All bus bar schemes in substation|Busbar system in substation|Power system|Typical bus configuration

แชร์
ฝัง
  • เผยแพร่เมื่อ 10 ก.ค. 2019
  • Bus bar arrangements or bus bar scheme is a very important aspect of power system or Electrical substation. There are various types of bus bar arrangements. The bus bar arrangements are generally known as bus bar scheme.
    #AllBusBarScheme, #ElectricalTechnologyAndIndustrialPractice, #TypicalBusBarArrangement
    In this video all bus bar arrangements or all bus bar schemes used in Electrical substation or power system are described.
    This video is also applicable for the following topics.
    Bus bar schemes in power systems
    Electrical bus bar system
    Electrical substation Busbar scheme
    busbar system in Electrical substation
    Typical bus bar configuration
    Typical bus bar arrangements
    bus bar schemes
    bus bar arrangements
    single bus bar scheme
    double bus bar scheme
    single bus with sectionalizer
    one main one transfer bus scheme
    one main one reserve cum transfer bus scheme
    two main one transfer bus scheme
    double bus double breaker scheme
    one and a half breaker scheme
    all bus bar arrangements
    different bus bar schemes
  • วิทยาศาสตร์และเทคโนโลยี

ความคิดเห็น • 56

  • @krnair2255
    @krnair2255 หลายเดือนก่อน +1

    Aptly explained. Hope this the tutorial will aid students as well as beginners of profession a handy presentation. Thanks a lot.

  • @Cromanea
    @Cromanea 3 ปีที่แล้ว +2

    Best tutorial on protection. Thanks for sharing your valuable knowledge for free and for people like us who cannot afford premium subscription to some online educators. You are one of the best teachers I have learnt from as far as Electrical Engg. is concerned. 👍🙏

  • @shady4071
    @shady4071 4 ปีที่แล้ว +5

    This video is an underrated masterpiece.

  • @DryPepperEntertainment
    @DryPepperEntertainment 7 หลายเดือนก่อน

    Superb explanation thank you soo much

  • @awadmohamedahmed4839
    @awadmohamedahmed4839 2 ปีที่แล้ว

    Nice Explanation, thank you so much

  • @zoro4zena
    @zoro4zena 3 ปีที่แล้ว

    Best content utube ❤️

  • @rameshnabde1582
    @rameshnabde1582 3 ปีที่แล้ว

    Very good & informative video

  • @prabhakarangovindaraj9238
    @prabhakarangovindaraj9238 4 ปีที่แล้ว +2

    Hatts off sir,👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍👍

  • @surendrakverma555
    @surendrakverma555 ปีที่แล้ว

    Very good. Thanks 🙏🙏🙏🙏🙏🙏🙏

  • @Durga189
    @Durga189 4 ปีที่แล้ว

    Nice explanation. Please do a video on breaker rating calculation

  • @abhisheksingh-cv7iq
    @abhisheksingh-cv7iq 3 ปีที่แล้ว

    Very nice explanation 👌

  • @xnasna6151
    @xnasna6151 2 ปีที่แล้ว

    អគុណបង😍

  • @kiransaikia1252
    @kiransaikia1252 2 ปีที่แล้ว

    Necely described tutorial. Please add voltage levels for eachv scheme.

  • @PramodKumar-zl4gq
    @PramodKumar-zl4gq 2 ปีที่แล้ว

    Excellent explanation sir

  • @sanjaykumarsharma3452
    @sanjaykumarsharma3452 3 ปีที่แล้ว

    Great!

  • @safnaskariapper7505
    @safnaskariapper7505 3 ปีที่แล้ว

    superb!

  • @prafulhalmare
    @prafulhalmare 4 ปีที่แล้ว

    Great video
    Ring mail system is awaited

  • @sohambhattacharyya1126
    @sohambhattacharyya1126 4 ปีที่แล้ว

    Very good sir,
    Sir just define me and provide me the purpose of bus bar, main bus transfer bus etc

  • @thinkseeeatthroughvickus4555
    @thinkseeeatthroughvickus4555 3 ปีที่แล้ว

    Sir, can you do a video on equipment voltage selection. ie, at what power rating equipment like motor should be LV, MV,HV...
    when we should go for LV, MV , HV substations... what is max available transformers, its KA ratings.

  • @anwarullakhayoom7863
    @anwarullakhayoom7863 ปีที่แล้ว

    Need more clarification on Earth switches used for isolators.

  • @madhukarshukla2564
    @madhukarshukla2564 4 ปีที่แล้ว

    I think protection will be shifted before charging the bus coupler breaker.... Also a scheme come in which when u close last isolator... It will not possible before transfer tht protection

  • @debarpanchanda9038
    @debarpanchanda9038 2 ปีที่แล้ว

    First of thanks a lot for the video sir.. 🙏🙏
    I just wanted to know that, in one n half breaker i-type scheme for every feeder there is one dedicated isolator is mentioned, but in case of feeder fault or maintenance both the Circuit Breaker as well as the isolator will open, which is placed either side of the feeder, then why there is one extra dedicated isolator for the feeder...?
    Expecting a reply from your side. Thanks in advance sir. 🙏🙏🙏🙏

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  2 ปีที่แล้ว

      So that the feeder can be connected in either bus. It can not be explained over comment. Iwill make vdo

    • @debarpanchanda9038
      @debarpanchanda9038 2 ปีที่แล้ว

      @@electricaltechnologyandind5335 plz sir make one video on it..🙏🙏

  • @Rajram810
    @Rajram810 2 ปีที่แล้ว

    Nice

  • @thinkseeeatthroughvickus4555
    @thinkseeeatthroughvickus4555 3 ปีที่แล้ว

    the switch gears with its cubicle consist of its portion of Bus bars. So except for single bus bar scheme & single bus bar scheme with sectionalyzer how do we employ other bus bar schemes, as we need to connect one breakers to more than one bus?

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  3 ปีที่แล้ว +1

      No other bus bar schemes are available either at outdoor i.e. switchyard or in gis(gas insulated switchgear). Normal pcc panel or switchboard has one bus with bus sectionaliser known as bus coupler

  • @satyarout9377
    @satyarout9377 4 ปีที่แล้ว +2

    Sir can u make a video in switchyard protection scheme

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  4 ปีที่แล้ว +1

      there is nothing as such switchyard Protection. switchyard is basically high voltage feeder and bus bar system. so there Protections shall be just like the feeders like transformer feeder, incomer feeder , line feeder etc. only thing you have to remember if the switchyard voltage is 220kv or higher then bus bar differential protection is must.
      and for switchyard having more than one bus, there shall be Protection switching scheme. suppose you are transferring an incomer to transfer bus for the incomer breaker maintenance, then all the incomer Protection shall be switched to bus coupler.

  • @shashankkumar7770
    @shashankkumar7770 3 ปีที่แล้ว

    We have single busbbar scheme at switchyard,single busbar with sectionaliser in indoor switchyard,double busbar scheme at alternator site..

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  3 ปีที่แล้ว +1

      Indoor switchyard!!!!!!! Is it GIS or the PASS which is also called hybrid substation.

    • @shashankkumar7770
      @shashankkumar7770 3 ปีที่แล้ว

      @@electricaltechnologyandind5335 yes sir gis

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  3 ปีที่แล้ว +1

      Yard is refer to outdoor system. Switchyard will refer outdoor assembly and interconnection of switching equipments. GIS is a very reliable system. But expensive. Which plant you are referring??

    • @shashankkumar7770
      @shashankkumar7770 3 ปีที่แล้ว

      @@electricaltechnologyandind5335 sorry sir instead of swithgear I wrote switchyard mistaken

  • @delosmark18
    @delosmark18 4 ปีที่แล้ว

    Hi sir, can u please discuss sizing of equipment/element in the substation?

  • @varimas
    @varimas 4 ปีที่แล้ว

    11:00 Sir, is it allowed for a double bus scheme system to skip the bus coupler
    Theoritically, i want to isolate bus 1 for maintenance.
    Convention is:
    1. Close bus coupler
    2. close both bypass isolator
    3. Open bus 1 isolators bus side
    4. Open bus coupler
    Can i do it like this?
    1. Close incomer bypass isolator
    (Negligible current, bus 2 energize, same potential as bus 1)
    2. Close outgoing bypass isolator (Same potential as bus 1)
    3. Open bus 1 isolators bus side
    If i skip the bus coupler using these step what are the consequence?

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  4 ปีที่แล้ว

      No, then all the incoming and outgoing feeders breaker will be bypassed. You need to close the bus coupler first to bring both the buses at same potential. Follow convention an standard operating procedures. Do not improvise in ehv system, that can be fatal. Think multiple time properly.

    • @varimas
      @varimas 4 ปีที่แล้ว

      @@electricaltechnologyandind5335
      Sir, Thank you for the safety concern/instruction and speedy reply
      I am nowhere near any ehv. I am working on a school project computer program on bus operations. All theoretical. I have allowed isolator to operate on no load condition except if there exist a parallel path of equal potential or negligible current. So far my incorrect steps allowed the bus to operate without consequences and the incoming and outgoing feeders where not bypassed.
      I have to find a way to include these restriction.
      Sir what program did you use to show us the operation of isolators and breakers in another video?
      Again thank you, this video gave me an understanding on how bus scheme operation works.

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  4 ปีที่แล้ว

      Remember two thing regarding isolator operation. 1 no current change 2. No voltage change.
      Now what you said earlier will let you operate the isolators but that will eleminate all circuit breakers of the feeders. And also the by pass isolators are interlocked with other bypass isolator. So you can close only one by pass isolator at a time.

    • @varimas
      @varimas 4 ปีที่แล้ว

      @@electricaltechnologyandind5335
      Sir, Thank you for your insights and suggestions.
      What you mean by eliminate all feeder circuit breakers is that the circuit breakers will automatically open?
      I realized I was missing the interlock restriction.
      By putting an interlocking condition such as if a bus isolator is closed, the other bus isolator can only be operated when the busbar coupler is closed, i avoided comitting my hazardous incorrect steps.

  • @varadharajanelectricalengi5954
    @varadharajanelectricalengi5954 2 ปีที่แล้ว

    🐸🌎🌏🙄

  • @sandyroyalsandeep6137
    @sandyroyalsandeep6137 4 ปีที่แล้ว

    In double bus scheme your closing the buscoupler that time both bus are charged how your going to take maintenance for bus section 1..?is it compulsory to close the bus coupler..?No

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  4 ปีที่แล้ว

      After closing of bus coupler both the buses are charged.. now you switch over each feeder from say bus 2 to bus 2. Now your bus 2 is free. Open the bus coupler. Your bus 1 is de energized

    • @sandyroyalsandeep6137
      @sandyroyalsandeep6137 4 ปีที่แล้ว

      @@electricaltechnologyandind5335 atlast we should open the buscoupler then only bus 1 is de energised thnk for your valuable information,kindly do a vedio on CT switching relay how it will work ..?

  • @godforbidden6206
    @godforbidden6206 4 ปีที่แล้ว

    in your opinion which scheme is the most optimized one??

  • @EberFarmo
    @EberFarmo 2 หลายเดือนก่อน

    Hi. Are you sure about your explanation for close the disconnector???? 9:00 to 10:00 You can not close the disconnector just because the voltage of both side is equal.

    • @electricaltechnologyandind5335
      @electricaltechnologyandind5335  2 หลายเดือนก่อน

      Possible. Isolator can be closed if there is no change in current or voltage.

    • @EberFarmo
      @EberFarmo 2 หลายเดือนก่อน

      ⁠but you did not say that in video.
      Please check again your description about the priority of disconnector and circuit breaker.
      You said before opening the outgoing CB , you could close the disconnectir.
      Even you said , first close the coupler CB and after that close the bypass disconnector . It is completely wrong and impossible

  • @Devendrakumarpankaj
    @Devendrakumarpankaj 2 ปีที่แล้ว

    😊 🫂 🙏