Hi Siva, that is incorrect. At 8:55 in the video, it is mentioned that B can be delayed by 3 days and the project will still be on track. It doesn't mean B becomes 9, B remains 6. Hope that's clear 👍
The difference between early start of the successor activity and early finish of the predecessor activity is known as Free Float. It typically means if you finish early, you will have free time at hand for even the early start of your next activity. In real life projects, for example, if a resource working on an activity with free float wants to go on a leave, you as a Project Manager know that it will not impact the project schedule. You should thus approve the leave. You can check this video to understand how these values are used on real life projects to answer interview questions th-cam.com/video/hNOmnXuG3cI/w-d-xo.html
Check out more videos on the Critical Path Method (CPM) here goo.gl/S6RKCB
Also, check out more Schedule Management videos here goo.gl/sKpxmP
This channel is live saviour for pmp aspirants
Thanks for the good words, Priyanka.
Do share with other PMP aspirants, see you around 🙌
I am so glad that i came across your channel. Your explanation makes it so easy to understand everything. Thank you and well done!!
Hi Punit, You're very welcome! Don't forget to subscribe for more 👍
Very nicely explained. This was the easiest I could find anywhere. Thank you and I am glad I came across your channel :)
Great to hear! Don't forget to subscribe for more 👍🙂
This channel helps me so much!
Thanks for the good words. Don't forget to subscribe for more
Lol, I liked the initial statement you made about the images your designers made... On a serious note, your videos are very helpful
Glad you like them! 😀😀
Sir, which means B has already schedule for 6 days.. after calcuting with critical path now B becomes 6+3 = 9 days ..am I correct sir ??
Hi Siva, that is incorrect. At 8:55 in the video, it is mentioned that B can be delayed by 3 days and the project will still be on track. It doesn't mean B becomes 9, B remains 6. Hope that's clear 👍
Nicely explained. Thanks a lot
Most welcome Dhruvil. Don't forget to subscribe for more 😊👍
Superb explanation.
Glad it was helpful Duminda. Don't forget to subscribe for more :)
Super Explained !!
Thank you, glad you liked it 👍
The article link doesn't work.
Thanks for the callout, the link is fixed 👍
We have Float 5 & free Float 2 of an activity , what does it mean ? How it is used in Project ?
You can refer to this video for explanation of Float and Free Float th-cam.com/video/bChK4u34RD8/w-d-xo.html
Ya sir I have gone through that but I was asked in interview that "What is the use of free Float in the project ? "
The difference between early start of the successor activity and early finish of the predecessor activity is known as Free Float. It typically means if you finish early, you will have free time at hand for even the early start of your next activity. In real life projects, for example, if a resource working on an activity with free float wants to go on a leave, you as a Project Manager know that it will not impact the project schedule. You should thus approve the leave. You can check this video to understand how these values are used on real life projects to answer interview questions th-cam.com/video/hNOmnXuG3cI/w-d-xo.html
Yup thnx
I love it. Thank you so much
You're welcome 😊
You are great, Thank you!
Happy to help! 👍🙂
awesome explanation! thanks
Thanks for the good words appreciate it 😊👍
Does that mean D E and H all can be delayed by 4 days as a group or individually?
All together can’t exceed 4. Putting f=4 for each does imply 12 though.