  • @shommytv
    @shommytv 4 ปีที่แล้ว +6

    I studies for 4 months and didn’t focus on the issue log. If it wasn’t for this video that I discovered in the last week, I would have missed these questions on the exam. I passed this morning and all your videos were the perfect length to revIew and fill in gaps. Love the visuals and your presentation style is great, thank you so much!

  • @normaleestudio8444
    @normaleestudio8444 2 ปีที่แล้ว +1

    Thank you for this video! Love your teaching style... very easy to follow. I am taking my PMP exam soon and found this helpful ~

  • @boristim9707
    @boristim9707 4 หลายเดือนก่อน

    Contrary to the info in the video the issue log should be an output of the process 4.3 "Direct and Manage Project Work", therefore part of the Execution of a project according to Ricardo Vargas Process Flow. In the video it is stated that the issue log is part of 4.5 "Monitor and Control Project Work", therefore part of Monitoring & Controlling the project - could you expand on where it is located and what is (more?) correct? Thank you 🙂

  • @--SubZer0--
    @--SubZer0-- ปีที่แล้ว

    Hi.
    If a change request is being initiated because either a defect was found during testing or if a requirement was missed in the scope, at what point does the issue log get updated? Does it get updated "after" the change request is created? Or is the issue log updated first and then the change request is created? Thanks