2.8 : Primavera Learning - Calendars In Primavera P6 || Primavera tutorials

แชร์
ฝัง
  • เผยแพร่เมื่อ 6 ก.พ. 2025

ความคิดเห็น • 5

  • @vaithiyanathanarunasalam2964
    @vaithiyanathanarunasalam2964 ปีที่แล้ว +1

    Super🎉😊

  • @antonynixson4515
    @antonynixson4515 4 หลายเดือนก่อน

    After adding a new standard time in Primavera P6, i noticed that the "time period" button, which is located below the "work week" section, disappears or becomes hidden .Plz explain it

  • @prasantadey4257
    @prasantadey4257 3 ปีที่แล้ว +1

    I am trying to add national holidays like 15th aug & 26th jan and if my project duration is for 02 yrs then do i have to mark these dates non - working for each other or it may be done at a time?

    • @dptutorials
      @dptutorials  3 ปีที่แล้ว

      You can simply mention as non-working days in calendar