Scenery: Imagine that we are planning activities that must be finished on a specific date and to do it you must work two shift of 12 hours to work the 24 hours of the day. Question: What would be the set up to apply in the calendar? Should I set up only the time period of 24 hour per day to all the working days or should I do it with the detailed work hour per/day in order to specify the hours of this two shifts to manage better the resources need it?
Your lectures are amazing! Appreciate your efforts. Thank you so much for your valuable time and work!
You're welcome. Glad you found it helpful!
Not 10 days... It's 10 hrs... Brother... Your primavera p6 tutorial is amazing 👌👍
thats wot!! ... confused me there ... ...
Detailed work hours, Is there a way to make it for one day and apply for all working days. Because I have to change for everday manually.
You have to do it manually and it is not a lot of work though. You will also do it once only.
Scenery:
Imagine that we are planning activities that must be finished on a specific date and to do it you must work two shift of 12 hours to work the 24 hours of the day.
Question:
What would be the set up to apply in the calendar? Should I set up only the time period of 24 hour per day to all the working days or should I do it with the detailed work hour per/day in order to specify the hours of this two shifts to manage better the resources need it?
Dear Osama, are these videos is a full course?
Thanks in advance
Yes, please check the full course here smartpmtraining.com/courses/p6-basic/
I do not have Contractors calendar. where can İ find it ?
same issue