  • This Video shows you how to complete the dead testing sequence. It will guide you though testing a lighting circuit and a ring final test.
    C - continuity of CPC
    R - Ring Final
    I - Insulation resistance
    P - Polarity Dead
    P - Polarity Live
    E - Earth Loop Impedance
    R - RCD

ความคิดเห็น • 42

  • @georgebrassington1244
    @georgebrassington1244 2 ปีที่แล้ว +15

    So many oversights on this video. 1 - No Lock off , 2 No supply voltage check with test lamps confirmed working with proving unit. 3 You disconnect main protective conductors to copper pipe work so has not to pick up false readings on R1 + R2 tests via parellel paths. 4 To get a correct R1 + R2 result on the ring main you divide the reading by 4. 5 When doing an R1+R2 test on lighting take a reading from all fittings + switches and record the highest !

  • @pepperthekobold
    @pepperthekobold 5 ปีที่แล้ว +25

    Very helpful, thank you. Just what I needed as a quick refresh before my exam tomorrow.

  • @ifyougetstucklookitup237
    @ifyougetstucklookitup237 ปีที่แล้ว

    excellent summary - thank you

  • @soniajaynefelton5049
    @soniajaynefelton5049 5 ปีที่แล้ว +11

    Surely you check at every point on R1 + R2 test and switch the light switch on and off to prove polarity

  • @petg9473
    @petg9473 5 ปีที่แล้ว +10

    Hi mate great video but could you please do one more in depth, demonstrating how youre setting up your megger for each test and explain the purpose of each test phase of cripper. Thanks again.

  • @jamesoconnor2417
    @jamesoconnor2417 ปีที่แล้ว +1

    Could you do live tests never heard of “CRIPPER” but best video I’ve seen for my am2 not complicated just straight to the point cheers

  • @jamesglover650
    @jamesglover650 6 ปีที่แล้ว +2

    How did u get those results, the first three tests the main switch was on except for the last one, doing my practical, at college and just noticed it

  • @9T9times
    @9T9times 6 ปีที่แล้ว +4

    Would be great if you'd show the actual meter settings and the readings you get.
    What you appear to be doing here is just enacting the CRIPPER testing sequence without actually showing much.
    Sorry if I sound negative, but thanks for the vid. ;)

  • @jackcooper4655
    @jackcooper4655 7 ปีที่แล้ว +2

    Thankyou v helpful

  • @petergambling671
    @petergambling671 3 ปีที่แล้ว

    Excellent thanks you so much

  • @leebrown3895
    @leebrown3895 6 ปีที่แล้ว +1

    Well done dave please could you let us know what setting the testers are on every test, good luck

    • @WVRElectricalTraining
      @WVRElectricalTraining  6 ปีที่แล้ว +1

      Lee Brown i will do this not a problem. Will upload next couple of weeks. Will keep you posted.

  • @edwardcoe8838
    @edwardcoe8838 3 ปีที่แล้ว

    what page shows the correct readings for r1+r2?

  • @izuchukwucollins5687
    @izuchukwucollins5687 2 ปีที่แล้ว +1

    Helpful, could you still complete the pper ?

  • @CommonInvesting
    @CommonInvesting 2 ปีที่แล้ว +1

    For the first test (continuity of cps) do you place ALL cpc's in the connector block? including ring etc?

    • @caincawkwell8092
      @caincawkwell8092 2 ปีที่แล้ว +1

      Remove bonding, everything else can be used via croc. Clips onto earth terminals on DB

    • @CommonInvesting
      @CommonInvesting 2 ปีที่แล้ว

      @@caincawkwell8092 perfect! Thanks for clearing that up

  • @no_short_circuit
    @no_short_circuit 6 ปีที่แล้ว +1

    Good stuff. Please can you do the "live" tests in a future video?

    • @WVRElectricalTraining
      @WVRElectricalTraining  6 ปีที่แล้ว +1

      GrumpyGrampa i will do a live testing video in the next couple of weeks.

  • @Hiccup77
    @Hiccup77 7 ปีที่แล้ว +7

    1st test is. continuity of protective conductor (disconnect cpc from met)
    2nd test is. continuity of main and supplementary bonding conductors (disconnect cpc from met)
    3rd test is. continuity of final rind circuits (no need to disconnect the cpc from the met)

    • @saidtoubi6751
      @saidtoubi6751 6 ปีที่แล้ว +2

      Not done safe isolation!!!

    • @seandempsey7351
      @seandempsey7351 2 ปีที่แล้ว

      Point 2) is wrong testing supplementary bonding , the conductors remain connected at the MET or earth bar .also he should of used a crock clip on one of the test leads and clipped onto the earth conductor to insure a good connection and a good reading

    • @ruaraidhmaccormick4677
      @ruaraidhmaccormick4677 ปีที่แล้ว

      And Bulbs grow in gardens 😅 and he forgets to null leads 😂 not bad for an apprentice tho

  • @AlexEatonPDPIGaming
    @AlexEatonPDPIGaming 6 ปีที่แล้ว

    Hi, could you please do a video finishing the sequence with the live tests

    • @WVRElectricalTraining
      @WVRElectricalTraining  6 ปีที่แล้ว +1

      Alex Eaton i will do a live testing Video in the next couole of week. Ill keep you posted.

  • @yusufrehman2157
    @yusufrehman2157 4 ปีที่แล้ว

    Good effort, can you please make this video with zooming the camera and showing all wires and tester reading

  • @Raf-el4pu
    @Raf-el4pu 5 ปีที่แล้ว +2

    where are live tests?????

  • @easyfix5366
    @easyfix5366 4 ปีที่แล้ว

    Can't see where you are connecting your tester

  • @Robert-ts2ef
    @Robert-ts2ef 3 ปีที่แล้ว

    My only negative comment is that you did not specify what readings you got for each test. Why not?

  • @seandempsey9396
    @seandempsey9396 3 ปีที่แล้ว

    Nothing like an instructor giving a demonstration with his back to you and you can't see what he is doing, maybe I could do a corce at his college and I could then a job and no one would be any the wiser weather or not I have done it properly

  • @jackcahill7746
    @jackcahill7746 ปีที่แล้ว +1

    U never made sure the circuits were isolated and checked they were dead

  • @llVIU
    @llVIU 5 ปีที่แล้ว +2

    mate, I can see that you're working live

  • @brinxmatty1
    @brinxmatty1 5 ปีที่แล้ว

    Ok but as said show results

  • @valentinokennedy7672
    @valentinokennedy7672 3 ปีที่แล้ว +1

    , please don't use this method for your exam or for your job !!!

  • @pblazi
    @pblazi 4 ปีที่แล้ว +10

    This video is a joke. Should've nulled his leads before he started, should've done a safe isolantion before doing anything. He is removing live and cpc conductors while MCB and main isolator is ON and LIVE. Didn't flick the light switch ON and OFF as he was doing his r1r2 at the light circuit. Used a bloody painters ladder. Didn't null the crock clips before doing end to end on ring. IR at 500V he tested between the Live and the entire Netral bar instead of removing the Neutral from the circuit in question, while still having a bulk head with a light still on above the dis board. Don't do what this guy is doing under exam condition. You're bound to fail.

    • @Tryingtimes007
      @Tryingtimes007 4 ปีที่แล้ว

      painters ladders 😂 first thing i noticed.

    • @oldgrunger5
      @oldgrunger5 4 ปีที่แล้ว

      Might be a great Idea to also confirm polarity before energizing the circuit and operating the switches on the ring final circuit ...just saying ! 😎

    • @oldgrunger5
      @oldgrunger5 4 ปีที่แล้ว

      Also Ive always taught to verify continuity of cpc at every point served on the lighting circuit

    • @zumber2811
      @zumber2811 3 ปีที่แล้ว +1

      Pretty sure he is JUST showing how to test it and which conductors to connect/cross-connect.

  • @colintatum6872
    @colintatum6872 5 ปีที่แล้ว +3

    As clear as mud unless you’ve prior experience. Crap.

  • @colinhumphryes5664
    @colinhumphryes5664 5 หลายเดือนก่อน

    Poor