So this is all about manpower calculation for Manufacturing department. What about other department, let us say quality department? We consider output as no. of parts inspected?
Sir I just want to asko who is the philosopher behind the formula of Manpower requirement? Thanks. Just need for our research.. We put Total Standard Time/ Tak time Instead of the walking time+ manual time. Thanks
Hi. If is still relevant. Week off, or sickness leave are usually incorporated in effeciency decreasing availability time. It is important to plan vacations, to not have majority people gone. Does this helped?
purushoth karunanithi we will do time study of the process, either with current allocated manpower or we can use 1 manpower for all processes. And calculate walking time & manual time of that operator for every process
Offcourse, It required 3 Manpower in order to meet customer demand, But it is biggest waste to company. So as an engineer need to KAIZEN to reduce 0.1 manpower.
@@RamanPahujaIndustrialEngineer how about the main process + additional steps like putting the products in the bin and getting it from the bin. Is it included as the walking time, since there is no walking included in our process. Thanks
@@RamanPahujaIndustrialEngineer ok sir, so if there is no walking or transportation included in the process the formula will be Manual time over Takt Time only? Am I right? Thankd
Total cycle time / tact time = Manpower
If my load pattern is not constant in a single day, in that case how I will plan my manpower?
Great sir aise hi video bna k sikhaate raho
Very good job doing Raman san....👍
Thanks for taking the time to explain.👍
How to take cycle time using stopwatch for parallel process
Hi, is there any specific name for the manpower formula? Couldn't find it online...
So this is all about manpower calculation for Manufacturing department. What about other department, let us say quality department? We consider output as no. of parts inspected?
sorry why are you not accounting the O.E.E in this calculation?
GRACIAS
what is manual time???working time i understand,
Sir I just want to asko who is the philosopher behind the formula of Manpower requirement? Thanks. Just need for our research..
We put Total Standard Time/ Tak time
Instead of the walking time+ manual time. Thanks
Video kam ka he but English me he
What is walking time ??
What is meaning of walking time ...???
Plz explain
That is operator's movement time.
Non value added activaty
On takt time you are wrong.
Nice calculation
I like it.
But one thing I didn't got
Total working time = 14+12 how come here ??
Plz explain
lucky Indian that is walking time, not working time... Still you have query than contact me on my no. 9466549142
Bhai hindi language use karo
SIR CAN YOU HELP ME IN ASSINGNMENT
01. HIGH OPERATONAL COST DUE HUGE MANPOWER
sure..you can text me on whatsapp
@@RamanPahujaIndustrialEngineer UR NUMBER SIR
@@centraljail2923 already given in video...anyways it's 9466549142
Have you included week off ? If no what will be the factor included ?
Hi. If is still relevant. Week off, or sickness leave are usually incorporated in effeciency decreasing availability time. It is important to plan vacations, to not have majority people gone. Does this helped?
Practically not correct.
first i would thank you sir.......then i have one doubt
* how to know about walking time and we want to know to calculate manpower is must na
purushoth karunanithi we will do time study of the process, either with current allocated manpower or we can use 1 manpower for all processes. And calculate walking time & manual time of that operator for every process
Good information.
Bhai Hindi me video uploaded kro, I am an indian
Hahahaha
Sir can u pls told some answers sir.. 1.leadtime, productivity Vs production, throughput time
Surely i will explain.... You can contact me via whatsapp on my no. 9466549142
Sir 2,073,600 sec. Kaise aaya h.
Bro
24 days
1 day = 24 hours
1 hour = 60 minutes
1minute = 60 seconds
Total= 24×24×60×60
=2073600
Very nice 👍
How to calculate requirement if i have cycle time?
If you know CT of each process CT, You can calculate Crew size= ( Sum of all process CT/Takt time)
Hi. If is still relevant.
It is true that you can calculate manpower.. But you must make sure that CT supports customer demand.
If we get 2.1 as no of manpower required then we need to declare no of manpower as 3 and not 2
No Sarat San.. Do kaizens then
Offcourse, It required 3 Manpower in order to meet customer demand, But it is biggest waste to company. So as an engineer need to KAIZEN to reduce 0.1 manpower.
So the Manual Time + Walking Time is also equivalent to the whole Cycle Time of the process? Am I right?
No dear cycle time is also include auto time...manual time + walking time is the time of operator only. Not machine or whole process
@@RamanPahujaIndustrialEngineer how about the main process + additional steps like putting the products in the bin and getting it from the bin. Is it included as the walking time, since there is no walking included in our process. Thanks
@@khentsaludo5162 additional processes are the manual time.... Which operator do...
@@RamanPahujaIndustrialEngineer ok sir, so if there is no walking or transportation included in the process the formula will be Manual time over Takt Time only? Am I right? Thankd
@@khentsaludo5162 exactly then we will consider walking time as zero
difference between manual time & working time
Praveen Undru it's walking time, not working time
Raman Pahuja Industrial Engineer thank u sir
Most welcome dear