Link Budget and At Completion for not Started Activities | Calculation | settings in Primavera P6

แชร์
ฝัง
  • เผยแพร่เมื่อ 4 ต.ค. 2024

ความคิดเห็น • 7

  • @nadendlabalachandra7455
    @nadendlabalachandra7455 3 ปีที่แล้ว

    Kindly make a video on suspend and resume activities and how many times can we suspend and resume a single activity.

    • @SoftEdemy
      @SoftEdemy  3 ปีที่แล้ว +1

      I will make vedio Mr. Nadendla. For just your information one activity can be suspended and resume one time only in one updated schedule. there are different techniques to handle it. If there is more than one suspension then you have to crush your activity in the upcoming revision and add any delay event to show you delay in that event.Keep commenting it will bring a us closer to the viewers.

  • @SoftEdemy
    @SoftEdemy  3 ปีที่แล้ว

    For any query contact us on our email : info@softedemy.com

  • @HaiderAli-tj4jd
    @HaiderAli-tj4jd ปีที่แล้ว

    Why sometimes after progress update, there is a difference in budgeted units vs at completion units. Even If I checked the Link Button

    • @SoftEdemy
      @SoftEdemy  ปีที่แล้ว

      Because you update the Duration percent or physical percent, You have to update also unit percent. This setting will be applied for only not stated activities. When there will an activity in progress this setting will be not implement. At completion, units are different when you haven't updated the actual units of the activity. Thanks

  • @usmanshani2
    @usmanshani2 3 ปีที่แล้ว

    So what is recommended setting for not started activities.?

    • @SoftEdemy
      @SoftEdemy  3 ปีที่แล้ว

      For Not started it's recommended to check the box. Reset Orignal Duration with remaining is recommended also