Two way slab reinforcement details | BBS of slab | Steel quantity calculation | Civil tutor

แชร์
ฝัง
  • เผยแพร่เมื่อ 4 ก.ค. 2024
  • Download our android app for job oriented courses
    clpsheldon.page.link/x3kb In our previous lecture we have calculated the quantity of steel for a one way slab
    Quantity surveying topics compiled PDFs 👇🏻👇🏻
    store.civiltutorofficial.com/
    Subscribe 2nd channel 👇🏻 @Civil Tutor Official
    In this tutorial i have explained briefly how to calculate the quantity of steel for a two way slab
    Before starting the procedure we must know how to identify a two way slab
    If the ratio of longer span to the shorter of a slab is less than 2, the slab is considered as a two way slab slab
    As i already told you that a one way slab is supported on beams on two opposite sides and the loads are carried along the shorter span
    But in case of two way slab the supports are provided along all the dimensions since the loads are carried along both the directions.
    I have illustrated this method with the help of an example
    and at the end of this lecture i have shown you how to prepare the table for BBS of two way slab.
    It should be noted that the spans are to be considered by excluding the width of beam from all the sides.
    #BBS #civiltutor #ErMuyeenMubarak #quantitysurveying
    #barbendingschedule
    Topics covered;
    Bbs of slab
    Bar bending schedule of two way slab
    Two way slab reinforcement details
    Civil engineering technical knowledge
    Quantity surveying topics
    Steel quantity calculation
    Estimation of steel in concrete
    Steel quantity in slab
    Material quantity calculation
    How to calculate materials in slab
    Steel bars in slab
    Weight of steel in slab
    Formula for weight of steel
    Cutting length of main bars in slab
    Cutting length of distribution bars in slab
    Cutting length of top bars in slab
    One way slab reinforcement details
    • One way Slab reinforce...
    Footing reinforcement details
    • Steel quantity calcula...
    Column reinforcement details
    • Quantity of steel in c...
    Cement sand and Aggregate quantity in column
    • Cement sand and aggreg...
    How to calculate the quantity of cement and sand for plastering work 👇🏻
    • How to calculate quant...
    What is 1.54 in concrete? 👇🏻
    • What is 1.54 in concre...
    How to calculate the volume of a cement bag? 👇🏻
    • How to calculate volum...
    AAC BLOCKS VS RED BRICKS 👇🏻
    • AAC Block vs Bricks | ...
    Difference between one way slab and two way slab 👇🏻
    • What is One way slab t...
    What is development length? 👇🏻
    • What is development le...
    Why do we provide cranked Bars?
    • WHY CRANK BARS ARE PRO...
    Basic knowledge for civil engineers 👇🏻
    • Part 1 | Basic knowled...
    Civil engineering animations Playlist 👇🏻
    • Civil Engineering anim...
    Strength of materials Playlist 👇🏻
    • Shear force and Bendin...
    Read complete article about this tutorial here
    civiltutor15.blogspot.com/202...
    Subscribe our youtube channel
    / civiltutor
    Follow civil tutor on Instagram
    / civiltutorofficial
    Follow civiltutor on Facebook
    / civiltutorofficial

ความคิดเห็น • 37

  • @CivilTutor
    @CivilTutor  3 ปีที่แล้ว +10

    @5:20 I forgot to deduct the 45degree bends (2x1d= 2x1x8=16) after applying the formula for cutting length of distribution bar.... The cutting length will be 4.66m....total length will be 98m & total weight 38.7Kg or 38Kg..... Please do the calculations accordingly.... Sorry for the error!

    • @gajjala4837
      @gajjala4837 2 ปีที่แล้ว +3

      You forget one more thing that is D=slab thickness - 2×clear cover -diameter
      That's D=150-50-8= 92
      But you mentioned there D=150-50-8=84
      Sorry for telling this little thing

    • @CivilTutor
      @CivilTutor  2 ปีที่แล้ว +3

      You are right....this has happened due to a typinging error.... Anyways thanks for correcting me! 😊

    • @gajjala4837
      @gajjala4837 2 ปีที่แล้ว +1

      I don't knw one and two slab so I listen carefully.thats why I catch that point sir..

    • @CivilTutor
      @CivilTutor  2 ปีที่แล้ว +1

      You are right....It's 92 (Typing error)

  • @g.rameshpatnaik8699
    @g.rameshpatnaik8699 2 ปีที่แล้ว

    No words to say, Civil guruji🙏🏼🙏🏼🙏

  • @sachin-ry7zr
    @sachin-ry7zr 2 ปีที่แล้ว +1

    Overall great presentation

  • @funny.gaming8388
    @funny.gaming8388 3 ปีที่แล้ว +5

    Extraordinary mind blowing 👍

  • @asgharbadshah5592
    @asgharbadshah5592 3 ปีที่แล้ว +2

    Pls make a video on Mobilisation of Site ? What is mean by Mobilisation of Site ? What it includes ? Who will do Mobilisation on contractor? What are the merits of Mobilisation

  • @karunakarpuli6356
    @karunakarpuli6356 2 ปีที่แล้ว

    Sir excellent 👌 sir beautiful knowledge for civil engg sir please make video on BBS of staircase with example please as soon as early sir thank you so much sir

  • @muthukumaranrkalaiselvim3154
    @muthukumaranrkalaiselvim3154 3 ปีที่แล้ว +2

    Excellent presentation. Please keep it up

    • @CivilTutor
      @CivilTutor  3 ปีที่แล้ว +1

      Thank you! 😊

  • @ogwangoluka1760
    @ogwangoluka1760 2 ปีที่แล้ว

    In Ugandan we use maxpan in slab so I'm appealing to include in your calculations.

  • @imranhusain88
    @imranhusain88 ปีที่แล้ว +1

    Sir Top extra bar in L/4 (main bar at double spacing) in midle part is not mentioned.

  • @UdaykumarmM-lr8yj
    @UdaykumarmM-lr8yj 19 วันที่ผ่านมา

    Sir in two way slab ,during cutting length of distribution bars the bends are not deducted in calculation please check once and verify the cutting length of distribution bar.

  • @guydedje6378
    @guydedje6378 ปีที่แล้ว

    Could you please illustrate how you get the cutting length of bars or indicate a simple pdf sketch? Thanks in advance .

  • @reshmaramesh7363
    @reshmaramesh7363 ปีที่แล้ว

    Soooper 😍

  • @Mr61303103013
    @Mr61303103013 4 หลายเดือนก่อน

    ❤❤❤❤

  • @oooooo-rt5km
    @oooooo-rt5km 3 ปีที่แล้ว +2

    Nice fabulous ❤️❤️❤️

    • @CivilTutor
      @CivilTutor  3 ปีที่แล้ว +1

      Thank you! 😊

  • @learncivilengineering2927
    @learncivilengineering2927 2 ปีที่แล้ว

    sir cutting length of main bar 2ld i cant understand that sir

  • @dhrumilmistri5066
    @dhrumilmistri5066 2 ปีที่แล้ว +1

    Why 1× incline length...?
    What is 1?

  • @amritpalsinghsehjra7959
    @amritpalsinghsehjra7959 2 ปีที่แล้ว +2

    is it according to indian standards?

  • @bakiyarajkaliyaperumal8938
    @bakiyarajkaliyaperumal8938 8 หลายเดือนก่อน

    mistake at distribution bar cutting length didn't minus the 45°bend ×2

  • @ch.__Sr
    @ch.__Sr 8 หลายเดือนก่อน

    2 way all main bars sir,... Distribution bars not use...

  • @khajagazanfaroz3465
    @khajagazanfaroz3465 2 ปีที่แล้ว

    Pdf is lifetime or any month limit

    • @CivilTutor
      @CivilTutor  2 ปีที่แล้ว

      You can keep it for lifetime 😊

  • @ataullahsiddiqui5142
    @ataullahsiddiqui5142 2 ปีที่แล้ว

    @4:00 Sir D= Slab thickness- 2*side cover - dia of bar
    D=150-50-8=92 ( Distribution bar)
    U wrote 84 please see it Sir

    • @CivilTutor
      @CivilTutor  2 ปีที่แล้ว +1

      That might be a typing error.... I will rectify it.
      Thanks and Regards!

    • @ataullahsiddiqui5142
      @ataullahsiddiqui5142 2 ปีที่แล้ว

      Okay Sir thanks

  • @sscreation1629
    @sscreation1629 3 ปีที่แล้ว +1

    Where is extra top rods...

    • @CivilTutor
      @CivilTutor  3 ปีที่แล้ว +1

      Watch complete video

  • @muthuprakasam2806
    @muthuprakasam2806 ปีที่แล้ว

    Main bar is shorter bar but you put longer bar

    • @CivilTutor
      @CivilTutor  ปีที่แล้ว

      In two way slabs main bars are provided along both the sides.