Boring Co Tunnel Progress, Electric Upgrades, DIE load sys! 15 Nov 2024 Giga Texas Update (07:45AM)

แชร์
ฝัง
  • เผยแพร่เมื่อ 11 ม.ค. 2025

ความคิดเห็น • 93

  • @kendiener9465
    @kendiener9465 หลายเดือนก่อน +26

    Joe, Thank you for including me in your video. I am the one in the safety vest and hardhat walking towards the camera by the tunnel in the inside of SX. Time Stamp 2:21 You put the yellow arrow over me. :). I sold them doors for the Data hall.

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน +5

      @@kendiener9465 👍😎 sorry about the arrow 😎

  • @mycalltoadventure9712
    @mycalltoadventure9712 หลายเดือนก่อน +10

    I know watching daily sometimes it’s hard to see changes. I just went back and watch videos from 1 year, 2 years, 3 years etc. it’s amazing to see that just over 4 years ago the site was basically a swamp.
    Thanks for all the videos Joe!!

    • @DessieDoolan
      @DessieDoolan หลายเดือนก่อน +2

      An impressive achievement!

  • @highlanderapparel
    @highlanderapparel หลายเดือนก่อน +2

    Thank you, Joe. I don’t get to watch your videos often but I do enjoy them. The Highlander PS is always remember. Kindness is always free, but I got a feeling you’re the kind of guy that doesn’t need to be told that.😊

  • @DavidJohnson-tv2nn
    @DavidJohnson-tv2nn หลายเดือนก่อน +9

    Thanks Joe!
    Tunnel entrance/exit:
    Inside the building:
    @ 2:21 Excellent view of the inside entrance! Thanks Joe!
    West side:
    @ 6:17, 6:20 and 6:33 Forms being built for retaining walls.
    @ 7:03 Newly paved roads to connect the tunnel to the EOL facility.
    Possible Megapack site:
    @ 24:05 Site is getting much bigger. Continuing to raise the grade.
    @ 24:22 (Bottom right) Two vaults that provide power to the Cathode building/Die Shop may end up inside the new site.
    Also @ 24:22 Joe.... If those transformers are used here there will be Megapacks. Transformers in this area would be of no use with out the Megapacks due to the low secondary (output) voltage of 480/277 volts. But... It does match the input/output voltage for the Megapacks, which is 480 volts.
    Substation expansion project:
    @ 24:56 (Bottom left) Rebar cages for footings to support switch and busbar structures on the medium voltage (secondary) side of the transformer.
    Red square marked in the dirt is for a pad to support a medium voltage circuit breaker set.
    @ 25:14 Gravel spread around the new footings and circuit breakers.
    Rooftop cable trays:
    Data center:
    @ 4:35 Cables in the tray to the right (only the cable tray on the right) going through the roof are energized and providing temporary power to the date center. Power comes from the existing main switchgear room below the roof in the casting/BIW area.
    North end:
    @ 21:55 and 22:14 Ongoing work to pull cable on the north end. 24 cables per tray, 48 total.

    • @WarrenLacefield
      @WarrenLacefield หลายเดือนก่อน +1

      I have been thinking that those 480v transformers were for going from middle voltage to the voltage needed by the Cortex racks/bays. But now it sure does seem more likely they are for 2-way power flow between the (new) megapacks and the mid-voltage feeds. As you pointed out (here and in a previous post), there are 16 3-phase feeds in the roof-top cabling. I've thought these were middle-voltage. It would seem a long way for wire to go for such high power needs at low voltage.) Now wondering where and how the Cortex bay stepdown does occur? (Maybe in some other switchgear room?) Heck, I just need a schematic diagram to remember what is going on as the infrastructure construction continues and reveals.

    • @DavidJohnson-tv2nn
      @DavidJohnson-tv2nn หลายเดือนก่อน

      @@WarrenLacefield Rooftop cable trays.....
      Correct, all 16 3-phase feeds on the roof are medium voltage. Either 24.9 or 34.5 kV. There is no other way to transmit that much power over that distance. Which is Why Joe is wrong when he suggests @ 24:22 that there may transformers and possibly additional Megapacks at the new construction site. Transformers would never be placed here by themselves. It is either both of them together or none of them. Just like at the existing Megapack yard.
      Data center transformers.....
      You are also correct that there will be transformers of some type in the data center. The medium voltage must be reduced down to 480 or 240 volts.
      Switchgear room....
      The main switchgear room I'm referring to in my comment above is located in the east side of the factory in the area where Casting meets BIW. It is also the same area where the existing main power duct-banks bring power into the building. The switching would be medium voltage.
      Possible new substation....
      Based on a contractor present at the site and the need for 500 MW.... Speculating that there is the possibility they may build a new substation as well. Again pure speculation.
      See my replies and other replies under Dessie's comment.

    • @WarrenLacefield
      @WarrenLacefield หลายเดือนก่อน +1

      @@DavidJohnson-tv2nn Yes, roof-top cables medium voltage. We do not know actually what the other set of transformers might be for (and apparently no transformers on the roof - and inside would seem a waste of space). So maybe there are other ways and plans for stepping down to the Cortex bay power requirements and distribution to the bays - perhaps some kind of solid state power devices rather than transformers. Like a switchgear room above the computer cluster and its cooling pipes.
      Your speculation about the substation(s) and the grid feeds does seem to me to be a reasonable one. I have fretted about the eventual power requirements for Cortex myself and you about protecting the grid from large demand rapid fluctuations, etc.

    • @DavidJohnson-tv2nn
      @DavidJohnson-tv2nn หลายเดือนก่อน +1

      @@WarrenLacefield Data center power....
      Guessing that Solid State Transformers (SSTs) may be a possibility. Hoping we get lucky and the drone will catch a view of whatever they bring in there.
      Large batch of 102 transformers being stored on the west side.....
      Brad's video 8/17/24 at the 7: 45 time stamp shows an excellent view of the transformer ratings....
      34500 V
      4800 kVA
      Joes photos 11/16/24 shows an excellent view of the existing Megapack transformer ratings....
      24900 V
      4800 kVA
      They have the exact same power rating of 4.8 MW (4800 kVA = 4.8 MW at a power factor of 1).
      Another indication that the transformers are intended to be used for Megapacks someplace.

    • @DavidJohnson-tv2nn
      @DavidJohnson-tv2nn หลายเดือนก่อน +1

      @@WarrenLacefield F-ing TH-cam! Second try at posting.....
      Guessing that Solid State Transformers (SSTs) may be a possibility. Hoping we get lucky and the drone will catch a view of whatever they bring in there.
      Large batch of 102 transformers being stored on the west side.....
      Brad's video 8/17/24 at the 7: 45 time stamp shows an excellent view of the transformer ratings....
      34500 V
      4800 kVA
      Joes pictures 11/16/24 shows an excellent view of the existing Megapack transformer ratings....
      24900 V
      4800 kVA
      They have the exact same power rating of 4.8 MW (4800 kVA = 4.8 MW at a power factor of 1).
      Another indication that the transformers are intended to be used for Megapacks someplace

  • @jonathanlanglois2742
    @jonathanlanglois2742 หลายเดือนก่อน +1

    18:50 Rather than being additional connections, it might just be a bypass. Pipelines of that size can't be shut down as easily as smaller distribution pipelines. More often than not, the work has to be carried out while the pipeline is under pressure. To do so, they build a temporary bypass, they insert plugs at both ends of the work zone and do the repair. Once completed, the bypass is removed. A plug is inserted in the connections that were used for the bypass, but the T junction remains.

    • @DessieDoolan
      @DessieDoolan หลายเดือนก่อน +1

      18:50. That's correct, no additional connections. Bypassing a section of the existing pipeline as a means of replacement.
      You may remember large lengths of pipeline were replaced in this pipeline easement in 2021. Day 379 to day 451. Possibly this same pipeline as there are only 2 in the easement.

  • @nanaimoshoerepair
    @nanaimoshoerepair หลายเดือนก่อน +4

    Hey Joe, Have fun at the launch, can't wait to see the coverage.

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน

      @@nanaimoshoerepair 👍🚀

  • @accumapmodels
    @accumapmodels หลายเดือนก่อน +4

    Thanks Joe! Have a great trip down! Can't wait for Starship launch Monday! Hopefully TS Sara will continue moving slow and not interfere.

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน +2

      @@accumapmodels thx and I’m watching the weather too … would not be surprised to see a slip to Tuesday

    • @benguthrie49
      @benguthrie49 หลายเดือนก่อน +1

      @@JoeTegtmeyer I'm hoping for Tuesday. I'm taking my wife out for a birthday dinner Monday.

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน +1

      @ you got your wish! Launch is officially Tuesday, 19 Nov!

    • @benguthrie49
      @benguthrie49 หลายเดือนก่อน +1

      @@JoeTegtmeyer Thanks Joe

    • @accumapmodels
      @accumapmodels หลายเดือนก่อน

      @@JoeTegtmeyer you correctly predicted a slip to Tues, tho maybe not weather related. Hope the views are amazing!

  • @benguthrie49
    @benguthrie49 หลายเดือนก่อน +4

    Thanks Joe, have fun at Starbase.

  • @bimmergeezer
    @bimmergeezer หลายเดือนก่อน +3

    Thanks for completing my week, Joe! See you in a couple of days!

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน +3

      @@bimmergeezer 👍🚀

  • @ohtoah
    @ohtoah หลายเดือนก่อน +4

    The pavement markings are for semi trucks to enter and exit thru the extension so thet they can unload steel coils in the stamping area,

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน +1

      @@ohtoah 😂😂

  • @awsdfsdgf34
    @awsdfsdgf34 หลายเดือนก่อน +4

    The purple pipe is for non-potable water, normally reclaimed

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน

      @@awsdfsdgf34 irrigation

  • @DessieDoolan
    @DessieDoolan หลายเดือนก่อน +9

    Thanks Joe
    *Sort by Newest First or Top Comments if only the first few lines are visible*
    1:41. Westside, Tunnel Project. Curved retaining wall formwork for the entry ramp. Slightly narrower than the tunnel diameter, but only needs to be the tunnel road surface width.
    4 bored shafts, 2 either side of the tunnel for some sort of canopy. Shaft is very close to the NG pipeline. 6’ to 8’ 1.8m to 2.4m. Centre left, rebar cages and yellow form tubes for the shafts.
    Right. 8 more bored shafts in the same configuration as those bottom right. Relocating perhaps.
    2:05. W-WOW yard. Reclaiming the Tunnel Project site. Quite an elevation/grade difference.
    3:26. Temporary switchyard site. Earthworks now extend south of the old site. This area is natural soil, was never strip mined. May only require compacted fill. Fill being extracted from the right.
    9:24. Westside, storage north. Stacks of flat plate in amongst the steel.
    13:06. Flagpoles. White base covers never got installed. Must have been satisfied with the concrete finish.
    Blue surveyors flags in amongst the Cybertrucks. More digging.
    13:37. GA, loading platform. Delivery of floor decking.
    14:00. Southend, west. 8000gal. grease trap installed for the second time. See Joe’s 9 August video at 4.02.
    16:11. Southend, east diagonal corner. Level 1. Installed the glazing channels on the retaining wall.
    Level 2 perimeter beam. Welding on the brackets for the glazing channel.
    18:32. Cyber Circle, pipeline works. Replacement pipe section connected at south (18:01) and north (top right).
    Loading up the hot-tapping gear on a trailer.
    18:50. Southend, east. Under the mezzanine is a road entrance. Arrow pointing westwards. Likely the other end of the road at 13:51. Likely used for general access through the building, including to Stamping 2.
    20:33. East Main Entrance. Bottom left. HVAC system removed (the orange ducting). Stacks of circular components on the loading dock ramp.
    20:50. Casting, east. Apron. Bottom left. Orange over-width trailer. Might be the one seen at the Die Shop in Joe’s 13 Nov video at 27.43. Likely method of transport dies back and forth to the Die Shop.
    21:03. Casting, east. Canopy. Red and black rail mounted framework, no apparent advance. Lots of hydraulic/air lines visible in Joe’s photos.
    Furnace charging machine likely.
    Silver/grey components on the apron may be the charging bins to be assembled on the red and black frame.
    22:03. Casting roof. Furnace gases visible from the flue.
    23:45. BESS site. Bottom left. Small trailer with the Saber Power logo. I can’t access the website, been geo-blocked. Likely the switchyard/substation contractor. Another trailer at 25:24.
    ‘Engineering-led & construction-focused professional services company specializing in complex medium & high voltage electrical infrastructure.’
    26:36. Crash Test Track. Semi wheels/tyres have been removed.
    27:42. Cathode, west. Plant platform. North of. Stormwater drainage works. Installing a catch basin/pit for the tank overflows.
    28:41. Die Shop, west. Left. Blue tarp was previously covering a trailer. See 20:50.

    • @Gig0Surf
      @Gig0Surf หลายเดือนก่อน +1

      Perhaps try opera browser, it has free VPN built in which might get your around geo-blocked sites

    • @DessieDoolan
      @DessieDoolan หลายเดือนก่อน +3

      @@Gig0Surf I've considered a VPN. I don't feel tech savvy enough to be confident about installing it.
      I was able to get around the geo-blocking by looking at their linkedin page. Pretty sure they are the switchyard/substation contractor.
      Last time I was geo-blocked with a company associated with this project was the rubbish disposal company.

    • @Gig0Surf
      @Gig0Surf หลายเดือนก่อน +2

      @@DessieDoolan Yes they appear to provide power related engineering, construction, maintenance and field services for utilities, bess/renewables, industrial/commercial, etc... Their engineering covers Electrical substation, industrial power system, transmission and distribution line experts

    • @DessieDoolan
      @DessieDoolan หลายเดือนก่อน +2

      @@Gig0Surf Fairly certain the trailer by the control building at 25:24 is one of theirs also. Same typeface on the logo.
      The company name seems familiar, but no mention in the database. Don't know where I would have seen it other than here.

    • @DavidJohnson-tv2nn
      @DavidJohnson-tv2nn หลายเดือนก่อน +3

      23:45 Since the company does both substation and BESS engineering work... Just curious if the new site could be for a new substation to tap the west transmission line circuit seen here @ 23:58 (Left) Currently, they are using only the east transmission line circuit to power everything. By 'west' I mean the west circuit on the west towers.

  • @PCMenten
    @PCMenten หลายเดือนก่อน +6

    Have a great trip!

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน

      @@PCMenten thx

  • @lourdessilva6442
    @lourdessilva6442 หลายเดือนก่อน

    Sem palavras esse documentário incrível apresentação acompanho seu trabalho desse o começou ah mal posso esperar para assistir o próximo da empresa dos foguetes nunca vou esquecer da apresentação do vídeo da subida do foguete muita emoção es como estivesse lá com vcs incrível mesmo sucesso sempre

  • @w3072
    @w3072 หลายเดือนก่อน +4

    good job

  • @andreandre1051
    @andreandre1051 หลายเดือนก่อน +2

    Merci👍👍👍

  • @rb8049
    @rb8049 หลายเดือนก่อน +1

    Looking forwards to the concrete panels painted white and pavement and grass growing!

  • @jimclester4754
    @jimclester4754 หลายเดือนก่อน

    Holyeee Smoke, hey there is a hole under the highway.

  • @garthbews4863
    @garthbews4863 หลายเดือนก่อน

    woot woot see who.. winks..enjoy.. spaceport

  • @Fred-w5r
    @Fred-w5r หลายเดือนก่อน +1

    Does Tesla not make giga castings when manufacturing cars? Would this be due to air “pollution”. Would the baghouse air filter allow them to make giga castings and car assembly at the same time?

    • @DessieDoolan
      @DessieDoolan หลายเดือนก่อน +3

      The baghouse is primarily to filter flue gases from the 3 new furnaces.
      Existing furnaces have smaller baghouses inside the Casting building.
      The Casting building is almost sealed off from the rest of the factory. There are some large doors into BIW.
      The rooftop ducted fan units are used to draw fresh air into the building via the louvres on the east side (replaced some windows), and exhaust the air through filter units downstream of the fans.
      Those filters are changed often. In the video at 21:52 a couple of workers in white coveralls might be doing just that.

  • @amartart
    @amartart หลายเดือนก่อน

    Nice flying, Joe and particularly the tunnel. Any idea how the finished cars/trucks get to the entrance of the tunnel (all inside, from finish build line, then driven to tunnel (all inside?)! also, any idea when will the Juniper Model Y refresh start being built here? Thanks!!

  • @TashiRogo
    @TashiRogo หลายเดือนก่อน +4

    Why are the concrete forms chopping off over a foot of width at the tunnel exit? Am I not understanding what they are doing there?

    • @grahammonk8013
      @grahammonk8013 หลายเดือนก่อน +1

      @TashiRogo The tunnel is circular, you can't use the total width anyway. The available width should be pretty much the same as the width of the floor inside the tunnel.

    • @DavidJohnson-tv2nn
      @DavidJohnson-tv2nn หลายเดือนก่อน

      12' tunnel, if I remember correctly.... 8.5' road width. Which is why I've been saying that these tunnels aren't much use for anything other than what they have here or perhaps a perdition path. Definitely NOT useful for an actual road anywhere else.

    • @upsill
      @upsill หลายเดือนก่อน

      @@grahammonk8013 but the car is larger at this height with mirrors

    • @DessieDoolan
      @DessieDoolan หลายเดือนก่อน +2

      @@DavidJohnson-tv2nn Road width scales to 10'6" 3.2m based on a tunnel internal diameter of 12' 3.6m. Brad's 9 Nov video at 7.51 is near perfect to measure this.
      Sectional elevation shown in Joe's 27 September video states 9'4" 2.84m. That drawing I think from the river tunnel project.

  • @desmovalveservice5282
    @desmovalveservice5282 หลายเดือนก่อน +2

    "Coffer-dam' is the name of the blue temporary box structure at the alternate exit point next to the tunnel, time stamp, 14:00. It provide protection again cave-ins when working in an excavated trench.

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน +5

      I think the correct term is a trench box.
      Trench Box: Primarily used for safety in construction, especially in trenching operations. It prevents the walls of a trench from collapsing, thus protecting workers from cave-ins.
      Cofferdam: A cofferdam is engineered to create a dry work environment in areas that are normally submerged, like rivers, lakes, or seas. It's used to exclude water from a construction area so that work can proceed in the dry.

  • @DanaOredson
    @DanaOredson หลายเดือนก่อน +1

    Kinda crazy that the boring tunnel, which is supposed to be quick operation, we are sitting around 10 months or so of working on that tunnel.

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน +3

      I’ve discussed this on several videos … this tunnel was a test for a variety of things and the Boring Company told me they were able to do this with a relaxed timetable. The road lanes breaking was a setback that has now been rectified. The lessons they got were important for Prufrock- 3 and Prufrock-4 TBM development.

    • @DanaOredson
      @DanaOredson หลายเดือนก่อน +2

      @@JoeTegtmeyer Thanks for your direct reply. I'm sure I missed the specific mention you called out. Good to know that the claimed timeline is not what they were actually striving for in this instance, but they used it as a learning experience for future tunnels.

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน

      @ you can go to my playlists for the Boring Company and watch Part 1&2 of my Boring Company tour and deep dive videos I put out in April

    • @GntlTch
      @GntlTch หลายเดือนก่อน

      @@JoeTegtmeyer Yes but, unfortunately, that "relaxed timetable" got the head of construction fired because the tunnel was taking too long and holding up the extention.

  • @potencjalnypracownik2966
    @potencjalnypracownik2966 หลายเดือนก่อน +2

    500 not volts, kilowatts and there is no info that Cybertruck can take up to that yet still should be max 350, which still will be better than 250 on older chargers

    • @Gig0Surf
      @Gig0Surf หลายเดือนก่อน

      Tesla's V4 video showed the Cybertruck charging at 500 kW but I wouldn't be surprised if that's only possible if you have the range extender installed. I only remember the Cybertruck hitting 327 kW with 800V charging but perhaps that's improved with more recent updates?

    • @bradcavanagh3092
      @bradcavanagh3092 หลายเดือนก่อน

      I'd expect that it will be able to, since I understand per the Munro Live tear down that the battery pack is split into 400V halves.

  • @davidanalyst671
    @davidanalyst671 หลายเดือนก่อน +4

    Tesla really needs a giant charger lot. Right off the highway. So you can see the factory, the other buildings, and maybe a snack bar with drinks. You really don't want people wandering around the factory, but hes got 3,000 acres, so he might as well put a charger lot there. Everyone knows the tesla supercharger horror stories on thanksgiving and christmas and any big holiday, so he should make a mega charger here. right off the highway.

    • @grahammonk8013
      @grahammonk8013 หลายเดือนก่อน +3

      @davidanalyst671 They probably will do, eventually. Arranging for a big charger install takes time, including the electrical provisions. They have been installing lots of electrical capacity already for the Coretex, and more needs to be done. The Christmas and Thanksgiving is about long distance travel, that is *between* cities.

    • @WarrenLacefield
      @WarrenLacefield หลายเดือนก่อน

      @@grahammonk8013 With Joe's recent video showing great plans for pubic access to river-side parks and facilities south of River Road, I'm pretty sure there are likely to be pubic charging stations in pubic parking lots.

    • @grahammonk8013
      @grahammonk8013 หลายเดือนก่อน +1

      @@WarrenLacefield Oh definitely. Not sure about "giant" charging lots. Depends on how popular it will be as local attraction. Probably mix of level 2 and level 3.

    • @WarrenLacefield
      @WarrenLacefield หลายเดือนก่อน

      @@grahammonk8013 Agree. Good chat. This will be something to watch for next year )or to)!

  • @charliehubbard4073
    @charliehubbard4073 หลายเดือนก่อน

    Hey, what happened to those white rings that covered the cement pilings at the bottom of the flag poles? They had been there previously... hadn't they?

    • @DessieDoolan
      @DessieDoolan หลายเดือนก่อน +1

      The white rings were never installed.

  • @jeffcarlton3590
    @jeffcarlton3590 หลายเดือนก่อน

    Hopefully, and somewhat logically the "dirt square" south of the 'end of line' chargers will be dedicated to Tesla Semi Truck chargers. I do not know how far along the development is on those or whether there still might be a chance these will have dual use as Cyber truck rapid chargers - like Elon at one time thought. Giga Nevada has a few early T. Semi Truck charger prototypes.

    • @Gig0Surf
      @Gig0Surf หลายเดือนก่อน +2

      They just unveiled the V4 cabinets which can back the V4 posts with NACS for passenger vehicles or presumably the existing Semi charging posts which use an older draft MCS connector which were unveiled with the updated cable cooling that V4 NACS posts also got. Less clear is if they'll update the Semi to use or include a NACS style port, which doesn't seem undesirable.
      Still, while perhaps convenient being adjacent to the loading area, I don't see why they'd want to intermix semi traffic with the charging area for newly produced vehicles. It might make more sense to have a much larger Semi charging area down by River Rd for example where all trucks could charger (car carriers, WoW trucks, etc.,)

  • @JoachimFrey-y3i
    @JoachimFrey-y3i หลายเดือนก่อน

    Hi Joe, Thank you for your Video. The tunnel, will this be for one way traffic or both way. In case it is both way a signalling system should be installed.

    • @WarrenLacefield
      @WarrenLacefield หลายเดือนก่อน

      Possibly there will be a signalling system or sensor monitors for sure. But when things get going again full speed, there will be an almost constant steady flow of vehicles (CT, cars, CyberCabs, etc.) during all shifts to the EOL, most likely with no need for human drivers. So mostly a one-way flow. The roadway for this on the West side will likely be fenced.

  • @balaji-kartha
    @balaji-kartha หลายเดือนก่อน

    When you are at Boca Chica, pass on our love to Ellie. Love both of you 👌👏🌹🙏

  • @CO2Whoo
    @CO2Whoo หลายเดือนก่อน

    Hey Joe, I have a question for you in the past. You’ve stated that the model Y will enter that area and then go into the tunnel and across the highway. However, the road marking suggest that’s only an exit. Where would the model wise enter to go through the tunnel or would they never entered the tunnel at all and just go around like they are now?

    • @JoeTegtmeyer
      @JoeTegtmeyer  หลายเดือนก่อน

      Yep that’s a change … as I now understand it, a new tunnel is planned for the Model Ys and this one will be just north of there main entrance.

  • @renekemna5620
    @renekemna5620 หลายเดือนก่อน

    Don´t they use the new 500kW Supercharger?

  • @mjcamp01
    @mjcamp01 หลายเดือนก่อน

    Hey Joe I see you have a new model 3, have you mentioned this in depth in a prior video? Could you link to it for me please?

  • @freddymax5256
    @freddymax5256 หลายเดือนก่อน +1

    How many miles of wire could have been saved if the computer centre been installed on the north end of the factory?

    • @DavidJohnson-tv2nn
      @DavidJohnson-tv2nn หลายเดือนก่อน

      About 48 miles of cable. 48 cables at a distance of about one mile (estimate).

  • @MJ-zo5gb
    @MJ-zo5gb หลายเดือนก่อน

    If they have FSD driving the car through the tunnel, there’s really no reason I have to go fast. 5 to 10 mph would be fine.

  • @lourdessilva6442
    @lourdessilva6442 หลายเดือนก่อน

    Podia fazer um breve resumo de todas as empresas pois a mídia de meu país Brasil diz que só está investindo na China

  • @S1nwar
    @S1nwar 25 วันที่ผ่านมา

    the boring company still exists?

  • @protectanimals9792
    @protectanimals9792 หลายเดือนก่อน +3

    Who installed the roof ?
    Too much water puddling. They didn’t taper the rigid insulation correctly.

    • @ohtoah
      @ohtoah หลายเดือนก่อน +1

      That type of roof is designed to hold some water, it is free cooling, energy saving.