Cost type Resource in MS Project | How to add cost of a cost resource and Fixed cost
ฝัง
- เผยแพร่เมื่อ 22 ธ.ค. 2022
- In this video you will learn:
1. How to create various resources in MS project
2. When to use what type of resource (work, material, cost) in Microsoft Project
3. How to add cost to a cost type resource
4. How to add fixed cost to a task
5. How to get month-wise or week-wise cash outflow from Microsoft Project
Our video tutorials are useful from beginner to advanced levels of Microsoft Project users and very much helpful for Project Managers and Planning Managers to schedule and get reports of various types from Microsoft Project.
#msproject
Nice
Very helpful ❤
Glad it helped. Stay tuned with us for more useful videos on project management.
Very helpful video. Thanks for posting. Please add more videos on similar topics
Thanks for your support. Which vidoe in our channel do you like the most? Please let us know in the comment box.
Hi Your Video was helpful, My doubt was for instance I appoint subcontractor as a resource who chareges per Sqft then how can we Enter the In MS Proj. Manag resoruces ?
Great job ... I am eagerly waiting for your videos ....
Thanks for your compliment
Sir Mane pura msp apki video dekh kar sikha h
Thanks a lot.
Thanks Sir
Good 👍👍👍
Thanks for your compliment
Hi, After long gap. Pls do put more video for Complete Project life cycle. Thank you.
Yes we are planning to post it in January for a G+1 building with as many items as possible. Thanks for your comment.
Also, Excavation 5K/ day. Cost per usage 10k. But, how come we are getting 60K and 50K for 10 days and 8 days duration. Possible, Pls explain...
@@ravindrankrishnan2964 Total cost = (cost per day x no.of days + cost per use)
= 5000 x 10 + 10000 = 60000
@@projectometric Thanks for your reply ...
Excellent
Thanks a lot for your compliment.
Sir m apki sbhi videos dekhta hu
Thanks for your support.
V.nice video. We learn fm this.
Thanks for your compliment. Stay tuned for construction management and technical videos.
very good Job!
Thanks for your compliment. Stay tune for more videos on project planning and management.
Hi I want to know how I increase the resources and duration of the Project minimizes showingin MSP? ❤😮
Good job 👍 thank you ❤️
Thanks for your compliment
Pl.make "S" curve by using MS Project. Thanx
Noted we will post video of S curve
Hello Sir.Please make a tutorial on how to entry materials cost if price is fluctuate.
Thanks
Good question, and this will be our next video topic. Keep watching.
We have uploaded a video on this topic, hope you watched.
Sir how to download 2019 msp. Kindly provide link
Sorry i dont have link for a full version. You can try torrent or other similar sevice.
Where to download excel or project sheet
We will shortly add you in our Whatsapp Group.