Import Cost from excel to primavera 6

แชร์
ฝัง
  • เผยแพร่เมื่อ 14 ก.ค. 2024
  • Did you like this Video? Join us in Planning Engineer Website where we have specialized training courses for planning and scheduling. courses link: bit.ly/2yVJ3z2
    How to import budget cost from excel to primavera and avoid common mistakes.
    ---------------
    Keep in Touch:
    Join our email Newsletter, we send useful free content regularly: planningengineer.net/newsletter/
    WhatsApp: +201277767728
    Email: Info@PlanningEngineer.Net
    Linked in: / planning-engineer-est
    FaceBook Page: / planningengineerdotnet
    FaceBook Group: / 1138400132963230
    Twitter: / planningeest
    Instagram: / planningengineerest
    ---------------

ความคิดเห็น • 32

  • @motorcycle.journal
    @motorcycle.journal 4 ปีที่แล้ว +1

    Helpful video, thanks for sharing.

  • @peterharbman
    @peterharbman 7 ปีที่แล้ว +1

    Good job! This is very helpful. So updating the budgeted units updates the budgeted cost.

  • @ahmedayoub8105
    @ahmedayoub8105 2 หลายเดือนก่อน

    Very Excellent 🌺🌹

  • @mothilalkanagaraj7820
    @mothilalkanagaraj7820 8 ปีที่แล้ว

    Thanks - i did and complete my job

  • @318482
    @318482 9 ปีที่แล้ว

    Omar , you need to go to your setting in resource and select unit and change it to 1 instead of 8 per hour and also make sure your max uni is 1

  • @magedmetry6575
    @magedmetry6575 3 ปีที่แล้ว

    thanks too much for the review and valued information

  • @muthuxs
    @muthuxs 5 ปีที่แล้ว

    Very Nice regd MuthuPMP

  • @aminalmosharaf9675
    @aminalmosharaf9675 3 ปีที่แล้ว +2

    very nice

  • @racielbautista6510
    @racielbautista6510 6 ปีที่แล้ว

    Hi, I believe that you should order the ID activities for copy the dates

  • @318482
    @318482 9 ปีที่แล้ว

    Hello , In order to avoid changing duration you need to go to the project before assigning resource and in resource setting , uptick Drive activity be default

  • @benaragon12
    @benaragon12 6 ปีที่แล้ว

    So do you add an additional resource (CostPlanning) on top of the resource that is aleady assigned? Or can you use the reosurce that ois already in there?

  • @serkanbal847
    @serkanbal847 9 ปีที่แล้ว +1

    Omar, probably your resource isnt "material" resource type. then it multiples with 8 hours.

  • @MUHAMMADQASIM-kk1ts
    @MUHAMMADQASIM-kk1ts 8 ปีที่แล้ว

    Hello! i am a young planner and i have a couple of questions regarding this topic;
    1. Would you please elaborate the difference between the expense loaded from BOQ and the cost loaded for resources.

  • @STCRM78
    @STCRM78 6 ปีที่แล้ว

    Hello, nice work! Congratulations!!
    Please, let me ask you this: In your excel file "WBS-Activity-List-Full.xlsx"
    Q1. What is the complete name of the cell A3 ("BOQ..?")? And what it is referred to those letters ("A, B, C", etc)?
    Q2. What information do you have in the column B, "DIV"? Why is it useful?
    Thank you!

  • @fas-yt765
    @fas-yt765 9 ปีที่แล้ว

    i got a better idea by watching this

  • @AK2Auburn
    @AK2Auburn 8 ปีที่แล้ว

    Is there any reason you wouldn't want to do this with something as simple as the default "budgeted total cost" or something like that?

  • @carlodigma5128
    @carlodigma5128 3 ปีที่แล้ว

    Hello, Thanks for the information again, but why when I export from p6 to excel the arrangement of activity ID was not in order, Do I need to fix the save excel before importing to P6. Its says the application has been intercepted please note the event code for reference. Event code TP CAT-3080-C. Thanks and God bless.

  • @OmarShahin.
    @OmarShahin. 10 ปีที่แล้ว

    When im importing the budgeted total cost , the budgeted total cost in primavera is multiplying by 8 i dont know why ? Please help . Thank you

  • @albertthomas398
    @albertthomas398 7 ปีที่แล้ว

    But, is this the right way to add cost to activities? Typically it has to be by adding labor / material / Expenses to each activity. And that will drive the cost of the activities.

  • @rajeshsukumar1087
    @rajeshsukumar1087 4 ปีที่แล้ว +1

    hi ,i need a help ,when iam importing an excel file to primavera iam geting an error message that "The User Preferences used to create this Excel file are not the same as your current preferences. Importing this file could corrupt your data"

    • @qobla_worgbah
      @qobla_worgbah 4 หลายเดือนก่อน

      Am getting the same message ,when i try importing same.Any Help

  • @archiemaddy5122
    @archiemaddy5122 9 ปีที่แล้ว +2

    My budgeted cost shows 0 after importing. Please help.

  • @colleeno4929
    @colleeno4929 7 ปีที่แล้ว +1

    When I get to the end of this video, at time 6:51 when I try to import from excel to Primavera, I do not have any options for Projects to import to. Does anyone know how to remedy this?

    • @MrAgummer
      @MrAgummer 7 ปีที่แล้ว

      you need to be an administrator on the OBS for that project.

    • @adacorte1
      @adacorte1 7 ปีที่แล้ว

      Co

  • @muhammadsarkar4778
    @muhammadsarkar4778 3 ปีที่แล้ว

    Brother, How can I get all of your lessons?

  • @jechp1344
    @jechp1344 3 ปีที่แล้ว

    It does not work with decimals... Any suggestion?

  • @nisanthchaithanyasasidhara8697
    @nisanthchaithanyasasidhara8697 6 ปีที่แล้ว

    How to import manhours from excel to primavera

  • @ahmadaltayeb1983
    @ahmadaltayeb1983 ปีที่แล้ว

    Dear Sir
    I had a problem in Primavera P6, the problem is Performance % Complete and Schedule % Complete, can not roll up to Project level, but it is already rolling up to WBS Level, and please note that I already assign materials on activities.
    Please anyone can give advice, to solve this problem, I use Ver. 19.12 and Ver. 21.12.
    Thanks

  • @sohambandyopadhyay1911
    @sohambandyopadhyay1911 6 ปีที่แล้ว

    The moment I assign a 0 bugeted hour resource , all durations come to 0