PMP® Exam Practice questions with Explanations | Task 1.11 Engage & support virtual team | PMP® Exam

แชร์
ฝัง
  • เผยแพร่เมื่อ 21 พ.ย. 2024

ความคิดเห็น • 13

  • @Nini11849
    @Nini11849 5 หลายเดือนก่อน +2

    Passed my pmp exams today & couldn’t have made it without your revision videos for the 3 domains, the practice questions & exam mindset. It was really helpful, thank you so much!!! 🙏🏼🙏🏼

    • @edzest
      @edzest  5 หลายเดือนก่อน

      You're welcome Nini ... I'm glad the videos could help. Thanks a lot for taking out time to let us know about your success. 😀🙏

    • @christianmusicandlyrics
      @christianmusicandlyrics 5 หลายเดือนก่อน +2

      🎉congratulations 🎉

  • @MasterPro-iq1bu
    @MasterPro-iq1bu 5 หลายเดือนก่อน +1

    Thank you for uploading, most valuable info in TH-cam

    • @edzest
      @edzest  5 หลายเดือนก่อน

      Thanks Qudratullah 😀

  • @bvpcoe2008
    @bvpcoe2008 5 หลายเดือนก่อน +1

    @edzest Thank you for such short and crisp task wise videos, I am following this series and planning to write my PMP after all the tasks are covered.

    • @edzest
      @edzest  5 หลายเดือนก่อน

      That's great to know Alok
      Which means we also need to speed up to help you prepare... Will do that. :)
      All the best.

  • @suhaspai118
    @suhaspai118 4 หลายเดือนก่อน +2

    Question #1 Not sure why answer is A; The concern is lack of collaboration due to work Schedule, so how does remote team's virtual needs address this.

    • @edzest
      @edzest  4 หลายเดือนก่อน

      Hi, it’s the work schedule of the virtual team because of which they are not able to collaborate with other collocated teams. Hence, we need to address the virtual team’s needs (work schedule being a part of it).

    • @VimalKumarVV
      @VimalKumarVV หลายเดือนก่อน +1

      @@edzest Difficult to understand. Remote teams issues is with other collocated team. Answer A is about remote teams virtual need.

    • @edzest
      @edzest  หลายเดือนก่อน

      @@VimalKumarVV hi, because the remote team is not able to find time to meet collocated team, it is important to understand virtual team needs and meet those. Which could be to set up a meeting timing as per their availability

  • @russ4u4love
    @russ4u4love 5 หลายเดือนก่อน

    Question 2 i very much agree to your answer but i have a little doubt with regards to the question stem. The question asked for what will PM do and hence the answer should be an action. So is investigation considered as an action (If going for action i will go with answer B). Also what if after investigation the PM didnt find any alternate software so this question also remains unanswered while answering with option C.

    • @edzest
      @edzest  5 หลายเดือนก่อน

      Hi, what will the project manager do, doesn't necessary look for a decision/action on projects. It could be a meeting, a discussion etc.
      Also, for the second part of the query, we don't have to worry about what happens after. The PM may or may not be able to find an alternative software, but that shouldn't stop the PMP from trying out alternative.
      Hope this clarified your doubt, do let me know. :)