Estimation by Long Wall Short Wall method (Part-2)

แชร์
ฝัง
  • เผยแพร่เมื่อ 10 ก.ย. 2024
  • Learn hoe to estimate quantities and costs of a residential by Long wall Short wall method with simple method of explanation.
    Watch Part-1 : • Estimation by Long wal...
    Video series of Estimation & Costing :
    Estimation, Costing & Valuation: • Estimation, Costing & ...
    Website link- technicalcivil...
    Channel link - / technicalcivil
    #EstimationAndCosting #LongwallShortwallMethod #Technicalcivil
    Don't forget to SUBSCRIBE....🙂
    Music: Blue Skies - Silent Partner • Blue Skies - Silent Pa...

ความคิดเห็น • 37

  • @yogeshkumar-em3ok
    @yogeshkumar-em3ok 5 ปีที่แล้ว +1

    Bahut ache se samjhaya aapne. Aap aise hi or topic par video bnate rahe...

  • @CIVILblaster
    @CIVILblaster 5 ปีที่แล้ว +1

    Plz pls sir ....E sub video mene puri college me baat diye ...bahut use full hey ....7th sem ke liye .....Lecture jane ki bhi jarurat nahi rehti .....sub hamari book ke hi sum aap solve karate ho aap ....E baat bahut achi lagi muje

  • @chiragkava6962
    @chiragkava6962 5 ปีที่แล้ว +1

    A very good work sir...tysm..😎👏🏻👏🏻✌🏻✌🏻

  • @CIVILblaster
    @CIVILblaster 5 ปีที่แล้ว +1

    Thank u very much ....Sir .....Jaldi se ek video center line method ka

  • @divyanagvadiya6438
    @divyanagvadiya6438 5 ปีที่แล้ว +1

    Sir, 2 CM thick marble flooring k andar toilet and toilet k pass wale area ka calculation kyun nahi kiya hai.....???

  • @_SH0OTER
    @_SH0OTER 5 ปีที่แล้ว +1

    good work 👍👍

  • @manohar181
    @manohar181 5 ปีที่แล้ว +3

    Arey bhai varhnda foundtion ka plan alag huva to kya krna pdega

    • @Technicalcivil
      @Technicalcivil  5 ปีที่แล้ว

      Agar plan ya section alag dimensions ke hai to apko uske liye separately calculations krne padenge.

    • @manohar181
      @manohar181 5 ปีที่แล้ว

      @@Technicalcivil apke pass use ke notes hoge to de doo na

  • @DeadPool-mw6ug
    @DeadPool-mw6ug 5 ปีที่แล้ว +3

    Bhai hydroloy aur water resource engineering ke vdo bando... exm hai.🙏🙏

  • @selfenquiry456
    @selfenquiry456 5 ปีที่แล้ว +1

    Sir ab to sub structure mein isolated footings provide Kar Raha hain bt syllabus mein wohi old stuff hain,Mene bhi iss Jo sikhi thi semester ke samay bt Jo jo changes hai usko nehi Jan pa Raha hu,so isolated foundation wala buildings that means frame structure ke upor detail mein estimate kare,sab types ke foundations Ka estimate Kare..toh iss channel Ka biggest point Hoga...kya kya changes ho Raha hai Woh bhi bataiye practically

  • @hemitaahir6783
    @hemitaahir6783 5 ปีที่แล้ว +2

    Sir pls made vedio on estimation of sepetic tank & soak pit , culvert, steel roof truss, road ,dam ,canals

    • @Technicalcivil
      @Technicalcivil  5 ปีที่แล้ว

      Ya sure, don't worry, we will discuss these all in this series. So be tuned with technical civil

  • @owaishaqqani6473
    @owaishaqqani6473 5 ปีที่แล้ว

    What about flooring in the area outside of attached toilet? Why are we not considering that area for flooring?

  • @darshanbaria5554
    @darshanbaria5554 3 ปีที่แล้ว

    Sir not clearly mentioned about Earth filling in plinth in Verandah , can you explain it ? Unable to understood that one .
    21:43

  • @Er.C.kartikey
    @Er.C.kartikey 4 ปีที่แล้ว

    bhai thoda sa government Tender kaise hota hai uspe detail btaye thanks u

  • @zimi7616
    @zimi7616 3 ปีที่แล้ว

    deduction mein ventilation ki area toh 0.5 m3 se less hai toh yeah include kyu huaa??. last qsn mei toh 0.5 se less tha isiliye include nai huaa thaa. pls specify.

  • @danishkumar6219
    @danishkumar6219 5 ปีที่แล้ว

    bhai Verandah ...ki foundation ki height ...kaam pa bi ..ek video banao

  • @ringus_wale_khatu_shyam_ji
    @ringus_wale_khatu_shyam_ji 4 ปีที่แล้ว

    Aapne earth filling mai verandah ki length 3.5 kyu liya hai 3.8 honi chaiye na

  • @IrshadAli-cy5tj
    @IrshadAli-cy5tj 5 ปีที่แล้ว

    Sir earth filling me hamne inner dimensions liye. Lekin door waali jageh me bhi filling karni padegi na to wo quantity add nahi karna hoga kya?

  • @shudhanshushekhar2322
    @shudhanshushekhar2322 4 ปีที่แล้ว +1

    Sir Rcc column 0.3*0.3 ko v include karna hoga na ?

  • @rohanshinde4327
    @rohanshinde4327 5 ปีที่แล้ว

    Sir there's another example of semi-circular short wall in our book. In that example they have subtracted less excavated area from it. Can you explain what is it?

  • @lsoni1208
    @lsoni1208 5 ปีที่แล้ว

    Pls sir make a lecture on "ANALISIS AND DESIGN OF BEAMS FOR TORSION AS PER CODAL METHOD" in D.C.S. in this weak.

  • @allforyou5390
    @allforyou5390 5 ปีที่แล้ว +1

    Is videos ka saath SA-2 ke bhi upload kardo before 17 નવેમ્બર

  • @CIVILblaster
    @CIVILblaster 5 ปีที่แล้ว +1

    Sir centre line method ka video jaldi bana do plz ......Thursday exam hey ....aati hey lekin thode bahut doubt hey ...so

    • @asikahamed4947
      @asikahamed4947 5 ปีที่แล้ว

      CIVIL blaster jjnnenemnnnn?nnjgvhkk

  • @yogeshbhardwaj6364
    @yogeshbhardwaj6364 5 ปีที่แล้ว

    Hello sir... Sir ap ek Video Yield Lines Theory pe bano ya phir silos and bunker pe bano jaldi se

  • @akhan4214
    @akhan4214 5 ปีที่แล้ว

    Plz make video on center line method

  • @mayur_ingle
    @mayur_ingle 4 ปีที่แล้ว

    Sir no of W2 = 2 lekin apne RCC weather shed me no of W2 = 1 liya hai...kyun?

  • @allforyou5390
    @allforyou5390 5 ปีที่แล้ว

    Today is 17 November... Will you upload SA-2 videos today?

  • @chintanpatel2266
    @chintanpatel2266 5 ปีที่แล้ว +1

    sir can you explain same example by center line method
    #TECHNICALCIVIL

  • @Ravihbk
    @Ravihbk 4 ปีที่แล้ว

    Do i have these excel sheets

  • @IrshadAli-cy5tj
    @IrshadAli-cy5tj 5 ปีที่แล้ว

    2 cm thick marble flooring ka calculation Toilet me kyu nhi kiya sir?

  • @anilabpv2049
    @anilabpv2049 5 ปีที่แล้ว

    sir please explain this method in English

  • @ayushbanchhor1537
    @ayushbanchhor1537 2 ปีที่แล้ว

    Lots of error in calculation