How to Assign Relationships to Activities | Primavera P6 | 19.12 | Beginners Tutorial

แชร์
ฝัง
  • เผยแพร่เมื่อ 11 ก.ย. 2024
  • SoftEdemy is latest academy for learning all software’s up to professional level
    #PrimaveraP6, #Relationship, #Activities
    In this video we have discussed about
    Once activities and activity durations have been added in Primavera P6 EPPM, connecting activities with relationships is important for finding the true length of the project. Precedence diagramming is the foundation of these activity relationships. Experienced schedulers thoroughly understand the precedence relationships between Activities enabling them to compute accurate project duration, and also helping them ensure that the project duration is as short as possible
    Previous Videos
    How to Download and Install Primavera P6 |19.12 | 18.8 | Latest Version| Oracle | Free Download
    • Video
    Introduction of Interface | Primavera P6 | 19.12 | 18.8 | Latest 2020
    • Introduction of Interf...
    How to Create Organizational Breakdown Structure | Primavera P6 |19.12 | 18.8 | Latest Version 2020
    • How to Create Organiza...
    How to Create Enterprise Project Structure | Primavera P6 |19.12 | 18.8 | Latest Version 2020
    • How to Create Enterpri...
    Create a Project | Primavera P6 |19.12 | 18.8 | Latest Version 2020
    • How to Create a Projec...
    How to Create and Assign Project Codes| Primavera P6 |19.12 | 18.8 | Latest Version 2020
    • How to Create and Assi...
    How to Create Work Breakdown Structure | Primavera P6 | 19.12 | 18.8 | Latest 2020
    • How to Create Work Bre...
    How to Create Calendar | Primavera P6 | 19.12 | 18.8 | Latest 2020
    • How to Create Calendar...
    How to Create Activity | Primavera P6 | 19.12 | 18.8 | Latest 2020
    • How to Create Activity...
    How to Create and Assign Activity Codes to Activities | Primavera P6 | 19.12 | 18.8 | Latest 2020
    • How to Create and Assi...

ความคิดเห็น • 5