m of rock perhaps another!
    Using 3d modeling software to calculate real-time cut/fill would have been an invaluable resource on this course. The days of hand-drawn contours are almost behind us with all these new technologies (eg. Landshaper Golf is great for real-time contour manipulation)
    Can't wait for the event...