Very informative. Just one correction though, the calculated accomplished amount for the exterior walks under Masonry should be 62,400 (i.e. 0.52x120,000=62,400) rather than 62,000. The total accomplishment amount should be updated. Love your site and I’m a constant follower. Thanks.
@@danmarksalvadorcacatian4889 yes, we just showed calculation of relative weight in case we want to see total percentage of a given project status, and then you can use it also to get relative amount of each line item. Thanks for watching and comment!
Hi sir ask lang po hindi ko po maiintindihan paano po nakuha yon 45% na total nag try po kasi i total yon buo amount then devide ko po sa total amount ng project paano po malalaman kung ilan percent na? Thank you po
@@GianMendoza-e3d you are right, but the accurate way of getting percentage accomplishment is to sum-up relative accomplishment per line item like I showed in the video. Thanks
Very informative. Just one correction though, the calculated accomplished amount for the exterior walks under Masonry should be 62,400 (i.e. 0.52x120,000=62,400) rather than 62,000. The total accomplishment amount should be updated. Love your site and I’m a constant follower. Thanks.
AKO NGA RIN MEDYO NAWLA AKO SIR SA COMPUTATION. PERO MAGANDA ANG PALIWANAG NI SIR PARA SA ATING MGA ENGR..
hello sir im a avid follower on you hope makakusap ko kayo in personal im a new contractor po and sobrang na appreciate ko mga video
Sir pwede ba copy excel yan.
Tolits, kumusta?remember me, Rick Encina?
Ofcourse Rick syempre naman kumusta ka na?
Ok nmn. Umalis n ko sa company since 2017.nag put-up ako sarili ko single prop. Ikaw sir, musta dyan?
Ok nmn. Umalis n ko sa company since 2017.nag put-up ako sarili ko single prop. Ikaw sir, musta dyan?
@@epoencina1495 ayos naman ako dito.
Mas maganda yan self employed. Meron ako fb page pwede tayo mag chat doon.
Hindi ko magets po sir bakit naging 62000 diba po percentage ng qty times relative weight times contract ammount ( 52%x3%x120000)= 1872?
@@danmarksalvadorcacatian4889 yes, we just showed calculation of relative weight in case we want to see total percentage of a given project status, and then you can use it also to get relative amount of each line item. Thanks for watching and comment!
Hi sir ask lang po hindi ko po maiintindihan paano po nakuha yon 45% na total nag try po kasi i total yon buo amount then devide ko po sa total amount ng project paano po malalaman kung ilan percent na? Thank you po
@@GianMendoza-e3d you are right, but the accurate way of getting percentage accomplishment is to sum-up relative accomplishment per line item like I showed in the video. Thanks
LAGPAS KAUNTI SIR, .45X4,000,00= 1,800,000 M
⭐ "promo sm"
1,800,000-.10%= 1,799,999 CORRECT ME IF IM WRONG.
@@VinceNiuda The accurate way is to do it in excel per line item then sum it up. Thanks