MUST SEE!!! I watched this video just prior to taking my PMP exam. I believe it made all of the difference. .I had many questions on change and this video helped to guide me to answers that I would have not chosen otherwise.
Glad it helped! To know more iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/ It is complete and comes with an end to end support.
Identify Stakeholders( initiation) , Define activities, develop schedule, plan risk response and plan procurement output is the change requests. 1 process in initiating and 4 process in planning output is change requests.
To clarify (And mentioned in the video), the change request outputs for these 5 processes won't come during the initial setup/creation of the process during Initiating & Planning; they will come later when Executing and Monitoring/Controlling processes have determined an adjustment to these 5 processes is necessary.
Thank you! Cheers! To know more about PMP program, please visit - www.izenbridge.com/pmp/online-course/ It is complete and comes with an end to end support.
Any problem I have. If you are not able to help me with your utube videos, then it means I can't get the understanding anywhere. Your explanations are always on point! Thank you so much for your videos. You have helped me a lot in project management. I'm preparing for my pmp.
Hi Venkatesh, thank you for exploring our content. You can explore our complete content of PMP (Project Management Professional) Based on PMBOK6 here: www.izenbridge.com/pmp/online-course/
I have a question, as soon as a stakeholder suggest a change what would you do? My question is: I evaluate the impact? or first I have to documented and then I proceed to make a preliminary impact before sent it to the board? SECOND QUESTION: When do I have to put down in the change log? As soon as the stakeholder asks for the change or at the end when the board approved/rejected?
The change management plan explains what you should first. You need to document the first change request. Else how would it be available to all to analyze its impact? The change log need a continuous update. Whenever you get a request, update it. When you are in review- update it. When you get approval, update it. And if it gets rejected, update it. It tracks the progress of each change.
Thank you!! Sahar for exploring and liking our content. You can also explore our PMP content as per PMBOK guide Sixth edition by enrolling with us. www.izenbridge.com/pmp/online-course/
Glad it helped!! To know more about PMP program please visit - www.izenbridge.com/pmp/online-course/ It is complete and comes with an end to end support.
I am still confused by some of the questions that the answer is "Submit a change request first" instead of evaluate the impact. I assume if you do not see the question stated a change request has been submitted, then your next step is to submit one first?
@@shasankv85 do let us know if you wish to share your exam journey by doing conversation with Saket. You just need to drop email to Saket.bansal@izenbridge.com, rest we will schedule
WHO in case of PMP depends on your project management plan, usually as part of it you have RACI where you identify it. PM is expected to get it done, in many case PM may do it.
During execution in a Hybrid project, one key stakeholder requests the Project Manager for a change in a work package for which work has not started yet. What should the Project Manager do NEXT? a) Ask the stakeholder to raise a formal change request b) Document the change request in the change log
Do we have more options? if these are the only options B is definitely not relevant since you need to have change request first before you log it in change log. But i feel we can have better options, if one has to select from this, i advice go for A.
thank so much for video :)!! in case we realize during execution there might be a new risk not mentioned in the risk register do we need to send a CR ? and if we want to use the risk and management reserves do we also need to send a CR for that?
It is is a good question. If we identify a new risk and if we need to implement a risk response - In this case, you have not mentioned anything in the baselined plan you have to raise a change request. Other case is you have a consolidated contingency reserve you may plan to use this reserve instead of raising a change request. If you have a risk reserve, then there is no need to raise a change request because there is already a provision in the baselined plans. For more details, please watch the following video: th-cam.com/video/q1SByzT0gTI/w-d-xo.html
Thank you Rakesh, for exploring our video. Many PMP aspirants face challenges while answering questions related to change management due to the gap in the change request flow. This video fills the gap and clears the concept. You can explore our content for more such videos here: www.izenbridge.com/pmp/online-course/
This is just superb, I've been looking for "what is the purpose of a management team plan?" for a while now, and I think this has helped. Have you ever come across - Tannilara Stupendous Transcendence - (Have a quick look on google cant remember the place now ) ? It is an awesome one off product for discovering how to getting 7000 plus project management and business templates without the hard work. Ive heard some pretty good things about it and my cousin got excellent results with it.
Sometimes an input to the control processes in each knowledge area is "an approved change request" what is the purpose of that? I dont see CRs flowing into your knowledge area control processes in your flow chart, only out.
I figure it out, sometimes "approved" change requests (CRs) flow into the Direct and manage work, control quality, and control procurement because the approved CRs themselves effect the control process. makes sense.
True!! Also approved change requests need to be completed and Direct and Manage Project Work is the process which implements approved changes to achieve the project's objectives. To know more, please watch - th-cam.com/video/LraSNL-SaRY/w-d-xo.html
As usual, it's great to watch Saket's video!! He is an awesome instructor. One observation though, whosoever is uploading these videos from Saket's team needs to focus on youtube thumbnails, the thumbnail gives an impression that Saket is about to collapse on the floor lol
What change can be done when someone is not approved from day one. From who is the misunderstanding? From the one who refuse or for the one who does not understood a refuze? Is in India clear the language waste of time?
Thank you for asking. Once we have approved change request, the project manager needs to ensure that the project management plan (schedule, resource, work package, scope etc) gets updated based on the approved change. The execution happens based on the plan. Some changes need an act in this week, some may need to act after month.
Well explained Sir. Many questions from this topic have appeared in the real exam which was really confusing to choose the best answer. I have some doubts, how can I contact you?
MUST SEE!!! I watched this video just prior to taking my PMP exam. I believe it made all of the difference. .I had many questions on change and this video helped to guide me to answers that I would have not chosen otherwise.
Glad you liked it!! keep exploring iZenBridge TH-cam Channel.
I am very impressed with your teaching quality. awesome.... this is a real teacher....namste
So nice of you
Very simple and interesting way of teaching 👏
Thanks for liking our teaching
Beautifully and clearly explained! Thank you for this lesson.
Thank you.
Wow! I've struggled to understand this over the past 2 weeks.. this video really breaks the process down in a simplistic way...I FINALLY understand!!
Glad it helped! To know more iZenBridge PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Dear Sir
I passed pmp recently in my first attempt.
Thanks for your valuable guidance through youtube. I used to see you videos.
Thanks once again!
Congratulations!! Glad videos supported you in your success.
well explained sir, thank you it clears so many doubts
Identify Stakeholders( initiation) , Define activities, develop schedule, plan risk response and plan procurement output is the change requests. 1 process in initiating and 4 process in planning output is change requests.
To clarify (And mentioned in the video), the change request outputs for these 5 processes won't come during the initial setup/creation of the process during Initiating & Planning; they will come later when Executing and Monitoring/Controlling processes have determined an adjustment to these 5 processes is necessary.
You are amazing. Your videos helped me make so many breakthroughs. I passed this morning and you helped me made that a possibility. Thank you!
Congratulations!! Good to know that iZenBridge videos were part in your success. Keep exploring iZenBridge TH-cam Channel.
Thank you for the clear and easy to understand process of change control. Much appreciated!
Thank you! Cheers! To know more about PMP program, please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
Excellent explanation
Glad it was helpful!
Any problem I have. If you are not able to help me with your utube videos, then it means I can't get the understanding anywhere.
Your explanations are always on point!
Thank you so much for your videos. You have helped me a lot in project management. I'm preparing for my pmp.
All the best!! Keep exploring
awesome video Saket ! Very confusing topic for most of pmp aspirants :)
Hi Venkatesh, thank you for exploring our content. You can explore our complete content of PMP (Project Management Professional) Based on PMBOK6 here: www.izenbridge.com/pmp/online-course/
I have a question, as soon as a stakeholder suggest a change what would you do? My question is: I evaluate the impact? or first I have to documented and then I proceed to make a preliminary impact before sent it to the board? SECOND QUESTION: When do I have to put down in the change log? As soon as the stakeholder asks for the change or at the end when the board approved/rejected?
The change management plan explains what you should first. You need to document the first change request. Else how would it be available to all to analyze its impact? The change log need a continuous update. Whenever you get a request, update it. When you are in review- update it. When you get approval, update it. And if it gets rejected, update it. It tracks the progress of each change.
Amazing explanation and thanks for effort making this video
Thank you!! Sahar for exploring and liking our content.
You can also explore our PMP content as per PMBOK guide Sixth edition by enrolling with us.
www.izenbridge.com/pmp/online-course/
Sir, awesome explanation
Glad it helped!! To know more about PMP program please visit - www.izenbridge.com/pmp/online-course/
It is complete and comes with an end to end support.
I am still confused by some of the questions that the answer is "Submit a change request first" instead of evaluate the impact. I assume if you do not see the question stated a change request has been submitted, then your next step is to submit one first?
I agree with you your comment brother. I am also having same issue with the
mocks.
Can you paste one similar question here? Just to understand if any keyword was missed.
Excellent explanation, thank u
Glad you liked it, we do have complete PMP program in case you are exploring :
www.izenbridge.com/pmp/online-course/
@@izenbridge , Passed PMP Exam today with above the target.
@@izenbridge , Thank you once again.
@@shasankv85 do let us know if you wish to share your exam journey by doing conversation with Saket. You just need to drop email to Saket.bansal@izenbridge.com, rest we will schedule
@@izenbridge No problem ,will do it.
Nice video , who will do impact analysis?
WHO in case of PMP depends on your project management plan, usually as part of it you have RACI where you identify it. PM is expected to get it done, in many case PM may do it.
During execution in a Hybrid project, one key stakeholder requests the Project Manager for a change in a work package for which work has not started yet.
What should the Project Manager do NEXT?
a) Ask the stakeholder to raise a formal change request
b) Document the change request in the change log
Do we have more options? if these are the only options B is definitely not relevant since you need to have change request first before you log it in change log. But i feel we can have better options, if one has to select from this, i advice go for A.
thank so much for video :)!! in case we realize during execution there might be a new risk not mentioned in the risk register do we need to send a CR ? and if we want to use the risk and management reserves do we also need to send a CR for that?
It is is a good question. If we identify a new risk and if we need to implement a risk response -
In this case, you have not mentioned anything in the baselined plan you have to raise a change request.
Other case is you have a consolidated contingency reserve you may plan to use this reserve instead of raising a change request.
If you have a risk reserve, then there is no need to raise a change request because there is already a provision in the baselined plans.
For more details, please watch the following video: th-cam.com/video/q1SByzT0gTI/w-d-xo.html
@@izenbridge thank you so much for the support you are the best :)
Excellent sir
Thank you Rakesh, for exploring our video. Many PMP aspirants face challenges while answering questions related to change management due to the gap in the change request flow. This video fills the gap and clears the concept.
You can explore our content for more such videos here: www.izenbridge.com/pmp/online-course/
very well explained the steps to follow, Thanks
Thanks Toni for your kind words!! Keep watching videos.
This is just superb, I've been looking for "what is the purpose of a management team plan?" for a while now, and I think this has helped. Have you ever come across - Tannilara Stupendous Transcendence - (Have a quick look on google cant remember the place now ) ? It is an awesome one off product for discovering how to getting 7000 plus project management and business templates without the hard work. Ive heard some pretty good things about it and my cousin got excellent results with it.
Thank you
Thank you
Sometimes an input to the control processes in each knowledge area is "an approved change request" what is the purpose of that? I dont see CRs flowing into your knowledge area control processes in your flow chart, only out.
I figure it out, sometimes "approved" change requests (CRs) flow into the Direct and manage work, control quality, and control procurement because the approved CRs themselves effect the control process. makes sense.
True!! Also approved change requests need to be completed and Direct and Manage Project Work is the process which implements approved changes to achieve the project's objectives. To know more, please watch - th-cam.com/video/LraSNL-SaRY/w-d-xo.html
As usual, it's great to watch Saket's video!! He is an awesome instructor.
One observation though, whosoever is uploading these videos from Saket's team needs to focus on youtube thumbnails, the thumbnail gives an impression that Saket is about to collapse on the floor lol
What change can be done when someone is not approved from day one. From who is the misunderstanding? From the one who refuse or for the one who does not understood a refuze? Is in India clear the language waste of time?
When will the change be executed..after approval or after communication to stakeholders?
Thank you for asking.
Once we have approved change request, the project manager needs to ensure that the project management plan (schedule, resource, work package, scope etc) gets updated based on the approved change. The execution happens based on the plan. Some changes need an act in this week, some may need to act after month.
Well explained Sir. Many questions from this topic have appeared in the real exam which was really confusing to choose the best answer. I have some doubts, how can I contact you?
Happy to know that you found value in the course. Keep exploring.
a PM communicates with stakeholders rather than communicate to stakeholders. I guess